C(14). E(11). A(7). H(4). D(5). F(7). I(18). B(5.3). G(11). Example 2. Network. ES=7 EF=21. ES=21 EF=32. Duration = 54 Days. ES=0 EF=7. ES=32 EF=36. LS=7 LF=21. LS=21 LF=32. ES=7 EF=12. ES=12 EF=19. LS=0 LF=7. LS=32 LF=36. ES=36 EF=54. LS=20 LF=25. LS=25 LF=32.
E N D
C(14) E(11) A(7) H(4) D(5) F(7) I(18) B(5.3) G(11) Example 2. Network ES=7 EF=21 ES=21 EF=32 Duration = 54 Days ES=0 EF=7 ES=32 EF=36 LS=7 LF=21 LS=21 LF=32 ES=7 EF=12 ES=12 EF=19 LS=0 LF=7 LS=32 LF=36 ES=36 EF=54 LS=20 LF=25 LS=25 LF=32 ES=0 EF=5.3 ES=5.3 EF=16.3 LS=36 LF=54 Critical Path: A-C-E-H-I LS=19.6 LF=25 LS=25 LF=36