An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Schedule Risk Analysis of Software Development By: Dr. Joe H. Dean Engineering Chief Risk & System Analysis LFWC And: Mr. David W. Benson, Jr. Engineering Specialist Avionic Software Engineering LFWC BV41840

  2. Current Practice – Schedule Risk Analyses for Software Projects Are Typically Performed for Individual Software Tapes However, No Quantification of Integrated Schedule Risk Is Made Short Coming – If a Tape Is High Risk (or Moderate or Low) What Does That Mean Regarding the Probability of Timely Completion Of That Tape? Of Effected Programs? Needed – Cumulative Analysis to Show Sensitivity of Integrated Program Schedules to Tasks on Individual Software Tapes Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data Why Integrated Schedule Risk Analysis? BV41841

  3. Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data Schedule Risk Model Basis & Capability Risk Issues Program Schedules • Task Duration • Consequences • Abatement Options Min. Most Max Likely Task Relationships SS FS FS FS SS FF FS FF SF Schedule Risk Analysis Task Relationships: Robustness SS Start-to-start Sensitivities SF Start-to-finish Delivery Dates FS Finish-to-start Prob SS Finish-to-Finish Time • Program Schedule Risk • Alternative Critical Paths • Abatement Analysis BV41842

  4. Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data FS: Finish-to-Start Task Connectivity Within & Between Tapes Is Modeled Software Start TAPE 1 FS FS FS FS FS FS ... System Design Detailed Design Preliminary Design Code/Unit Test CSC Test BV41843

  5. Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data FS: Finish-to-Start Task Connectivity Within & Between Tapes Is Modeled (Cont’d) Software SW Start TAPE 1 FS FS FS FS FS FS ... System Design Detailed Design Preliminary Design Code/Unit Test CSC Test FS FS FS TAPE 2 FS FS FS FS ... System Design Detailed Design Preliminary Design Code/Unit Test BV41844

  6. Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data Task Connectivity Within & Between Tapes Is Modeled (Cont’d) Task Relationships FF: Finish-to-Finish SF: Start-to-Finish FF: Finish-to-Finish SF: Start-to-Finish Software Start FS FS FS FS FS FS System Design Detailed Design Code/Unit Test CSC Test Tape 1 (Prog. 1) Preliminary Design FS FS FS FS FS FS FS System Design Preliminary Design Detailed Design Code/Unit Test Tape 2 (Prog. 1) FS FS FS FS FS Tape 3 (Prog. 1) Detailed Design Preliminary Design System Design FF FF FF Tape 4 (Prog. 1) Preliminary Design Detailed Design FF Tape 1 (Prog. 2) System Design Preliminary Design Detailed Design FS FS FS Tape 2 (Prog. 2) Preliminary Design FS Tape 1 (Prog. 3) System Design Preliminary Design FS LOA FS FS Tape 2 (Prog. 3) Preliminary Design Flight Test BV41845

  7. Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data REVIC Basics • COCOMO (Constructive Cost Model) Developed by Dr. Barry Boehm Based on Curve Fit of Approx. 70 Projects Across Industry 75% OF NOMINAL • Model Calibration via 15 Factors Covering Product, Computer, Personnel, and Project Attributes Software Task (e.g. DSI) • Model Covers Tasks from Availability of Firm Software Requirements (Assumed Reasonably Stable) through Completion of Software Test NOMINAL RISK • Schedule Compression Adds Cost and Risk and Cannot Be Compressed to Less than 75% of Nominal Time • REVIC (Revised Version Intermediate COCOMO) Based on USAF Specific Projects • The F-16 SPO and LFWC Have Used COCOMO/REVIC Since the Mid 1980’s BV41846

  8. Task Completion Variations Are Assigned Based on REVIC Analysis Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data High Risk Moderate Risk Nominal Risk Schedule Less than 80% of Nominal Schedule 80 - 92.5% of Nominal Schedule Within 92.5% of Nominal 90% 100% 140% 90% 100% 120% 90% 100% 110% 75% OF NOMINAL Task Size (DSI) NOMINAL RISK Time BV41847

  9. Monte Carlo Process In Schedule- Risk Model Is Straightforward Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data 1 2 Enter Task Completion Variability and Connectivity Between Tasks Random Draw Determines Completion Time for Each Task 1 Random Number FS MIN MAX Completion Time FF SS FS 0 Min Most Likely Max 3 4 For Each Trial (Total Network), Construct Critical Path & Project Completion Date. At Any Given Time (Date), Probability of Success # of Trials Complete Total # Trials = [Repeat N Trials] 1 Trial Results P (t) S 0 0 Time (Completion Dates) t = Time BV41848

  10. Probability of Completion vs. Planned Finish Time Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data 1.00 0.75 Probability of Completion 0.50 0.25 0.00 -60 -40 -20 0 20 40 60 80 100 Number of Days from Planned Finish PLANNED TIME (BASELINE) BV41849

  11. Assessing Schedule Changes Resulting from Risk Abatement Plan Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data 1.00 RISK ABATEMENT ALTERNATIVE 0.75 Change In Probability Completion BASELINEPLAN Probability of Completion 0.50 0.25 Change In Planned Finish 0.00 -120 -100 -80 -60 -40 -20 0 20 40 60 80 100 Number of Days from Planned Finish BV41850

  12. Results Corresponded Well with Expert Opinion Software Task/Tape Completion Times Were “Reasonably” Bounded in Regard to Program Schedule Impact Customer Needs Analysis & Control Requirements Allocations Verification Design Product Data Summary Preliminary Findings Appraisal • This Process Is a Promising Method to Quantify Schedule Uncertainty, Especially in Highly Interrelated Task Networks • This Process Allow Potential Schedule “Savings” from Risk Abatement Alternatives to Be Considered as an Aid in Decision Making BV41851