COCHIN INTERNATIONAL AIRPORT LIMITED. CIAL-A PATHBREAKER. Cochin International airport, the country’s first Greenfield airport built under public private partnership is a trendsetter in aviation infrastructure development.
E N D
CIAL-A PATHBREAKER • Cochin International airport, the country’s first Greenfield airport built under public private partnership is a trendsetter in aviation infrastructure development. • The unique rehabilitation package, the astonishing public participation and a sustainable business model have made CIAL a path breaker
UNIQUE ARCHITECTURE The airport, featuring Kerala’s typical architecture is unique
CREDENTIALS • Over 5 million passengers a year • 47072 aircraft movements • 54440 tons of cargo • CIASL- Aviation Services Limited • CIAL Infrastructure limited • 18 hole golf course • Aviation security training academy
NEW INTERNATIONAL TERMINAL CIAL is gearing up to take new challenges in passenger traffic growth as its dream project is about to set in. Chief minister Mr.Oommen Chandy laid the foundation stone of the new international passenger terminal on feb 1.
SALIENT FEATURES • Two level terminal-Arrival in ground level • Departure in first level
SALIENT FEATURES Finger pier concept to handle 13-15 aircrafts through aerobridges during peak operations
SALIENT FEATURES • Elevated road approach to departure level • Parking area with a capacity of 3000 cars
SALIENT FEATURES Departure level 2 • Covered road/ Kerb area of 3 lakh sft- 3+3+2 lane traffic • 56 check in counters with provision for additional 56 • 48 immigration counters • 10000 sft duty free shop • 13 security gates
SALIENT FEATURES Departure level 3 • 2 food courts • 4 premium lounges
SALIENT FEATURES Arrival level-1 • Connectivity to departure for transit passengers at arrival corridor • Connectivity to remote arrival • 50 immigration counters • Aquarium, vertical garden, hanging installations, murals
SALIENT FEATURES Arrival level-0 • 20000 sft duty free shop • 6 conveyor belts • 18000 sft passenger exit lounge with 2 main exit points • Visitors waiting area and related concessionaries • Meet and greet area
Cost of the project & period for completion • Us $ 150m( Rs. 8500 m) • The terminal will have a built up area of 15 lakh sft. It will have a peak hour capacity of 4000 passengers. • The project is expected to be completed in 24 months.