The Hyatt Regency Walkway Collapse

The Hyatt Regency Walkway Collapse. Presented By: Jonathan Foster 4/9/02. An Engineering Disaster. Kansas City, Missouri - 1981. July 17, 1981. Approximately 2000 People Came for a Dance Competition At 7:05 pm a large crack was heard and two walkways collapsed

ilario
Download Presentation

The Hyatt Regency Walkway Collapse

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Hyatt Regency Walkway Collapse Presented By: Jonathan Foster 4/9/02

  2. An Engineering Disaster Kansas City, Missouri - 1981

  3. July 17, 1981 • Approximately 2000 People Came for a Dance Competition • At 7:05 pm a large crack was heard and two walkways collapsed • Leaving 114 Dead and Left over 200 injured

  4. Gillum-Colaco International Inc. (G.C.E. Inc.) Proposed Design for the Walkways • wide flange beams were to be used on either side of the walkway which was hung from a box beam • a clip angle was welded to the top of the box beam which connected to the flange beams with bolts • one end of the walkway was welded to a fixed plate while the other end was supported by a sliding bearing • each box beam of the walkway was supported by a washer and nut which was threaded onto the supporting rod

  5. Proposed Design

  6. The Revised Design • one end of each support rod was attached to the atrium’s roof cross beams • the bottom end went through the box beam where a washer and nut were threaded on • the second rod was attached to the box beam 4" from the first rod • additional rods suspended down to support the other levels in a similar manner

  7. Actual Design

  8. The Fourth Floor Connection

  9. Reasons For Disaster • Lack of Communication • Interpreting Preliminary Drawings as Finalized Drawing • Insufficient Review of the Final Design