William A. Daigneau Operations & Facilities Management Vice President, Chief Facilities Officer

“Here We Grow Again!” Managing Growth at M. D. Anderson Cancer Center. William A. Daigneau Operations & Facilities Management Vice President, Chief Facilities Officer CMAA Owner’s Forum May 3, 2010. Title. Growth Over 10 Years FY 1999 – 2009. Title. North Campus. Mid-Campus.

irisa
Download Presentation

William A. Daigneau Operations & Facilities Management Vice President, Chief Facilities Officer

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. “Here We Grow Again!” Managing Growth at M. D. Anderson Cancer Center William A. Daigneau Operations & Facilities Management Vice President, Chief Facilities Officer CMAA Owner’s Forum May 3, 2010

  2. Title

  3. Growth Over 10 Years FY 1999 – 2009

  4. Title North Campus Mid-Campus South Campus East Campus

  5. M. D. Anderson Cancer Center North Campus

  6. What We’ve Built 2 Hospitals (including surgery, GMP facilities) 4 Outpatient Clinics 6 BioMedical Research (up to BSL-3, GLP’s) 3 Vivaria 4 Office Buildings 2 Hotels 3 Data Centers 2 Warehouse 4 Parking Garages 3 Imaging (Cyclotrons, PET, MR, etc.) 3 Treatment Centers (Proton/Linear Accelerators) 4 Conference Centers w/ TeleMedicine 2 Freezer Farms 1 Blood Bank Plus roads, central plants, parks, underground utilities (sewer, water, fiber, retention) Equal to adding a 600k GSF building every year for 15 straight years, totaling $4 billion

  7. How We Built It • Hard Bid Lump Sum • CSP • CM at Risk • Design-Build • Job Order Contract • Multiple Contracts • Third Party, w/ and w/o Equity Involvement • Greenfield • Constrained Site • High and Low Rise • Steel and Concrete • New Construction and Renovation

  8. How We Managed It • • 125 person in-house PDC management group • • Agile processes • Mall developers • Toyota • Lean • Standard modules/kit of parts • • Project organization/decision-making • • Trust but verify - documentation • • Building relationships - fairness • • Advance planning

  9. What We Learned • Project and situation - determine best delivery method • Contracts - read only when disputes arise • Contract terms – have multiple interpretations • Project success - directly related to team member quality, commitment • Project schedules - run by hope and prayer • Teamwork - direct function of who’s making, losing money

  10. Issues in the Industry • Construction quality - too much rework • Subcontractor management expertise • Adoption of Lean concepts • Educating Owners (www.coaa.org) • Greater standardization & transparency

  11. Questions?