sPHENIX DOE-SC CD-1/3A Review RLS Schedule Development Rich Grubb May 23-25, 2018 BNL
sPHENIX P6 development 13 Microsoft Project files • P6 Integrated Master Schedule • Validated matching to MS Project plan • Identified completed work vs work to-go • Implemented cost reduction • Implemented expanded FY18 R&D phase Aug 2017 • Project Manager’s schedule work fest • All L2 managers and Project Estimators worked in the P6 schedule with Project Controls and improved the work plan. Validated estimate data and project coding. sPHENIX DOE-SC CD-1/3A Review
How costs are shown in reports • Escalated (Esc) equals At Year (AY) = Direct + Burden + Escalation • Total Burdened Esc $ • = Direct + Burden + Escalation • Escalated (Esc) equals At Year (AY) • Direct $ • Labor includes fringe • Nonlabor units is budgeted value of contracts and/or purchase orders Example P6 Activity Report sPHENIX DOE-SC CD-1/3A Review
Tips for Cost Book summary data sPHENIX DOE-SC CD-1/3A Review
Tips for Cost Book detail • Resource level (white rows) is the detail shown • May have many resources to one activity • Highlighted rows are summary • Time phase data is period units or cost. The column title of the column prior to the first period indicates the data type sPHENIX DOE-SC CD-1/3A Review
P6 data tables • Project • Activities • Activity Coding • Resource Assignment • Resource Assignment coding • Resource • Global Codes • Added P6 fields prefixed by • “BNL_” activity code fields • “BNL_UDF” activity user defined fields • “BNL_Res” resource code fields • “BNL_RAU” resource assignment user defined fields sPHENIX DOE-SC CD-1/3A Review
Attribute Coding sPHENIX DOE-SC CD-1/3A Review
P6 Resource Table Project is using 73 resources: 68 Labor 5 Nonlabor sPHENIX DOE-SC CD-1/3A Review
BNL Finance source of resource rates Project base year = FY17 sPHENIX DOE-SC CD-1/3A Review
Open Ends • Activities without predecessors..................................8 • Project: POM02B_J Activity: S100010 Approve Mission Need CD-0 • Project: POM02B_J Activity: S100400 CD-1 Review • Project: POM02B_J Activity: S100600 CD-3a Budget Appropriation • Project: POM02B_J Activity: S100800 CD-2/3 Review • Project: POM02B_J Activity: S101008 FY18 funding available • Project: POM02B_J Activity: S101009 FY19 funding available • Project: POM02B_J Activity: S101010 FY20 funding available • Project: POM02B_J Activity: S101015 FY21 funding available • Activities without successors....................................7 • Project: POM02B_J Activity: S100200 Prepare for CD-1 Review • Project: POM02B_J Activity: S100700 Prepare for CD-2/3 Review • Project: POM02B_J Activity: S100900 Transition to CD2/3 • Project: POM02B_J Activity: S101008 FY18 funding available • Project: POM02B_J Activity: S101040 Approve Project Closeout CD-4 • Project: POM02B_J Activity: S247500 Oversight of sPHENIX Digitizers Procurement • Project: POM02B_J Activity: S318540 Start of RHIC Run 30-Jan-23 A Fuse Analysis of the schedule has been prepared and is available for Review. sPHENIX DOE-SC CD-1/3A Review
Integration/Summary • Integration with other management tools • P6 data is the source • P6 to Cobra wizard • Cobra is the earned value cost processor • P6 & Cobra used to set the Performance Measurement Baseline (PMB) • Monthly status cycle • Collect status and ETC information prior to end of month in P6 • Import status with wizard from P6 to Cobra • Import of project actuals data from Peoplesoft Financials into Cobra • Post schedule and earned value reports for project team • Project Resource Loaded Schedule well developed for CD-1. sPHENIX DOE-SC CD-1/3A Review