We take care of the tracks ! . Ger van der Wal Manager Tendering, cost engineering and procurement EFRTC, Amsterdam, 2 december 2005. Mission ProRail. Sufficient, reliable and safe infrastructure; Delivers train path , transfer capacity en information services;

issac
Download Presentation

We take care of the tracks !

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. We take care of the tracks! Ger van der Wal Manager Tendering, cost engineering and procurement EFRTC, Amsterdam, 2 december 2005

  2. Mission ProRail • Sufficient, reliable and safe infrastructure; • Delivers train path , transfer capacity en information services; • Transparent and to benefit society; • With motivated and professional personnel; • Acts as partner in the rail branch and contributes to solve mobility problems now and later; • Wants to be the best rail infrastructure manager in Europe. 2

  3. Our infrastructure • 2.800 km net length • 6.500 km track • 4.000 km catenary • 8.400 switches • 387 stations • 2.900 level crossings • 4.500 bridges, viaducts and tunnels 3

  4. Daily traffic • 5.000 passenger trains with 1 million passengers • 230 cargo trains with 80.000 tons cargo 4

  5. Organisation Board of directors HRM Planning & control Communica- tion Strategy Facility Services Information policy Safety Audits Capacity management Infra management Infra projects Development ICT services Traffic control 5

  6. Turnover Income Government Access fee Profit Investments Assets 1.106 1.129 912 119 23 982 11.417 Financial figures 6

  7. Infrastructure management • Planning renewal • Daily maintenance 7

  8. Capacity management • Specify infrastructure bottlenecks • Capacity planning • Qualify operators 8

  9. Traffic control • Traffic control • Information services 9

  10. Infrastructure projects • New infrastructure • Stations and transfer • Renewal projects • Mega projects • Tendering & cost engineering • Land acquisition 10

  11. 2 to 4 tracks Utrecht-Amsterdam • Track length 30,5 km, 4 new stations, 12 level crossings replaced by tunnels, Two flyovers, etc. • Investment€ 1000 million New station Amsterdam - Bijlmer 11

  12. Upgrade Major Stations Six new stations give a hart to their city • Renewal Stations due to High Speed Lines • Enlargement public transport hubs • Development of city centres • Investment by Government – Municipalities - Private investors) • Total investment equals billions Amsterdam Zuid /WTC – Arnhem - Breda - Den Haag - Rotterdam - Utrecht 12

  13. The Betuweroute • 160 km cargo track from Maasvlakte via motorway A15 to Germany • 130 viaducts and bridges and 5 tunnels • Connecting Rotterdam to Europe by dedicated rail • Completion January 2007 13

  14. Projects now and in the future • Station development: • Amsterdam Central Station • New stations • Railtunnel Delft • New infrastructure: • Hanzelijn (connection Lelystad – Zwolle) • Light Rail (various projects) • IJzeren Rijn (connecting Antwerp with Germany) • From 2 to 4 tracks Amsterdam – Utrecht • From 2 to 4 tracks Vleuten – Geldermalsen • OV Chip card • Space for the Dutch bicycles • Zuiderzeelijn, direct raillink between Groningen and Amsterdam 14

  15. Investments, renewal, maintenance New track work € 200 million pa Track renewal € 400 million pa Track maintenance € 200 million pa Total incl. structures, buildings, ect. € over 1.5 billion pa 15

  16. ProRail and rail contractors • Qualification codes for: • Track • Catenary • Interlocking systems • Maintenance (all techniques) • Draft prEN 14969; Railway applications – Track Formal votes spring 2006 Dutch vote not yet decided 16

  17. Qualified contractors Interlocking Catenary Powersupply Track Maintenance BAM v v v v v Volker Stevin v v v v v Strukton v v v v v Imtech v v GTI v v v Fahrleitungbau v Nedrail v v Homij v Amec Spie v Spitzke v Schreck Mieves v 17

  18. -- - ‘90 ‘90 -’95 ‘95- ‘99 2000-> Feasebility Functional design Technical design Construction Maintenance Client Consultant Contractor 18

  19. Contracts & tendering For track work contracts • EPC (Engineering, procurement and construct) • Alliances • Multiple year renewal contracts • Public “electronic” tender procedures www.tenderned.nl • Past Performance used by awarding contracts • Contractor responsible for: • Safety • Procurement materials • Track possession time Maintenance 1e contract to be tendered 2006, next years 2 or 3 contracts pa 19

  20. Thank you for your attention Ger van der Wal Contact www.prorail.nl aki@prorail.nl 030 235 8405 www.aanbesteden.prorail.nl www.tenderned.nl 20