Ensuring Long Term Success of Indian PV Projects

Ensuring Long Term Success of Indian PV Projects. PV Module quality and reliability- Securing Yields from PV Installations. WHAT’S ON TODAY’S AGENDA?. Q-CELLS AT A GLANCE THE IMPORTANCE OF ROOFTOPS IN INDIA 3. KEY CHALLENGES IN ROOFTOP MARKET IN INDIA SUMMARY.

Download Presentation

Ensuring Long Term Success of Indian PV Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ensuring Long Term Success of Indian PV Projects PV Module quality and reliability- Securing Yields from PV Installations

  2. WHAT’S ON TODAY’S AGENDA? • Q-CELLS AT A GLANCE • THE IMPORTANCE OF ROOFTOPS IN INDIA • 3. KEY CHALLENGES IN ROOFTOP MARKET IN INDIA • SUMMARY

  3. WHAT’S ON TODAY’S AGENDA? • Q-CELLS AT A GLANCE • THE IMPORTANCE OF ROOFTOPS IN INDIA • 3. KEY CHALLENGES IN ROOFTOP MARKET IN INDIA • SUMMARY

  4. Q-Cells: The world’s leading institutions in Photovoltaic technology • A German Public Company, operating since 1999 • Deployment of 3 GWp PV components around the world • Among the leading system integrators in the world (>521 MWp) • #1 in Europe in terms of production volume and revenue • Leading Technology Brand, trusted across the world 1 2 a leader in the world of photovoltaics 3 4 5 6 About the picture: 91 MWp, Briest, Germany EPC by Q-Cells Construction time: 8 weeks

  5. Our Products are based on solid research and exhibit technology leadership • Monolythic serial production • Efficiency record out of development: 17.4% (AP) • Efficiency of 17.8 % (AP) • Efficiency of 18.5 % (AP) • each with 60 cells solar module • Efficiency Record on multi: 19.5 % • Efficiency Record on mono: 20.2% • Crystalline cells • CIGS thin film solar module • Crystalline solar module

  6. WHAT’S ON TODAY’S AGENDA? • Q-CELLS AT A GLANCE • THE IMPORTANCE OF ROOFTOPS IN INDIA • 3. KEY CHALLENGES IN ROOFTOP MARKET IN INDIA • SUMMARY

  7. Rooftop market is the most common form of PV power in developed markets of PV About the picture: Q-Cells modules at a typical Installation in Japan Source: QC Research Source:1. BSW, 10/2008 2. Photon 05/2010

  8. The roof top PV market becomes important for several reasons: #1 Avoid Transmission costs (& loss) About the picture: Q-Cells modules at a typical Installation in Germany EXAMPLE: GERMANY Source: QC Research About the picture: Q.SMART UF L reference Affi, Verona, Italy 686 kWp of Q.SMART UF L 100 W C&I Carport solution Completion: March 2011

  9. The roof top PV market becomes important for several reasons: #2 Reduce Diesel Consumption Source: QC Research Source:1. BSW, 10/2008 2. Photon 05/2010

  10. The roof top PV market becomes important for several reasons: #3 Self consumption of PV About the picture: Q-Cells installation at Chanyakapuri, New Delhi

  11. The roof top PV market becomes important for several reasons: #4 Green Buildings & BIPV About the picture: A C&I facade Installation of Q.SMART Location: Mels, Switzerland 14.2 kWp of Q.SMART Completion: April 2011

  12. WHAT’S ON TODAY’S AGENDA? • Q-CELLS AT A GLANCE • THE IMPORTANCE OF ROOFTOPS IN INDIA • 3. KEY CHALLENGES IN ROOFTOP MARKET IN INDIA • SUMMARY

  13. Issue #1:Choosing technology at is a important design criteria On a flat roof, Q.SMART generates 80% of its maximum yield  c-Si only 69% Less mounting structure needed, i.e. optimal utilization of roof surface

  14. Technology differences under roof orientation conditions About the picture: Residential facility Braunfels, North 45° Germany

  15. Issue #2: Minimizing shading is a important design criteria Q.PRO 60 cells connected in series 3 strings of 20 cells, each string protected by Bypass diode Q.SMART UF L 119 cell stripes connected in series and protected by Bypass diode

  16. Issue #2: Minimizing shading is a important design criteria CRYSTALLINE MODULE (e.g. Q.Pro) Q.SMART UF L • Cells in every string shaded  output zero • 2 of 3 strings affected  output reduced by 2/3 • More than one cell stripe shaded  Output zero • Output depends on shaded area

  17. Rooftop systems need to minimize shading About the picture: A typical mapping tool in Australia About the picture: A mapping for Delhi, India

  18. Issue #3: Maximizing total yields requires detailed site analysis About the picture: \ Q.FLAT system ILIOTEC – REGENSBURG – 252 kWp

  19. Detailed Site Analysis was a corner stone of the Q-Cells installation at New Delhi Marking mounting structure location Laser alignment Shading analysis in Software Mounting structure Installation Structure Commissioned Creating cement blocks Module Installation c-Si Installation done Thin film Installation done A High Quality 10.47 kWp rooftop with weather station and Remote monitoring was done in 25 days

  20. The IGCC PV project plays a role in the chain of world wide tests being conducted by Q-Cells • INDIA – New Delhi 10.47 KWp • QBASE, QSMART UFL

  21. Issue #4: It is known that PV Modules have to be robust in hot climates & with high moistures About the picture: 5.5 MWp Q.SMART Solar Mission project at Jodhpur About the picture: 150 kWp rooftop at Schindler, flat-roof North 2°, Germany * Modified from Solar Energy Centre at SolarCon 2010

  22. Issue #4: It is known that PV Modules have problems in hot climates & with moistures • Case Study: A Solar Energy Centre study of modules from eleven PV manufacturers from 1999-2010 • Degradation between 32% - 8% • Out of 11 manufacturers, 8 showed major degradation • Only 3 manufacturer module limits were ≤ 10% • Failure of modules due to • Junction Box detachments • Corrosion of terminals • Hot Spots * Source: 1.Solar Energy Centre at SolarCon 2010

  23. Issue #4 It is known that PV Modules have problems in hot climates & with moistures ! Fact: It could be worse with modules with Tier-2,3 manufacturers Source: An extract from a warranty clause from a Tier-1 Chinese cSi module manufacturer

  24. WHAT’S ON TODAY’S AGENDA? • Q-CELLS AT A GLANCE • THE IMPORTANCE OF ROOFTOPS IN INDIA • 3. KEY CHALLENGES IN ROOFTOP MARKET IN INDIA • SUMMARY

  25. SUMMARY • Rooftop installations should be an important segment to the PV installations in India • Grid-parity for residential segment knocks at the doors • Not every rooftop in India is suitable for a rooftop PV system • Qualiity matters : Robust modules & quality systems is the need of the hour for Indian PV projects.

  26. THANK YOU. THANK YOU. Visit us at: Booth #R1 For details, please contact: Q-Cells Systems India Private Limited, Registered Office: Level 9, Raheja Towers, 26-27 MG Road, Bangalore 560 001,   INDIA

  27. Observations in India have also confirmed that unlike IEC tests, C-Si modules do not behave uniformly • A long term testing was conducted by SEC (Gurgaon) on 11 PV manufactures • HIGH PERFORMANCE DEGRADATION UP TO 32% OBSERVED • MINIMUM DEGRADATION < 8% IS ALSO OBSERVED • OUT OF 11 MANUFACTURER 8 OF THEM SHOWED MAJOR DEGRADATION • ONLY 3 MANUFACTRERS MODULE WERE UNDER ACCEPTABLE LIMITS ≤ 10% • 2. There were several failure modes of the modules • -TERMINAL BOX DETACHMENT • -TERMINAL CORROSION, • -BY PASS DIODE FAILURES, AND • -BURNING SPOTS Source: Solar Energy Centre (Gurgaon), SolarCon 2010

  28. The “VDE Quality Tested (VQT)” process involves stringent product checks that are well beyond IEC tests More intense tests performed

  29. A Single Line Diagram of the IGCC installation, depicting Solar energy injection to building Diesel Generator PANEL 2 40 A MCB SPV1 Inverter 1 Energy counter 1 40 A MCB Energy counter 2 Inverter 2 250 A Bus bar SPV2 PANEL1 250 A T.P. 250 A T.P. Incoming mains connection Mains 415 V 250 A Bus bar

  30. A two month study: benefits of the system documented so far (more to come)

  31. A two month study: benefits of the system documented so far (more to come)