Challenges to Teamwork: A Multiple Case Study of Two Agile Teams Viktoria Gulliksen Stray, Nils Brede Moe, and Torgeir Dingsoyr 12 th International Conference, XP 2011. 報告者 : 陳勁霖. Problems. Solving the wrong tasks work on tasks without priority . Lack of communication

jase
Download Presentation

報告者 : 陳勁霖

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Challenges to Teamwork: A Multiple Case Study of Two Agile TeamsViktoriaGulliksen Stray, Nils Brede Moe, and TorgeirDingsoyr12th International Conference, XP 2011 報告者:陳勁霖

  2. Problems • Solving the wrong tasks work on tasks without priority. • Lack of communication approach the leader only in the meeting. • Unreleased potential of learning spend little time on improvement.

  3. Research

  4. Design

  5. North • Goal : redevelop a software package • Years using agile : 2 years • Member : two developers one scrum-master one project manager one product owner Product owner and project manager are situated in another city.

  6. Team Orientation • Product owner was often not available. too many project in same time. • The topics discussed often excluded the developers. • Developers worked less than plan. unrealistic plans.

  7. Team Learning • Did not transform their experience into action. • Solve problems in wrong way. 1. isolate the team without scrum-master. 2. work overtime.

  8. South • Goal : develop CMS-system • Years using agile : 10 years • Member : nine developers one project leader one product owner Product owner is situated in another city.

  9. Team Orientation • Members did not know the project plans • Daily meeting was poor efficiency. only discuss what was going on. • Can’t do truck factor.

  10. Team Learning • some problemsis hard to solve. daily meeting is hard to satisfy everyone.

  11. Discussion

  12. Why problems happen? • Solving the wrong tasks unrealistic plans、specialization. solve problems without the leader. • Lack of communication hard to communicate with the leader. • Unreleased potential of learning less experience.

  13. Suggestions & Conclusion – (1) • Transition phase processes 1. allocate enough time, resources. 2. make project more flexible. • Action phase processes 1. without external tasks. 2. create a culture for collaboration. 3. the use of visual boards.

  14. Suggestions & Conclusion – (2) • Interpersonal processes 1. provide forums for conflict resolution. 2. encourage team members to give feedback to each other.

  15. Thank you any question?