1 / 34

Turap berangkur

Turap berangkur. Yulvi zaika. gudang. ka p al. sheet pile. Sheet Piles. ~ turap baja atau kayu dipancang ke dalam tanah , yang membentuk dinding menerus. Anchored Sheet Pile Walls. An gker biasanya untuk dinding > 20’ Meningkatkan stabilit as Lebih murah Mudah dilaksanakan.

ismail
Download Presentation

Turap berangkur

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Turapberangkur Yulvi zaika

  2. gudang kapal sheet pile Sheet Piles ~ turapbaja atau kayu dipancang ke dalam tanah, yang membentuk dinding menerus

  3. Anchored Sheet Pile Walls • Angkerbiasanya untukdinding> 20’ • Meningkatkan stabilitas • Lebih murah • Mudah dilaksanakan

  4. Kategori Anchored Sheetpile Free Earth Fixed Earth

  5. Anchored Sheet Pile Free Earth Support (Bersendi)

  6. Anchored Sheet Pile Fixed Earth Support (Terjepit)

  7. Tertanampadapasir Free Earth Support Method

  8. KESETIMBANGAN GAYA  Fh=0 MOMEN TERHADAP TITIK O’ (LETAK ANGKUR) =0 MOMEN MAXIMUM L1 <z < L1 +L2; gaya geser =0

  9. Pasir Momen Reduction Rowe Relative flexibility of piles E = MN/m2 I = m4/m

  10. Free Earth Method Design Prosedurdesain • Pilih dimensi/penampang sheet pile • Menentukan S per unit panjang dinding • Menentukan momen inertia I • Didapat H’ dan hitung • Hitung log • Hitung kapasitas momen • Menentukan. • Note :Mmaxadalahmomen teoritis maksimum yang ditentukan sebelumnya.

  11. Free Earth Method Design Desain, Reduksi Momen Prosedur desain (lanjutan) • Plot log  (Step 5) dan pd gambar berikut. • Ulangi step 1 sampai 8 utk beberapa sections. • Titik di atas lengkung/kurva (pada loose sand atau dense sand,) adalah penampang aman. Titik di bawah lengkung/kurva adalah penampang yang tidak aman. Penampang paling murah dapat dipilih dari titik-titik yang berada di bawah lengkung. Penampang yang dipilih mempunyai

  12. Tertanampadalempung Free Earth Support Method P1

  13. KESETIMBANGAN GAYA  Fh=0 MOMEN TERHADAP TITIK O’ (LETAK ANGKUR) =0 MOMEN MAXIMUM L1 <z < L1 +L2; gaya geser =0

  14. Free Earth Method DesignCohesive Materials Tekanan Clay di bawah Dredge Line Keseimbangan statis, gaya horisontal Keseimbangan Momen (terhadap O’) P1 = luas diagram tekanan ACD F = gaya angker per unit panjang dinding

  15. Free Earth Method DesignCohesive Materials Reduksi momen Angka stabilitas: Nondimensional tinggi dinding

  16. Free Earth Method DesignCohesive Materials Langkah reduksi momen Dapatkan Tentukan  → Tentukan Sn Tentukangunakan  dan Sn untukberbagai harga log dan plot Md/Mmaxvs log .

  17. Lempung Moment Reduction Rowe Stability number

  18. Sheet Pile Wall Anchors • Dari perhitungan telah diketahui: • Gaya angker (Anchor Force) • Posisi angker/Anchor Position (Elevation) • Desain angker • Pertimbangkan jenis angker • a) Anchor Plates and Beams (deadman) • b) Tie Backs • c) Vertical anchor piles • d) Anchor beams supported by batter piles • Ukuran/panjang • Jarak

  19. Anchor (Jangkar) Plat ataubalokjangkar

  20. Anchor (Jangkar) Tie back

  21. Anchor (Jangkar) Tiang jangkar vertikal

  22. Anchor (Jangkar) Balok jangkar dengan tiang tiang miring

  23. Plat dan balok jangkar pada pasir

  24. Metode Ovesen dan Stromann Angker plat jalurpadatanahpasir LangkahPerhitungan: 1. HitunghargaKadarigrafikdan Pa

  25. Metode Ovesen dan Stromann 2. HitungKp sin  3. DenganmenggunakangrafikdiperolehKpcos 4. HitungPu’

  26. Metode Ovesen dan Stromann Jika angker menerus (ie, angker untuk B = ), Tentukan tinggi aktual h, pada kedalaman H P’us = tahananbatasuntukkasusjalur Cov = 19 untukpasirpadatdan 14 untukpasirlepas

  27. Metode Ovesen dan Stromann Kasus Aktual Plat angkerdiletakkanberjajar dengan jarak S’ Panjang ekivalen

  28. Hubungan beban dan perpindahan B/h

  29. Anchor Plates in Sand Korelasi empiris Kekuatan batas angker tunggal FOS (2 ~ 3 disarankan) Jarak Center-Center F = gaya per satuan panjang sheet pile

  30. Tahanan batas tie back Kekuatan batas yang diberikan oleh tieback Sudut geser dalam tanah efektif Teg vertikal efektifrata-rata K = koefisien tekanan tanah Pada tanah clays kekuatan mendekati: dimanaca = adhesi Dapatdiambil 2/3 c

  31. Contohsoal • Turapberangkurdirencanakanmerupakan plat denganukuran B=h =0.4m, S=1,2m dan H=1m dantanah =16.51 kN/m3 , =35. Tentukantahananbatasmasingmasing plat jangkar’. Plat jangkarterbuatdaribetondengantebal 0.15m. Bebanjangkarpadaperpindahan horizontal 40 mm