1 / 25

Presentation on Indo – Myanmar Kaladan Multimodal Transit Transport Project

Presentation on Indo – Myanmar Kaladan Multimodal Transit Transport Project (Port & IWT Components) 4 th May 2012. Aizawl. I N D I A. I N D I A. NH 54. B A N G L A D E S H. ROAD IN INDIA. Lawngtlai. Myeikwa (IM Border).

ivo
Download Presentation

Presentation on Indo – Myanmar Kaladan Multimodal Transit Transport Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presentation on Indo – Myanmar Kaladan Multimodal Transit Transport Project (Port & IWT Components) 4th May 2012

  2. Aizawl • I N D I A • I N D I A NH 54 • B A N G L A D E S H • ROAD IN INDIA Lawngtlai Myeikwa (IM Border) ROAD IN MYANMAR Kaletwa (Ch 225 km Myanmar Paletwa Ch. 158 Km Kyauktaw • Kaladan R. DISTANCES I W T • Bay of Bengal Sittwe Ch. 0.0 km Kaladan Multimodal Transit Transport Project

  3. Project Components …post review • Fairway development / Sea-dredging in Sittwe port area • Construction of Port / IWT terminals at Sittwe • Fairway development / Dredging on Sittwe – Paletwa stretch of Kaladan river (158 Km) • Construction of IWT Terminal at Paletwa • Construction of 6 IWT vessels (300 ton each) • Highway (129 kms) from Paletwa to Indo-Myanmar Border.

  4. Existing Sittwe Port Office

  5. Existing Port at Sittwe

  6. Existing Loading / Unloading at Sittwe Port

  7. Progress made • MEA issued Letter of Acceptance(LoA) to Essar Projects India Ltd. in April 2010 at a cost of Rs. 342 Crores (Approx US $ 75 millions) for the Port & IWT works. • Agreement between MEA and Contractor signed in May 2010. • Port & IWT works to be implemented in 36 months. 7

  8. Progress made… contd. Govt. of Myanmar has provided land for Construction & Setting up of Contractor’s camp at Sittwe during Sep 2010. Permissions for import of Construction equipments & Opening of bank account in Oct 2010. 8

  9. Progress made… contd. Ground breaking ceremony attended by Senior dignitaries from both countries held on 19th December 2010 at Sittwe.

  10. Progress made… contd. • Construction activity at Sittwe started in Dec 2010. • Consequent to relocation of terminal to Paletwa, preparation of DPR for New road section between Paletwa and Kaletwa has become necessary. • MEA has appointed M/s IRCON Infrastructure & Services Ltd. New Delhi as the agency for preparing the D.P.R. for the new road section. • Design and model testing of 300 DWT Barges has been completed. Selection of Yard is in final stage. Barges are to be built in Myanmar. 10

  11. Progress made… contd. • Reclamation for backup facilities at Sittwe 96% completed, Construction of Rubble mounted Dyke 70% Completed. • Construction of Pile work at IWT & Port Approach Jetty at Sittwe 98% completed. Main Jetty piling work shall commence shortly. • Pre-cast concrete works for IWT & Port Jetty at Sittwe 50% completed. • Excavation work at Paletwa 15% completed. 11

  12. Reclamation for backup facilities (96%)

  13. Dyke Construction work at Sittwe (70%)

  14. PILING GANTRY 1 PILING GANTRY 2

  15. Piling work at IWT Approach Jetty (98%)

  16. Pre-Cast Yard at Sittwe (50%)

  17. Excavation work at Paletwa (15%)

  18. Progress made… contd. • Hydrographic Survey at Sittwe Port and also in between Sittwe – Paletwa stretch was completed on 2.11.2009 and 20.2.2012 respectively by IWAI with the assistance from the local Survey agency. • 6 Nos of Shallow area for dredging in Kaladan river was identified. 5 Nos of Shallow area was indicated in DPR (2002). • The Location of Navigational Aids, Positions of submerged Rocks and Dredging alignment are to be demarcated as per the new Survey charts. 18

  19. Hydrographic Survey in Kaladan River

  20. Plan of Approach & Harbour channel at Sittwe

  21. Layout of Port & IWT Jetty, Sittwe

  22. Layout of IWT Jetty at Paletwa

  23. Important Points / issues • Approval of General layout drawings for backup facilities was submitted to Working Committee, Govt. of Myanmar :- • on 3.11.2011 for Sittwe. • on 9.11.2011 for Paletwa Approvals are yet to be received. 23

  24. Important Points / issues • M/s. Essar Projects has already expressed that they can complete the work within the scheduled time by mobilising additional resources subject to the receipt of above approvals without further delay. • Otherwise project may get delayed by another 6 more working months. 24

  25. Thank you

More Related