1 / 11

Ground Safety Status

Ground Safety Status. Ground Safety Process. Prior to handling hardware or processing at KSC, NASA requires that all hardware and operations be reviewed and approved through the Ground Safety Process Similar to the Three Phase Flight Safety Process

jemima
Download Presentation

Ground Safety Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ground Safety Status AMS-02 Technical Interchange Meeting - JSC - January 2007

  2. Ground Safety Process • Prior to handling hardware or processing at KSC, NASA requires that all hardware and operations be reviewed and approved through the Ground Safety Process • Similar to the Three Phase Flight Safety Process • Must be completed and certified prior to hardware shipment to KSC • Ground Safety Data Package (GSDP) relies heavily on the Flight Safety Package (FSP). • Phase I GSDP submitted Feb 2002 AMS-02 Technical Interchange Meeting - JSC - January 2007

  3. Current Plan for the GSDP • Identify all hazards associated with the Ground Support Equipment (GSE) • Example: Assembly/disassembly of hardware • Operational Hazards • Identify hazards specific to locations the GSE will be used. • Example: Hazard Analyses for the different locations the GSE will be used • Identify Integrated Hazards • Example: GSE fluids become contaminated, thus contaminated fluids enter Flight Hardware AMS-02 Technical Interchange Meeting - JSC - January 2007

  4. Hazard Summary • Examples of some hazards • Failure of Lifting Equipment • Structural Failure • Flammability • Sharp Edges • Touch Temperature • Electrical Shock • Major Hazards to be addressed • Pressure Systems • Asphyxiation • Contamination of Flight fluids by GSE • Bonding/Grounding of hardware while on the pad AMS-02 Technical Interchange Meeting - JSC - January 2007

  5. Information Needed to Complete GSDP • Procedures • Each location and operation • Assembly/Disassembly • Transportation • Testing/Operations • Identify which procedures are deemed hazardous • Most will be, GSE is cryogenic. • Drawings, Schematics and Photographs • Electrical Power Distribution Circuitry (EPDC) • Pressure Systems tables (similar to tables located in AMS-02-F03 and AMS-02-05) • Build Drawings AMS-02 Technical Interchange Meeting - JSC - January 2007

  6. Information Needed to Complete GSDP • List of all safety related anomalies or failures • Damage during shipping • Test failures • Damage during assembly/disassembly • Test TPS • Material Certifications • List of Collaboration Members and planned tasks during GSE Operations • Load ratings, capabilities and safety factor of lifting equipment being used at KSC AMS-02 Technical Interchange Meeting - JSC - January 2007

  7. Status of the GSDP • Phase I completed in 2002 • Phase I/II GSDP NLT Fall 2007 • Hazards identified, Hazard Reports currently being written • Text portion of GSDP currently being updated • Ground Safety Data Package relies heavily on the Flight Safety Package • Phase III ECD Early 2008 AMS-02 Technical Interchange Meeting - JSC - January 2007

  8. Forward Work • Continue working with KSC GSRP. • Identify all documents required • Identify all training/certifications for personnel • Complete the Phase II and III GSRP Reviews • Determining what classes, training and certifications the International Collaboration members are required to have in order to gain access to KSC. • Ex: Hazardous Communication AMS-02 Technical Interchange Meeting - JSC - January 2007

  9. Forward Work • Continue working with the AMS Project • Identifying ALL GSE to be used at KSC • Both AMS and KSC provided hardware • tools, equipment, computers, etc • Identifying procedures to be conducted at KSC • Identifying hazards, controls and verifications for all operations of AMS at KSC • Support GSE Testing • Generate list of Collaboration partners and their Certifications for accessing KSC and operating on the GSE and Flight Hardware AMS-02 Technical Interchange Meeting - JSC - January 2007

  10. Current HRs • Failure of AMS Lifting Equipment • Structural Failure during Ground Ops • Magnetic Field causes injury/damage to vehicle, flight hardware or surrounding structures • Flammability/Toxicity • Sharp Edges • Electrical damage to facilities, orbiter or other equipment • Shock to Ground Personnel • Electrical Short causes fire • Touch Temperature exceedance • Rupture of pressurized components • Failure of Servicing lines • Exposure to high pressure venting gases • Asphyxiation • Ionizing Radiation • Inadvertent tipping of ground hardware • JSC 1230 form AMS-02 Technical Interchange Meeting - JSC - January 2007

  11. CONTACT INFORMATION Arthur Nelson, Jr. ESCG/Jacobs AMS-02 Ground Safety Engineer 281 461 5134 Arthur.NelsonJr@escg.jacobs.com AMS-02 Technical Interchange Meeting - JSC - January 2007

More Related