LISD Construction Today October 2013 . Purdue. Projects currently Under Construction Lewisville High School Renovation and Rebuild Lewisville High School Auditorium Westside Aquatics Center Flower Mound High School 9 th Grade Campus
E N D
LISD Construction Today October 2013 Purdue
Projects currently Under • Construction • Lewisville High School Renovation and Rebuild • Lewisville High School Auditorium • Westside Aquatics Center • Flower Mound High School 9th Grade Campus • Flower Mound High School Athletic Fields • Marcus High School 9th Grade Campus
Contractor: Balfour Beatty Construction Architect: SHW Group Project started: September, 2010 Project completion: November, 2013 Lewisville H.S. Renovation and Rebuild Project
Contractor: Balfour Beatty Construction Architect: SHW Group Project started: November, 2012 Project completion: November, 2013 Purdue Lewisville High School Auditorium
Purdue Lewisville High School Auditorium
Contractor: Adolfson and Peterson Construction Architect: SHW Group Project started: November, 2012 Project completion: November, 2013 Westside Aquatics Center
Contractor: Satterfield & Pontikes Construction Architect: PBK Project started : May, 2013 Project completion: Fall, 2014 Flower Mound H.S. 9th Grade Campus
Contractor: Satterfield & Pontikes Construction Architect: PBK Project started: May, 2013 Project completion: Fall , 2013 Flower Mound H.S. Sports Package
Contractor: Satterfield & Pontikes Construction Architect: PBK Project started : May, 2013 Project completion: Fall, 2014 Marcus H.S. 9th Grade Campus
Projects Pending Construction • Camey Elementary School • Open Bids: September, 2013 • Board Approval: October, 2013 • Start Construction: October, 2013 • Substantial completion: November, 2014 • Griffin Middle School • Open Bids: November, 2013 • Board Approval: December, 2013 • Start Construction: December, 2013 • Substantial Completion: June, 2015
Construction Schedule: Project to start: Fall, 2013 Project Completion: Fall, 2014 Main Entry Camey Elementary Rebuild
Construction Schedule: Project to start: Fall , 2013 Project Completion: June , 2015 Griffin Middle School Rebuild
Projects Currently Under Warranty: Marcus HS Athletic Package Under Warranty until April 2014
Contractor: Pogue Construction Architect: PBK Project under warranty until April, 2014 Marcus High School Athletic Package