Summary of Data Handling Meeting:DAQ and Controls LHCb Plenary Meeting 17 September 1998 Beat Jost Cern/EP
Contents • Introduction • Summary of DAQ activities • Readout Unit Project • Event Building Project • TFC Project • Event Filter Farm • Controls
LHC-B Detector Data rates VDET TRACK ECAL HCAL MUON RICH 40 MHz Level 0 Trigger 40 TB/s 1 MHz Front-End Electronics Timing & Fast Control L0 Fixed latency 3.2 ms 1 TB/s 40 kHz L1 Level 1 Trigger Front-End Multiplexers (FEM) 1 MHz LAN Front End Links Variable latency <256 ms 4 GB/s RU RU RU Read-out units (RU) Read-out Network (RN) 2-4 GB/s CPU CPU CPU CPU Trigger Level 2 & 3 Event Filter SFC SFC Sub-Farm Controllers (SFC) Variable latency L2 ~10 ms L3 ~200 ms Control & Monitoring Storage 20 MB/s Introduction:DAQ Architecture
Introduction:Hardware Components • Hardware Components • Timing and Fast Control (TFC) • Front-End Multiplexers (FEM) • Readout Units (RU) • Event Building Network • Sub-Farm Controllers • Filter Farm }Event Building Strategy
Readout Unit Project • Architecture
Readout Unit • Input Stage blowup
32 Bits 32 Bits Event Number Event Number Event Number Data Size Data Size Data Size Data 1 Source Id Source Id Source Id Data 2 Data 1 Data 1 ... Data 2 Data 2 Data n ... ... Data 1 Data n Data m Data 2 Status CRC Status CRC Status CRC ... Data m Readout Unit • Data Formats • It is assumed that the data is self-describing
Event-Building Project • Aim is to devise an event building strategy for LHCb • Activities • Evaluation of Myrinet • 2 PCI Interfaces and one switch ordered • Material received • 2 PCs ordered • 1 received • Modeling of Myrinet (Finnish Students) • Reproduced Results (obtained using Ptolemy) with Foresight • Small systems (4x4) for the time being • Other technologies will also be evaluated if necessary
Timing and Fast Control (TFC) • Technical note in preparation (ready end of the month?) • General Architecture • Readout Supervisor Block Diagram We need to find manpower to put into the TFC sub-system
Event Filter Farm • Common project between LHC experiments being set up • LHCb participation is currently very minor (~0), we are just following the activities. More active participation would probably be welcome….
Controls • Joint Project between LHC Experiments and IT/CO • Finished or currently active of sub-projects • Technology Market Survey of available commercial Control Systems • Supervisory Control And Data Acquisition (SCADA) tools • Choice of Test Stand facilities for in-depth evaluation • Architecture Design for Experiment Control Systems (including DAQ Controls) • Level 3 Alarm Transmission at CERN • Small Hands-On Projects • ATLAS TRT gas system test setup : WAGO + I/O modules via Profibus • ALICE HPMID Cooling System: Siemens PLCs and Bridgeview • CANbus evaluation (especially in view of preferences inside Atlas - LMBs) • Eye on Fieldbuses in General • Continuing Study of Use of PLCs (contacts with Working group on PLCs, which has issued recommandations for 3 brands of PLCs for CERN)
Controls • Identified future sub-projects • Standardization of High Voltage Controls • Evaluation of the OPC (OLE for Process Control) Standard • Feasibility Study for ComponentWare • Magnet Controls • Rack Controls • Communication with LHC • pre-alarms (things leading to emergencies) • environment parameters (temperatures, leaks, opacity (=smoke),…) • machine parameters
Controls • General State of Health of Joint Project • Project is gaining momentum and real work is being done. Cause for (guarded) optimism that a joint Control System can be done. • What is required from the LHCb collaboration? • Quite some experience from LEP experiments available in the JCOP project, so the standard control questions for an LHC exp. well answered. The URD that was produced for ALICE/LHCb serves as a basis. • BUT: in case of specific control needs or specific hardware equipment that you expect to use, please keep in contact with Pere or Wolfgang. Please do NOT postpone this issue until later … and later… • and…any participation in joint project and its sub-projects very welcome
Conclusion • DAQ Hardware • good progress in RU project • starting activity on event building • need manpower for TFC • more participation in Filter Farm project welcome • Software, I.e. Controls • Joint project seems to be in good shape • LHCb involved in a number of sub-projects • new sub-projects being launched • external participation welcome • Plan to organize a DAQ/Controls Workshop in near future