Verification & Validation. IS301 – Software Engineering Lecture #30 – 2004-11-10 M. E. Kabay, PhD, CISSP Assoc. Prof. Information Assurance Division of Business & Management, Norwich University mailto:mkabay@norwich.edu V: 802.479.7937. Topics.
E N D
Verification & Validation IS301 – Software Engineering Lecture #30 – 2004-11-10 M. E. Kabay, PhD, CISSP Assoc. Prof. Information AssuranceDivision of Business & Management, Norwich University mailto:mkabay@norwich.edu V: 802.479.7937
Topics • Verification and validation planning • Software inspections • Automated static analysis • Cleanroom software development
Verification and Validation • Assuring that software system meets user's needs
Objectives • To introduce software verification and validation and to discuss distinction between them • To describe program inspection process and its role in V & V • To explain static analysis as verification technique • To describe Cleanroom software development process
Verification vs Validation • Verification: “Are we building the product right?” • software should conform to its specification • Validation: “Are we building the right product?” • software should do what user really requires
V & V Process • Whole life-cycle process • V & V at each stage in software process • Two principal objectives • Discover defects in system • Assess whether system is usable in operational situation
Static and Dynamic Verification • Software inspections • Analysis of static system representation • Static verification • May be supplemented by tool-based document and code analysis • Software testing • Exercising and observing product behavior (dynamic verification) • System executed with test data and its operational behavior observed
Program Testing • Can reveal • Presence of errors • But NOT their absence • Successful test • Discovers one or more errors • Only validation technique for non-functional requirements • Should be used in conjunction with static verification to provide full V&V coverage
Types of Testing • Defect testing • Tests designed to discover system defects • Successful defect test reveals presence of defects in system • Statistical testing • Tests designed to reflect frequency of user inputs • Used for reliability estimation
V & V Goals • Establish confidence that software is fit for purpose • Does NOT mean completely free of defects • Good enough for its intended use • Type of use will determine degree of confidence needed
V & V Confidence • Depends on system’s purpose, user expectations and marketing environment • Software function • Level of confidence depends on how critical software is to organization • User expectations • Users may have low expectations of certain kinds of software • Marketing environment • Getting product to market early may be more important than finding defects in program Sound familiar?
Testing and Debugging • Defect testing and debugging are distinct processes • Verification and validation concerned with establishing existence of defects in program • Debugging concerned with locating and repairing these errors • Debugging involves formulating hypotheses about program behavior then testing these hypotheses to find system error(s)
V & V Planning • Careful planning required to get most out of testing and inspection processes • Start early in development process • Identify balance between • Static verification and • Testing • Test planning is about • Defining standards for testing process rather than • Describing product tests
Structure of Software Test Plan • Testing process • Requirements traceability • Tested items • Testing schedule • Test recording procedures • Hardware and software requirements • Constraints
Software Inspections • People examine representation of system to find anomalies and defects • May be applied to any representation of system • Requirements, design, test data . . . • Do not require execution of system • Used before implementation • Very effective technique for discovering errors
Inspection Success • In testing, one defect may mask another so several executions are required • Reuse domain and programming knowledge so reviewers are likely to have seen types of error that commonly arise • Thus many different defects may be discovered in single inspection
Inspections and Testing • Inspections and testing are complementary and not opposing verification techniques • Both should be used during V & V process • Inspections can check • Conformance with specification • But not conformance with customer’s real requirements • Inspections cannot check non-functional characteristics • Performance, usability, etc.
Program Inspections • Formalized approach to document reviews • Intended explicitly for defect DETECTION (not correction) • Defects may be • Logical errors, • Anomalies in code that might indicate erroneous condition • (E.g. uninitialized variable) • Or non-compliance with standards
Inspection Pre-Conditions • Precise specification must be available • Team members must be familiar with organization standards • Syntactically correct code must be available • Error checklist should be prepared • Management must accept that inspection will increase costs early in software process • Management must not use inspections for staff evaluations • I.e., finding errors does not necessarily mean programmer is BAD
Inspection Procedure • System overview presented to inspection team • Code and associated documents distributed to inspection team in advance • Inspection takes place and discovered errors noted • Modifications made to repair discovered errors • Re-inspection may or may not be required
Inspection Teams • Made up of at least 4 members • Author of code being inspected • Inspector who finds errors, omissions and inconsistencies • Reader who reads code to team • Moderator who chairs meeting and notes discovered errors • Other roles: • Scribe • Chief moderator
Inspection Checklists • Checklist of common errors should be used to drive inspection • Error checklist is programming language dependent • ‘Weaker’ type checking needs larger checklist • Examples: • Initialization • Constant naming • Loop termination • Array bounds, etc.
Inspection Checks (1) Data Faults • Are all program variables initialized before their values are used? • Have all constants been named? • Should the lower bound of arrays be 0, 1 or something else? • Should the upper bound of arrays be equal to the size of the array or (size – 1)? • If character strings are used, is a delimiter explicitly assigned?
Inspection Checks (2) Control Faults • For each conditional statement, is the condition correct? • Is each loop certain to terminate? • Are compound statements correctly bracketed? • In case statements, are all possible cases accounted for?
Inspection Checks (3) • Input/Output Faults • Are all input variables used? • Are all output variables assigned a value before the are output? • Interface Faults • Do all function and procedure calls have the correct number of parameters? • Do formal and actual parameter types match? • Are the parameters in the right order? • If components access shared memory (globals), do they have the same model of the shared memory structure?
Inspection Checks (4) • Storage Management Faults • If a linked structure is modified, have all links been correctly reassigned? • If dynamic storage is used, has space been allocated correctly? • Is space explicitly deallocated after it is no longer required? • Exception Management Faults • Have all possible error conditions been taken into account?
Inspection Rate Estimating cost of inspection for 500 lines of code: • 500 statements/hour during overview = 1 hr per person x 4 people = 4 person-hours • 125 source statements/hour during individual preparation = 4 hours x 4 people = 16 person-hours • 90-125 statements/hour can be inspected in meeting with 4 people in team = ~5 hours x 4 people = ~20 person-hours • Inspection is therefore expensive process • Inspecting 500 lines thus takes ~ 4 + 16 + 20 = ~40 person-hours • Estimate programmer salary $80K/2K hr ~$40/hr • Multiply by 2 for extended costs = $80/hr • Therefore costs of 40 person-hours effort = ~ $3,200
Automated Static Analysis • Static analyzers = software for source text processing • Parse program text • Try to discover potentially erroneous conditions • Report to V & V team • Effective aid to inspections • Supplement to but not replacement for inspections
Stages of Static Analysis (1) • Control flow analysis • Checks for loops with multiple exit or entry points, finds unreachable code, etc. • Data use analysis • Detects uninitialized variables, variables written twice without intervening assignment, variables which are declared but never used, etc. • Interface analysis • Checks consistency of routine and procedure declarations and their use
Stages of Static Analysis (2) • Information flow analysis • Identifies dependencies of output variables. Does not detect anomalies itself but highlights information for code inspection or review • Path analysis • Identifies paths through program and sets out statements executed in that path. Again, potentially useful in review process • Both these stages generate vast amounts of information. Must be used with care.
138% more lint_ex.c #include <stdio.h> printarray (Anarray) int Anarray; { printf(“%d”,Anarray); } main () { int Anarray[5]; int i; char c; printarray (Anarray, i, c); printarray (Anarray) ; } 139% cc lint_ex.c 140% lint lint_ex.c lint_ex.c(10): warning: c may be used before set lint_ex.c(10): warning: i may be used before set printarray: variable # of args. lint_ex.c(4) :: lint_ex.c(10) printarray, arg. 1 used inconsistently lint_ex.c(4) :: lint_ex.c(10) printarray, arg. 1 used inconsistently lint_ex.c(4) :: lint_ex.c(11) printf returns value which is always ignored LINT Static Analysis
Use of Static Analysis • Particularly valuable for language such as C • Weak typing • Hence many errors undetected by compiler • Less cost-effective for languages like Java • Strong type checking • Can therefore detect many errors during compilation
Cleanroom Software Development • Name derived from 'Cleanroom' process in semiconductor fabrication • Philosophy is defect avoidance rather than defect removal • Software development process based on: • Incremental development • Formal specification • Static verification using correctness arguments • Statistical testing to determine program reliability
Cleanroom Process Characteristics • Formal specification using state transition model • Incremental development • Structured programming • Limited control and abstraction constructs are used • Static verification using rigorous inspections • Statistical testing of system (covered in Ch. 21)(but not in this course)
Formal Specification and Inspections • State-based model = system specification • Inspection process checks program against this model • Programming approach defined so that correspondence between model and system is clear • Mathematical arguments (not proofs) are used to increase confidence in inspection process
Cleanroom Process Teams • Specification team • Develops and maintains system specification • Development team • Develops and verifies software. • Software NOT executed or even compiled during this process • Certification team • Develops set of statistical tests to exercise software after development • Reliability growth models used to determine when reliability acceptable
Cleanroom Process Evaluation • Results in IBM impressive • Few discovered faults in delivered systems • Independent assessment: • Process no more expensive than other approaches • Fewer errors than in ‘traditional’ development process • Not clear how this approach can be transferred to environment with • Less skilled or • Less highly motivated engineers
Key Points (1) • Verification and validation are not same thing. Verification shows conformance with specification; validation shows that program meets customer’s needs • Test plans should be drawn up to guide testing process. • Static verification techniques involve examination and analysis of program for error detection
Key points (2) • Program inspections are very effective in discovering errors • Program code in inspections is checked by small team to locate software faults • Static analysis tools can discover program anomalies which may be indication of faults in code • Cleanroom development process depends on incremental development, static verification and statistical testing
Homework • Required by Wed 17 Nov 2004: • For 32 points • 22.1 – 22.5 (@4) • 22.9 & 22.10 (@6) (think hard) • Optional by Mon 29 Nov 2004 • For up to 25 extra points, write detailed answers for any or all of • 22.6, 22.7 (@10) • 22.8 (@5)