1 / 17

MINISTRY OF TRANSPORTATION Cyrville Road Bridge Replacement at Highway 417 (Ottawa Queensway)

Detailed study for the replacement of Cyrville Road Bridge at Highway 417 in Ottawa. Includes planning, design, and environmental assessment to improve operational efficiency. Study focuses on long-term highway improvements and construction staging alternatives. Benefits include reduced construction schedule, cost savings, and minimal traffic disruption. Study follows approved environmental planning process.

jamesdyer
Download Presentation

MINISTRY OF TRANSPORTATION Cyrville Road Bridge Replacement at Highway 417 (Ottawa Queensway)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MINISTRY OF TRANSPORTATIONCyrville Road Bridge Replacement at Highway 417 (Ottawa Queensway) Detail Design Study Group Work Project 4011-06-00

  2. Carry out a Detail Design and Class Environmental Assessment (EA) Study to facilitate the replacement of Cyrville Road Bridge. • Document the Study in a Transportation Environmental Study Report (TESR). • Prepare a Construction Contract for the recommended Bridge improvements. Study Purpose

  3. Planning, Preliminary Design and Transportation Environmental Assessment study undertaken to determine long-term operational improvements along Highway 417 (Ottawa Queensway) from Highway 416 Easterly to Anderson Road (GWP 663-93-00), which included the Cyrville Road Bridge replacement. • Completed TESR and Preliminary Design Report for the Highway 417 operational improvements in 2007. • Environmental approval obtained in October 2008. • Identified need to replace Cyrville Road Bridge in advance of scheduled Highway 417 operational improvements to address existing structural deficiencies associated with the age of the bridge. • Initiated current detail design study to facilitate replacement of the Cyrville Road Bridge. Study Background

  4. Study Area

  5. Bridge General Arrangement

  6. Plan Cyrville Road Highway 417 Labrie Ave.

  7. Alternatives to the Undertaking

  8. Preferred Alternative • Rationale In Support of Carrying Forward • Addresses deteriorated condition of the bridge. • Supports future operational improvements on Highway 417 and Cyrville Road (i.e., sufficient span length and bridge deck width respectively). • No future traffic and community impacts associated with four lane widening of bridge. • More cost effective for City of Ottawa than implementing four lane widening at a later date to accommodate the future expansion of Cyrville Road.

  9. Construction Staging Alternatives

  10. Preferred Staging Alternative • Rationale In Support of Full Closure • Minimize cumulative traffic impacts on Cyrville Road and adjacent roadways over the duration of construction (1 year full closure impact vs. 2 year staged construction impact). • Improve safety for construction workers and motorists by eliminating traffic through a confined work zone and southbound sightline restrictions to Labrie Avenue. • Improve construction efficiency and reduce overall construction duration (1 yr. vs. 2 yrs). • Reduce combined construction and contract administration costs ($16.05 vs. $21.3 M). • Coordinate timing of construction with future operational and safety improvements on Highway 417 scheduled to commence in 2012 (subject to funding and environmental approvals).

  11. Detour StrategyHighway 417 Short-Term Full ClosureBridge Removal and Demolition BLAIR ROAD

  12. Detour StrategyCyrville Road Long-Term Full ClosureConstruction of New Bridge and Approaches

  13. Benefits include reduced construction schedule, cost savings and minimal disruption to Highway 417 traffic. • Contractor will be responsible for preparing a Removal and Demolition Plan detailing a step-by-step procedure that addresses all aspects of the structure removal and demolition. • Measures need to address the proximity to and protection of the City of Ottawa watermain located in front of the Cyrville Road Bridge south abutment below the existing Highway 417 outside eastbound lane. • Financial penalties will be imposed for delays in re-opening all lanes of Highway 417 traffic. Rapid Bridge Removal and Demolition

  14. Compatibility with Future Planning Initiatives • MTO Highway 417 Improvements • Construction timing compatible with Highway 417 improvements scheduled to commence as per Southern Ontario Highways Program. • Span lengths accommodate proposed future Highway 417 widening. • Third span accommodates independent Ottawa Road174 to St. Laurent Blvd. ramp. • Interprovincial Crossing Study • Bridge span arrangement will not preclude incorporation of Aviation Parkway interchange modifications. • Third span adaptable to permit proposed Aviation Parkway ramp configuration. • Downtown Ottawa Transit Tunnel • Construction timing to be coordinated with DOTT improvements scheduled to commence in 2011. • Bridge general arrangement and substructure compatible with DOTT improvements.

  15. Cyrville Road Operational Improvements • Bridge cross-section will accommodate two lanes of traffic, bike lane and sidewalk in both directions including provisions for median island. • Ottawa Road 174 Operational Improvements • Construction timing compatible with Ottawa Road 174 improvements schedule for completion in 2010. • Outside limits of proposed improvements. Compatibility with Future Planning Initiatives

  16. This Project is currently following the approved environmental planning process for Group ‘B’Projects, under the Ministry’s Class Environmental Assessment (EA) for Provincial Transportation Facilities (2000). • Activities completed to date: • Published Notice of Study Commencement • Advertised July 3, 2008 in Ottawa Citizen and Ottawa LeDroit • Conducted Preliminary Design and Initial Coordination with City of Ottawa • Convened Business Community Meetings • Monday, April 12 and Tuesday, April 13, 2010 • 45 businesses were invited and 13 business meetings occurred • Prepared Draft Legal Agreement with City of Ottawa • Future Activities: • Public Information Centre on May 12, 2010 at the Earl Armstrong Arena • Detail Design and Final Coordination with City of Ottawa • TESR (issued for 30-day public review) (Summer 2010) • Prepare Construction Contract and Issue for Tender • Finalize Legal Agreement with City of Ottawa Environmental Assessment Process

  17. Construction Schedule

More Related