East Area Renovation: Project Team meeting # 29 Feedbacks from the worksites and coordination meetings. East Hall under construction - 1962. Aboubakr Ebn Rahmoun / EN-EA, 28-06-2019. East Area Renovation. Activities overview. Power converter b.251. PS Extraction, F61 b.352. East Hall

jbass
Download Presentation

Aboubakr Ebn Rahmoun / EN-EA, 28-06-2019

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. East Area Renovation: Project Team meeting #29Feedbacks from the worksites and coordination meetings East Hall under construction - 1962 Aboubakr Ebn Rahmoun / EN-EA, 28-06-2019 East Area Renovation

  2. Activities overview Power converter b.251 PS Extraction, F61 b.352 East Hall b.157 Project Team #29

  3. General information • Power converter b.251 • Asbestos removal under the old selector ongoing • PS extraction b.352 • The galleries contain asbestos, some part of de-cabling campaign affected • b.157 • Emergency evacuation plan during renovation, with help of Louis-Frederic A.  signalisation do be installed • Fence installation on south platform ongoing • From 1 to 5 July no access via door next to CLOUD • Damages during roof renovation & bad weather during June • On the control rooms of IRRAD and CHARM • Beam line T08b, all equipments and electrical services are consigned • Ongoing preparation of an event… Project Team #29

  4. The summer is here So… • Doodle East Area Renovation Project Team #29

  5. Summary Last coordination meeting 26th June, Indico: 830256 • B.157 • Dismantling (primary area) • Buffer area is ready for the dismantling • Test & validation of WDP for each operation (T11) ✅ • Cleaning of area & handling TCX • Storage blocks @157 and magnets @Flex • Floor load validation on pending from HSE • Q100 on CLOUD will be removed soon • Survey between T08B and T09-T10 experiments area done • EN-CV, dismantling on going, manifolds and water pipes • Civil engineering • On south wall, dismantling of scaffolding done. • The roof refurbishment on going, the dismantling of “lanterneau” started • B.352, PS –F61 • Magnets dismantling • Last magnets have been removed and stored in Prevessin b.954 • M100 15t & M200 30t • Transport activities, EN-HE • Trenches will be opened for removing the hoses removal, TE-MSC/EN-EL • EN-CV dismantling on going, manifolds and water pipes 251 & 817 • Next steep, EN-EL (+ build.251&157) Buffer area CLOUD Area preparation run *CLOUD run From 02/09 to 15/11/2019 Project Team #29

  6. Status power converters building • On going asbestos removal, to prepare remaining de-cabling @251, obsolete signal, all interlock and the transformer cables. • Dismantling false floor pending the de-cabling campaign • Inspection by HSE (asbestos) and VIC done to start the de-cabling phase. Project Team #29

  7. PS extraction, F61 Inventaire partie 352 Démantèlement F61 • Déconnexions câbles DC & flexibles ED, TE-MSC, • Déconnexions du vide et enlèvement pompe à vide, TE-VSC/EN-EA • Préparation network, EN-SMM, du 13 au 15/03 • Désinstallation BE-BI, LSD, SEC, BTV’s, TFA, BE-BI/EN-HE, • TREC et évacuation, matériel stockage, déchets en cours • Démontage de la porte secteur, EN-ACE, BE/ICS, • Manutention EN-HE • Etude structurel du sol validé par SMB, • Démontage blindage (coté accès et splitter), évacuation blocs < 24-16-8, Test de charge du pont validé • Désinstallation aimants/équipements et supports F61: Lancement VIC TE-MSC, EN-STI => EN-ACE • Q74 done TE-VSC, MNPA 25, Q120, MEA (DVT1), MEA (DVT2), QFL, Q600, SMH01(SPLITER) • Beam-stopper 01 et 02, EN-STI • Démontage blindage MCB, Dump F61D • MCB, Q120, Q120, MNPA25, M105, blindaccess for MCB transport • M100 M200, démontage prévu fin Mai, blindaccess, pont 25t->30t • EN-CV dismantling manifolds and water pipes b.352 done, 817->352 on going • EN-SMM laser scan + measure on PS magnets • EN-EA Shielding relocation between 157-352 (intersection opening) • EN-EL de-cabling DC & signal cable from 251 to 352 • Analysis of asbestos risk on galleries from PS, EN-ACE & EN-EA • opening trench by EN-HE and hoses removal by TE-MSC Project Team #29

  8. TCX assembly East hall • Primary are dismantling • Vacuum disconnected • Partial removal • T11, magnets BHZ01&02, collimators & beam-stoppers • T09,magnets QDE01, QFO02 & BZH01 • Magnets removed to reduce the ambient dose rate • All instrumentations and the target have been removed • TCX (Collimator for primary targets) • Highly radioactive and most of them (80%) contaminated, different at each layer: • Up to 5 mSv/h contact • 70 to 1400 Bq/cm² (up to 500 x CS limit for Co-60 = 3 Bq/cm²) • Contamination well managed during intervention: RAS on the floor after intervention < 0.4 Bq/cm2 • Very old equipment and little information about configuration • Many different parts and composition, (concrete, iron, lead, no controlled ventilation) Future TCX plug-in Estimation Work Dose Planning 0.5 day, 3 pers. handling and decontamination cleaning + 1 Rp agent 218 person.µSv 98 µSv max. indiv Real intervention 1.5 days, 6 pers. handling and decontamination cleaning + 1 Rp agent 434 person.µSv –well optimized compared to the actual duration 99 µSv max. indiv New DIMR version needed (ongoing) *Courtesy to G. Dumont, B. Lopez & J-F Gruber, HSE-RP Project Team #29

  9. Primary area Project Team #29

  10. EAR Schedule Project Team #29

  11. Questions? East Area Renovation Project Team #29