170 likes | 384 Views
CF MEP Commissioning. CF Commissioning Plan. Commissioning Plan (CP) developed by Jacobs Facilities (Engineer of Record) Title II project deliverable Reviewed and approved by LCLS CF Eng group leader – Javier Sevilla
E N D
CF Commissioning Plan • Commissioning Plan (CP) developed by Jacobs Facilities (Engineer of Record) • Title II project deliverable • Reviewed and approved by LCLS CF Eng group leader – Javier Sevilla • CP includes a comprehensive list of field deliverables and requirements that meet expectations of LCLS • Administration • Detailed scope of Commissioning work • Quality Control Plan • Testing and Training Schedule • Field • Plumbing and Fire Protection Systems • Mechanical Systems • Electrical Systems • Elevator and Crane Systems • Demonstration and Testing • CP managed by 3rd party subcontractor, independent of trades and Turner, hired by LCLS
Commissioning Areas • Beam Transport Hall – • Undulator Hall • Near Experimental Hall/Central Utility Plant/12Kv Substation • Far Experimental Hall – • Electron Beam Dump • Front End Enclosure • X-Ray Transport & Diagnostics Tunnel
BTH Looking East Ductwork SB 2.3 Storage tank for runoff water from tunnels AHU Drawings M4201 A2200
HVAC ducting NEH Cross Section M4602
CUP Plan View Drawing M0203 Boilers Chillers Mech Room-NEH Electrical Rm
Title II-IFC Two Chillers (425 tons/ea), Primary and Secondary CHW loops and Pumps BTH,UH,EBD,FEE, NEH and FEH One Boiler (150 BHP/ea) Primary and Secondary HW loops and pumps DDC Temperature Control System to be connected to SLAC network via Web Control One Air Compressor (268 SCFM@150psi), Air Dryer and Receiver. Will provide service to: BTH, UH, EBD, FEE, NEH,X-RAY, FEH Wet Sprinkler System-Ordinary Hazard Group 1 One AHU for electrical room Mechanical room for NEH HVAC system (MAU) CENTRAL UTILITY PLANT (CUP)
Substation 522-Phase I CUP S522
CP Procurement • Based on early estimates, budget was established at $350K • Bids were solicited Aug 07 for CxA (Commissioning Agent) • 5 CxA bidders invited • 4 bidders responded and all 4 were within budget! • Technical evaluation by CF group is complete • Weighted point score • Awarded to Engineering Economics Inc (EEI) at $229K
CxA • Engineering Economics Inc (EEI) • Offices nationwide and able to shift resources if necessary, although not likely • Commissioned over 33 million sf • Data centers • Medical research labs • Pharmaceutical labs • Federal facilities • LCLS Sector 20 Injector Facilities - successful • LCLS Magnetic Measurement Facilities - successful
Summary • Roles and responsibilities are clear • Expectations are documented and well understood • CxA will be assigned to work with trades, SLAC Facilities maintenance staff and LCLS CF Engineering group • Goal is to deliver a complete and functional project with all MEP systems fully operational, inspected, tested, verified and documented