Holland Park Renovations Playground & Splash Park Design. James F. Holland Memorial Park Existing Conditions. James F. Holland Memorial Park Project Milestones. 2007 Master Plan Study Completed (updated in 2009 & 2011). 2008 City Council approved contract for design services. 2013
E N D
James F. Holland Memorial ParkProject Milestones • 2007 • Master Plan Study Completed (updated in 2009 & 2011). • 2008 • City Council approved contract for design services. • 2013 • Completion of the design & permitting phase.
MASTER PLAN • Improvements • Replace Utility Infrastructure • Correct Drainage Issues • Enhance Traffic Circulation • Add Parking • Correct ADA Issues • Repair/Renovate existing Structures • New Bocce Ball Court Covering • 2 New Horseshoe Pits • New Enlarged Dog Park • New Enlarged Playground • New Splash Park • New Roadway & Parking Lot Lighting • New Sports Activity Lighting • Perimeter Walking Trail • New Fitness Stations • Landscape & Irrigation Playground & Splash Park Design
PLAYGROUND & SPLASH PARK • City Council Action • City advertised Request for Qualifications (RFQ-CD-CP-14-02) • 3 Qualification Submittals Received. • Littlejohn Engineering Associates, Inc. was selected as the top ranked firm. • City negotiated a scope and fee for an amount of $49,730.00 • December 17, 2013: City Council to consider design contract with Littlejohn Engineering Assoc.