1 / 25

THE SHAW GROUP, INC. “PANTHER FINANCIAL”

THE SHAW GROUP, INC. “PANTHER FINANCIAL”. Prepared for: Mr. Michael Bolch Shaw Group. Project Scope and Client Goals. Florida Institute of Technology Design and construction of a 12,600 s.f . commercial office building to be used as a financial institute

jagger
Download Presentation

THE SHAW GROUP, INC. “PANTHER FINANCIAL”

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. THE SHAW GROUP, INC.“PANTHER FINANCIAL” Prepared for: Mr. Michael Bolch Shaw Group

  2. Project Scope and Client Goals • Florida Institute of Technology • Design and construction of a 12,600 s.f. commercial office building to be used as a financial institute • SW corner of Babcock St. and Palm Bay Blvd. in Palm Bay, Fl • Create a construction schedule using MS Project • Generate an estimated probable cost • Develop construction contracts and terms

  3. Project Management Plan • Divided into 3 parts • Project Controls • Project Scope • Project Schedule • Structural Design • Layout • Structural analysis / Member design • Connections • Hurricane damage mitigation • Legal Aspects • Contract development & terms • Preparation for negotiations • Regulatory Agencies

  4. Project Size and Cost • Steel structure • 2 stories • 12,600 s.f. • Parking lot • Transportation • Level of service analysis • Water and sewer system design • Geotechnical • Foundation design • Total Estimated Cost: $1,895,000.00 ($150.00/s.f.)

  5. Project Design Schedule

  6. Structural Design • Key Elements • Layout • Structural analysis / Member design • Connections • Hurricane damage mitigation

  7. Anticipated Final Design PANTHER FINANCIAL

  8. Second Floor Layout

  9. Roof Layout

  10. Structural Analysis / Member Design • Two Dimensional Dr. Frame Analysis • Determining Maximum Shear, Moment, and Axial Loads being less than the Design Load

  11. Structural Elevation Drawing(Transverse View)

  12. Structural Elevation Drawing(Longitudinal View)

  13. Final Member Selection

  14. Connections / Drawings • Shear Connections are bolted • Moment Connections are shop-welded and bolted

  15. A3 Web-Shear Connection • 6 – A325 ½” bolts based on Slip Critical Strength • L2½” x 2½” x 1/2 Double Angles based on Areas

  16. Column Base Plate Drawings

  17. Work Breakdown Structure

  18. Hurricane Damage Mitigation • Constructed on raised foundations above sea level • Built upon steel, concrete, or wooden pilings or anchored to solid rock • All concrete is reinforced with steel • Specialized doors and windows • Using shutters over doors and windows during hurricanes

  19. Legal Aspects Contract Development Preparations for Negotiations Permits, Licenses, Agencies

  20. Contract Development-1 • Contract Development for Panther Financial • Description of lands/site • Contractors Responsibilities • Labor • Schedule • Permits • Owners Responsibilities • Communication • Payments • Insurance

  21. Contract Development-2 • Change Orders • Claims • Tests and Inspections • Dispute Resolution • Good Faith Negotiations • Mediation • Arbitration • Litigation • Liquidated Damages

  22. Negotiations • Preparation for Negotiations • Gather outside information • Establish points of leverage • Set a goal • BATNA • Shoot for a Win - Win conclusion

  23. Permits, Licenses, Agencies Follow codes and regulations Acquire permits and licenses Keep in good standing with agencies and the public

  24. Project Summary Scope Schedule Estimated Cost Structural Design Contract Development Negotiation Tactics Codes, Permits, and Licenses

  25. Thank you for choosing The Shaw Group, Inc. • Project plan will meet client’s goals • We will produce a quality project • We appreciate your business • Your Project Manager • Stephen M. Craig • StephenCraig11@gmail.com • (412) 657-6263

More Related