East Area Renovation: Project Team meeting # 29 Feedbacks from the worksites and coordination meetings. East Hall under construction - 1962. Aboubakr Ebn Rahmoun / EN-EA, 28-06-2019. East Area Renovation. Activities overview. Power converter b.251. PS Extraction, F61 b.352. East Hall
E N D
East Area Renovation: Project Team meeting #29Feedbacks from the worksites and coordination meetings East Hall under construction - 1962 Aboubakr Ebn Rahmoun / EN-EA, 28-06-2019 East Area Renovation
Activities overview Power converter b.251 PS Extraction, F61 b.352 East Hall b.157 Project Team #29
General information • Power converter b.251 • Asbestos removal under the old selector ongoing • PS extraction b.352 • The galleries contain asbestos, some part of de-cabling campaign affected • b.157 • Emergency evacuation plan during renovation, with help of Louis-Frederic A. signalisation do be installed • Fence installation on south platform ongoing • From 1 to 5 July no access via door next to CLOUD • Damages during roof renovation & bad weather during June • On the control rooms of IRRAD and CHARM • Beam line T08b, all equipments and electrical services are consigned • Ongoing preparation of an event… Project Team #29
The summer is here So… • Doodle East Area Renovation Project Team #29
Summary Last coordination meeting 26th June, Indico: 830256 • B.157 • Dismantling (primary area) • Buffer area is ready for the dismantling • Test & validation of WDP for each operation (T11) ✅ • Cleaning of area & handling TCX • Storage blocks @157 and magnets @Flex • Floor load validation on pending from HSE • Q100 on CLOUD will be removed soon • Survey between T08B and T09-T10 experiments area done • EN-CV, dismantling on going, manifolds and water pipes • Civil engineering • On south wall, dismantling of scaffolding done. • The roof refurbishment on going, the dismantling of “lanterneau” started • B.352, PS –F61 • Magnets dismantling • Last magnets have been removed and stored in Prevessin b.954 • M100 15t & M200 30t • Transport activities, EN-HE • Trenches will be opened for removing the hoses removal, TE-MSC/EN-EL • EN-CV dismantling on going, manifolds and water pipes 251 & 817 • Next steep, EN-EL (+ build.251&157) Buffer area CLOUD Area preparation run *CLOUD run From 02/09 to 15/11/2019 Project Team #29
Status power converters building • On going asbestos removal, to prepare remaining de-cabling @251, obsolete signal, all interlock and the transformer cables. • Dismantling false floor pending the de-cabling campaign • Inspection by HSE (asbestos) and VIC done to start the de-cabling phase. Project Team #29
PS extraction, F61 Inventaire partie 352 Démantèlement F61 • Déconnexions câbles DC & flexibles ED, TE-MSC, • Déconnexions du vide et enlèvement pompe à vide, TE-VSC/EN-EA • Préparation network, EN-SMM, du 13 au 15/03 • Désinstallation BE-BI, LSD, SEC, BTV’s, TFA, BE-BI/EN-HE, • TREC et évacuation, matériel stockage, déchets en cours • Démontage de la porte secteur, EN-ACE, BE/ICS, • Manutention EN-HE • Etude structurel du sol validé par SMB, • Démontage blindage (coté accès et splitter), évacuation blocs < 24-16-8, Test de charge du pont validé • Désinstallation aimants/équipements et supports F61: Lancement VIC TE-MSC, EN-STI => EN-ACE • Q74 done TE-VSC, MNPA 25, Q120, MEA (DVT1), MEA (DVT2), QFL, Q600, SMH01(SPLITER) • Beam-stopper 01 et 02, EN-STI • Démontage blindage MCB, Dump F61D • MCB, Q120, Q120, MNPA25, M105, blindaccess for MCB transport • M100 M200, démontage prévu fin Mai, blindaccess, pont 25t->30t • EN-CV dismantling manifolds and water pipes b.352 done, 817->352 on going • EN-SMM laser scan + measure on PS magnets • EN-EA Shielding relocation between 157-352 (intersection opening) • EN-EL de-cabling DC & signal cable from 251 to 352 • Analysis of asbestos risk on galleries from PS, EN-ACE & EN-EA • opening trench by EN-HE and hoses removal by TE-MSC Project Team #29
TCX assembly East hall • Primary are dismantling • Vacuum disconnected • Partial removal • T11, magnets BHZ01&02, collimators & beam-stoppers • T09,magnets QDE01, QFO02 & BZH01 • Magnets removed to reduce the ambient dose rate • All instrumentations and the target have been removed • TCX (Collimator for primary targets) • Highly radioactive and most of them (80%) contaminated, different at each layer: • Up to 5 mSv/h contact • 70 to 1400 Bq/cm² (up to 500 x CS limit for Co-60 = 3 Bq/cm²) • Contamination well managed during intervention: RAS on the floor after intervention < 0.4 Bq/cm2 • Very old equipment and little information about configuration • Many different parts and composition, (concrete, iron, lead, no controlled ventilation) Future TCX plug-in Estimation Work Dose Planning 0.5 day, 3 pers. handling and decontamination cleaning + 1 Rp agent 218 person.µSv 98 µSv max. indiv Real intervention 1.5 days, 6 pers. handling and decontamination cleaning + 1 Rp agent 434 person.µSv –well optimized compared to the actual duration 99 µSv max. indiv New DIMR version needed (ongoing) *Courtesy to G. Dumont, B. Lopez & J-F Gruber, HSE-RP Project Team #29
Primary area Project Team #29
EAR Schedule Project Team #29
Questions? East Area Renovation Project Team #29