This outline provides an assessment of the 4th quarter progress of the Twinning Project ENEA, including coordination, communication, activities, outputs delivered, and future program plans.
E N D
Twinning projectENEA – ENforcing Environmental Acquis 4th Steering Committee César Seoánez Skopje, 9th of February, 2016
OUTLINE • 4th quarter assessment (12 October 2015 – 11 January 2016) • Quarterly Report 4 • Programme for next 6 months (12 January – 11 July 2016) • Operative Side Letter 5 • Outputs delivered to Steering Committee • Addendum 2 Twinning Project ENEA – ENforcing Environmental Acquis
4th QUARTER: Coordination • Meetings: multiple, within missions, with stakeholders, including Inspection Council • Main outputs & conclusions so far communicated and forwarded • E-inspection software team communicate with SEI • Coordination with TA project supporting local level & Twinning IED • Coordination with training programme of TA project • Coordination meeting organised by MoEPP sharing & review of relevant docs • Mutual participation in workshops of Twinning & TA in November & December • Info exchange continues Twinning Project ENEA – ENforcing Environmental Acquis
4th QUARTER: Communication • Website: www.sei.gov.mk • SEI banner now visible in MoEPP’s website • First promotional video published online • Estimate of visibility materials to be prepared in following months Twinning Project ENEA – ENforcing Environmental Acquis
4th QUARTER: Progress vs. Work Plan Twinning Project ENEA – ENforcing Environmental Acquis
4th QUARTER: Progress vs. Work Plan • Good Twinning Project ENEA – ENforcing Environmental Acquis
4th QUARTER: Activities October (starting 12th ) • Activity 1.2, mission 7: factsheets for industrial sectors • Activity 1.2, mission 5: check lists for some waste streams • RTA Training in Brussels, 15-16 October • Activity 1.2, mission 4: last mission for general inspection manual • Activity 1.3, mission 3: preparation of training materials • Steering Committe 3 Twinning Project ENEA – ENforcing Environmental Acquis
4th QUARTER: Activities November • Activity 3.1, follow-up of mission 1: BPMS assessment & 1st recommendations • Activity 2.1, mission 4: workshop & 1st draft of Law for Inspection on Environment • Activity 2.1, mission 6: other supporting materials & training on planning (IRAM) • Activity 1.2, mission 10: 2nd mission to finalise IPPC/BAT guidelines • Draft Addendum 2 & meetings with Inspection Council December • Activity 2.2, mission 5: 4 one-day workshops on inspection cycle • Activity 1.2, mission 8: 2nd mission to finalise factsheets for industrial sectors • Updates to Addendum 2 upon request of CFCD Twinning Project ENEA – ENforcing Environmental Acquis
4th QUARTER: Activities Main outputs • SEI - Twinning website • Inspection manual • Draft sector inspection checklists & factsheets (12 sectors) • Trainings on IRAM & Inspection Cycle • Workshop & draft Law for Inspection on Environment • Draft proposals for indicators to evaluate inspectorate & inspectors • SEI’s BPMS assessment & first proposals for next steps Twinning Project ENEA – ENforcing Environmental Acquis
4th QUARTER: Activities Other outputs • Translation of Spanish templates for multiannual insp. plan & annual programme • First promotional video in FIIAPP’s web • Addendum 2 Twinning Project ENEA – ENforcing Environmental Acquis
4th QUARTER: Participation BC experts • 140 BC participants in meetings held in missions • A lot of drafting (to continue until February 2016) Twinning Project ENEA – ENforcing Environmental Acquis
4th QUARTER: Expenditures • As planned • Savings in flight tickets • In 4th quarter ~ 19 % of activities’ budget Twinning Project ENEA – ENforcing Environmental Acquis
QUARTERLY REPORT • Addendum 2: training needs urgent endorsement • Central planning & control of inspectors • new Law should come into force • Inspection Council should address Twinning docs sent, • to align to EU best practices Overload in planning & reporting, evaluation of inspectors with financial penalties... • Inspection Council activity should get the attention of EC • Paragraph slightly reformulated Twinning Project ENEA – ENforcing Environmental Acquis
QUARTERLY REPORT • Managers in SEI, MoEPP, CFCD, DEU & SEA should continue pushing for a change in Law for Insp. Supervision • Review & implement recommendations for improvement • 2nd update: deleted recommendation about E-inspection project, as it was cancelled Twinning Project ENEA – ENforcing Environmental Acquis
PROGRAMME NEXT 6 MONTHS January • Activity 1.2, start of mission 6: 2nd mission for check lists waste streams • Activity 2.1, start of mission 8: control & remediation of old polluted sites • Activity 1.2, mission 11: 1st mission leaflet operators & communication strategy February • Activity 2.1, mission 7: other supporting documents • Steering Committee 4 • Activity 3.1, mission 2: proposals for BPMS improvement • Activity 1.2, mission 12: 2nd mission to finalise leaflet operators & comm strategy Twinning Project ENEA – ENforcing Environmental Acquis
PROGRAMME NEXT 6 MONTHS TRAINING April-May April-May March June March-May July Twinning Project ENEA – ENforcing Environmental Acquis
PROGRAMME NEXT 6 MONTHS March • Activity 1.3, mission 4: 2 two-days trainings on industrial processes (regions 1 & 2) • Activity 1.3, mission 5: 2 two-days trainings on industrial processes (regions 3 & 4) • Activity 1.3, mission 6: training based on inspection to pilot installation (region 1) April • Activity 1.4, mission 3: study visit to The Netherlands • Activity 1.3, mission 7: 3 one-day trainings on comm. skills & team building • Activity 2.2, mission 6: training based on inspection to pilot installation (region 3) Twinning Project ENEA – ENforcing Environmental Acquis
PROGRAMME NEXT 6 MONTHS April • Steering Committee 5: 22nd April • Activity 3.1, mission 3: training on use of IRAM software May • Activity 1.3, mission 8: 3 one-day trainings on comm. skills & team building • Activity 2.2, mission 7: training based on inspection to pilot installation (region 2) • Activity 3.1, mission 4: further work on BPMS (to be defined in missions 3.1.2-3) • Updated project’s brochure Twinning Project ENEA – ENforcing Environmental Acquis
PROGRAMME NEXT 6 MONTHS June • Activity 2.2, mission 7: training based on inspection to pilot installation (region 4) • Activity 2.1, mission 9: first training on sampling & monitoring • Activity 2.1, mission 10: second training on sampling & monitoring July(until 11th) • Closure event Twinning Project ENEA – ENforcing Environmental Acquis
OPERATIVE SIDE LETTER 5 • Side letter 10: expert for mission 2.1.7 + 2 flights for act. 1.2 • Included Marc du Maine in act. 1.3 • Explicit approval of OSL is very welcome Twinning Project ENEA – ENforcing Environmental Acquis
COMMENTS TO OUTPUTS DELIVERED TO ST.C.? • 2.1.4 – Draft Law for Inspection on Environment • 2.1.4 – Report related to the draft Law, and Table of Concordance • 3.1.1 – BPMS assessment and first proposals for next steps • 2.1.6 – Procedure & minutes template for small incident/accident • 2.1.6 – IRAM’s users guide • 1.2.10 – Guidance on BAT on storage of hazardous and non-hazardous waste • 1.2.10 – Guidance on “mirror code waste” classification • 1.2.6 & 1.2.8 – 12 sector & waste inspection checklists • 2.1.8 – Issues to comply with EU legislation on soil protection • 2.1.7 – Indicators to evaluate inspectors & Inspectorate Twinning Project ENEA – ENforcing Environmental Acquis
ADDENDUM 2 Need for urgent endorsement • Training missions in March RTA affected • Study tour in April participation of RTA Assistant and of 11th participant All your support is needed! Twinning Project ENEA – ENforcing Environmental Acquis
Thank you very much ! Благодараммногу! www.sei.gov.mk blinkov_d@yahoo.com inspection.cs@gmail.com Twinning Project ENEA – ENforcing Environmental Acquis