1 / 23

Contractor Alternate Design

Contractor Alternate Design. Serving the Public’s Best Interest. Development / Building Phases. Project Planning. Development / Building Phases. Project Planning Prioritizing / Programming. Development / Building Phases. Project Planning Prioritizing / Programming Preliminary Design

isla
Download Presentation

Contractor Alternate Design

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Contractor Alternate Design Serving the Public’s Best Interest

  2. Development / Building Phases • Project Planning

  3. Development / Building Phases • Project Planning • Prioritizing / Programming

  4. Development / Building Phases • Project Planning • Prioritizing / Programming • Preliminary Design • Needs Analysis • Engineering Scope Activity • Environmental Scope Activity • Environmental Class of Action Identification • Preliminary Alternatives Development • Detailed Alternative Review • Environmental Impact • Engineering Evaluation

  5. Development / Building Phases • Project Planning • Prioritizing / Programming • Preliminary Design • Pre-Final Design • Right of Way Acquisition • Utility Relocation

  6. Development / Building Phases • Project Planning • Prioritizing / Programming • Preliminary Design • Pre-Final Design • Final Design • TS&L Study • Contracted Design • Single Option • Multiple Options

  7. Development / Building Phases • Project Planning • Prioritizing / Programming • Preliminary Design • Pre-Final Design • Final Design • Contracting • Contractor Alternate Design • Shop Drawing Reviews • QA Inspections

  8. Development / Building Phases • Project Planning • Prioritizing / Programming • Preliminary Design • Pre-Final Design • Final Design • Contracting • Open Structure to Public Use

  9. Why Contractor Alternate Design • It is simply not practical to pursue all design options to their conclusion • The optimum solution may have been overlooked • It creates a desirable environment where people with specific skills, equipment and facilities, are assembled to offer solutions to the owner.

  10. Definition A contractor bidding a design, essentially meeting the requirements as defined by the owner’s TS&L study, based on the owner’s standards, prepared by the contractor’s team, including a contractor selected design engineer.

  11. Essential Requirements • Having the same: • Load carrying capacity • Number and size of traffic lanes, shoulders, curbs, sidewalks, etc. • Meeting the requirements for: • Vertical and horizontal clearances • Roadway geometry requirements • Clearance to underlying roads, utilities, railroads, streams, structures, or wetlands • Other project specific considerations that might be discovered during exploratory drilling

  12. Benefits for the Owner • Lowers bids without a reduction in quality • Improves customer service by reducing construction time • Prevents “crippled” designs from being executed

  13. Benefits for the Owner (2) • Taps industry design methodology and technology • Considers changes in capabilities and technology • Fits the best team approach and the best all the participants have to offer • Rewards contractor’s agility and ability to solve problems • Takes advantage of the latest materials available

  14. Benefits for the Contractor • Creates a basis for competition on the basis of the best solution rather than the cheapest price • Rewards innovation, agility, and originality • Rewards ability to match conforming solutions with the problem at hand • Fosters a sense of partnering with owners and his suppliers

  15. Benefits for the Contractor (2) • Considers workload, efficiency and best fit in fabricating plants and at suppliers • Considers latest improvements in safety procedures • Moves competition further back in supply channel • Considers availability of suitable equipment • Accommodates contractor’s best construction operations

  16. How it Works • The Owner • Provides common design criteria • Establishes policy that lowest bid will take contract • Allows Contractor Alternate Designs • Provides rules for Contractor Alternate Designs • Provides development information for use by bidders

  17. How it Works • The Contractor • If his Contractor Alternate Design bid is successful • Submits conceptual plans and schedule of proposed design for approval • The Owner • Reviews for essential functional equivalency, based on specifications and approves or rejects • The Contractor • Prepares final plans • Provides design calculations • Establishes a required items schedule

  18. Rules to Make it Work • Anything additional falls on the shoulders of the contractor • Delays in submission or approvals are at the contractor’s risk • A Registered Professional Engineer, familiar with standards and criteria must prepare the design – the owner reserves the right to approve or reject the designer • Contractor may have to pay a review fee

  19. Rules to Make it Work (2) • If the Contractor Alternate Design solution fails to meet the owner specified design criteria and is rejected for that reason, the contractor is required to build the as-designed version for the amount bid

  20. Why Not the Best Design in the First Place? • Standards and specifications are at best a compromise between the minimums acceptable while allowing for sufficient competition • As-designed solutions are aimed at the lowest common denominator • Significant new methods can become available between design and bidding • Designers tend to think there is only one solution • “Necessity is the Mother of Invention”

  21. Why not Value Engineering After the Bid? • A contractors competitive creativity peaks at bid time when the team to support the project is assembled • After the bid the contractor is in a “build it as you see it” mode unless there is a major blunder • Can the contractor keep the job stay in limbo for the time needed to negotiate the division of savings, get approvals, and reviews for the proposal ???

  22. Public Policy • Chapter 2 of the PENNDOT Design Manual states: “Unless approved by the Chief Bridge Engineer, alternate designs by contractors are permitted in all cases. Justification must be provided whenever alternate designs are not allowed.”

  23. Thank You For Your Attention Questions?

More Related