March 2003 Operations Summary

March 2003 Operations Summary. Bill Blevins Manager Operations Engineering. March 08 to March 09 Comparison. March 2008 Wind Capacity ~ 5,000 MW Load 22,700,794 MWH #Outage Gen 419 #Outage Trans 2216 March 2009 Wind Capacity ~ 8,000 MW Load 22,150,823 MWH # Gen Outage 466

Download Presentation

March 2003 Operations Summary

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. March 2003 Operations Summary Bill Blevins Manager Operations Engineering

  2. March 08 to March 09 Comparison • March 2008 • Wind Capacity ~ 5,000 MW • Load 22,700,794 MWH • #Outage Gen 419 • #Outage Trans 2216 • March 2009 • Wind Capacity ~ 8,000 MW • Load 22,150,823 MWH • # Gen Outage 466 • # Trans Outage 2575 Meeting Title (optional)

  3. Comparison 2008-2009 Meeting Title (optional)

  4. Top March Congestion items Meeting Title (optional)

  5. ERCOT Stability IROLs

  6. NERC Criteria • FAC-11 • R3.3. A process for determining which of the stability limits associated with the list of multiple contingencies (provided by the Planning Authority in accordance with FAC-014 Requirement 6) are applicable for use in the operating horizon given the actual or expected system conditions. • FAC-14 • R6. The Planning Authority shall identify the subset of multiple contingencies (if any), from Reliability Standard TPL-003 which result in stability limits. • R6.1. The Planning Authority shall provide this list of multiple contingencies and the associated stability limits to the Reliability Coordinators that monitor the facilities associated with these contingencies and limits. • R6.2. If the Planning Authority does not identify any stability-related multiple contingencies, the Planning Authority shall so notify the Reliability Coordinator. Meeting Title (optional)

  7. TPL-003 Multiple Contingency Criteria Meeting Title (optional)

  8. TPL-003 Multiple Contingency Criteria continued Meeting Title (optional)

  9. Standard TOP-007-0 — Reporting SOL and IROL Violations • R2. Following a Contingency or other event that results in an IROL violation, the Transmission Operator shall return its transmission system to within IROL as soon as possible, but not longer than 30 minutes. • R3. A Transmission Operator shall take all appropriate actions up to and including shedding firm load, or directing the shedding of firm load, in order to comply with Requirement R2. • R4. The Reliability Coordinator shall evaluate actions taken to address an IROL or SOL violation and, if the actions taken are not appropriate or sufficient, direct actions required to return the • system to within limits. Meeting Title (optional)

  10. Market tool for Zonal Balancing Deployments MARKET Flow Time 22:00 Current Time 2145 Meeting Title (optional)

  11. Voltage Stability Limit in ERCOT identified as an IROL • The interface for the North to Houston includes the four 345 KV lines • Jewett to TH Wharton • Jewett to Tomball • Gibbons Creek to O’Brien • Roans Prairie to Kuykendahl Meeting Title (optional)

  12. West to North Dynamic Stability • Six 345kv transmission lines are measured and defined as the West North Dynamic Stability limit interface. • These six 345kv transmission lines are: • Mesquite to Graham (measured as entering Graham) • Sweetwater to Graham (measured as entering Graham) • Morgan Creek to Graham (measured as entering Graham) • Bowman to Graham (measured as leaving Bowman) • Bowman to Jacksboro SS (measured as leaving Bowman) • Red Creek to Comanche (measured as entering Comanche SS) Meeting Title (optional)

  13. ERCOT Information Available to Particpants • North to Houston Voltage • West to North Dynamic Stability

  14. Day Ahead Meeting Title (optional)

  15. Voltage Stability Meeting Title (optional)

  16. Messages Operations Post Real-Time Meeting Title (optional)

  17. CSC Calculator Results Meeting Title (optional)

  18. Real-Time Flows Meeting Title (optional)

  19. VSAT Results Meeting Title (optional)

  20. Info Operations Post After the fact Meeting Title (optional)

  21. March 29 information Meeting Title (optional)