An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bolt-On/Middleware Examples Kellogg Company Brown et al. [2001] Dow Corning Teresko [1999]

  2. Kellogg Company Bolt-On • Kellogg developed their own ERP • Forecast demand • Take customer orders • Coordinate raw material purchasing • Coordinate production of over 100 food products • Coordinate distribution • Added linear programming Kellogg Planning System (KPS) • Production, inventory, distribution planning • Budgeting & capacity expansion

  3. History • Long user of MRP, DRP (distribution resource planning) • 1987 realized product line growth, international expansion led to need for more computer support • Developed KPS in 1989, modified over time • By 1994 strong cost system in place • Saved $4.5 million in 1995

  4. Kellogg LP • Minimized total cost • Purchasing, manufacturing, inventory, distribution • Variables: product, package size, case size • 30 week planning horizon • Constraints: • Line, packaging capacities, flow constraints, inventories, safety stocks • 700,000 variables, 100,000 constraints, 4 million non-zero coefficients

  5. Kellogg LP • Continuous model took several hours to run • Generated starting solution for managers • Probabilistic features dealt with through safety stock • Example of bolt-on to ERP • Linear programming generated better plans

  6. Dow Corning System Integration • 1995 adopted SAP R/3 to integrate global business practices • Also adopted SAP data warehouse • Consolidated information generated internally, externally • Internal: plant-floor data, patent information, benchmarking • Allowed deeper data analysis

  7. Dow Corning System • Over 4,000 users had access • Integration & data compatibility problems dealt with by data warehouse • Added automated data collection system • Required middleware • Middleware allowed expansion into supply chain management