Bridge Projects. PCEF Meeting Dover, DE Aug 25, 2009. Troy M. Jenkins, P.E. Chief Engineer Northeast Prestressed Products, LLC. PCEF – Bridge Projects by State. PA : 20 Bridges 471 Beams DE : 1 Bridge 14 Beams MD : 11 Bridges 106 Beams NJ : 3 Bridges 80 Beams
E N D
Bridge Projects PCEF Meeting Dover, DE Aug 25, 2009 Troy M. Jenkins, P.E. Chief Engineer Northeast Prestressed Products, LLC.
PCEF – Bridge Projects by State • PA : 20 Bridges 471 Beams • DE : 1 Bridge 14 Beams • MD : 11 Bridges 106 Beams • NJ : 3 Bridges 80 Beams • NY : 11 Bridges 165 Beams • VA : 5 Bridges* 676 Beams • MA : 6 Bridges 101 Beams • RI : 2 Bridges 35 Beams • CT : 1 Bridge 12 Beams *582 beams listed as one bridge project.
PA Bridges • Alternate Designs: 6 Bridges – 255 Beams • Latest Alternate Project: • 4 Contractors Bid Concrete Alternate • 0 Contractors Bid Steel As-Designed • Contract price $101,558,000 • Bridge price $ 56,487,262 • Design Build : 3 Bridges – 96 Beams Latest Design Build: Contract Price Bridge Price • PCEF Solution – $16,280,860 $7,008,800 • Steel Solution – $17,697,000 $8,204,498 Savings $ 1,416,140 $1,195,698 • Work In Progress: Splice Girder Standard • Starting with Simple Span designs.
Other Projects • KY – 3 Span Box Beam – 132ft Radius • CT – PCEF Beams = NEBT • Full Depth Precast Deck Panels • MA – 3 Span Splice Girder (PCEF)