Prioritizing R&D Activities in Construction Project: NGNP Lessons Learned. David Petti Director, VHTR Technology Development Office. April 2011. Outline. Requirements Definition Risk Management Technology Development Roadmaps Technology Readiness Level Examples R&D Plans Schedules

jeri
Download Presentation

Prioritizing R&D Activities in Construction Project: NGNP Lessons Learned

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Prioritizing R&D Activities in Construction Project: NGNP Lessons Learned David Petti Director, VHTR Technology Development Office April 2011

  2. Outline • Requirements Definition • Risk Management Technology Development Roadmaps • Technology Readiness Level Examples • R&D Plans • Schedules • Execution

  3. Understanding Requirements is Critical

  4. Risk Management • Technology Development Roadmaps • Identifies key risks for each technology • Uses technology readiness levels to map activities onto readiness scale • Uses technology development activities to establish a roadmap timeline • Links successful completion of specific activities that mitigate key risks • Increases readiness while reducing risk

  5. How Much Risk is Acceptable? Probability Consequence

  6. Design maturity aligned to technology readiness to reduce risk

  7. R&D Plans • For each component/system/technology develop a detailed plan of activities required to move the technology from where it is today to where it needs to be for the project • Develop detailed schedule of activities • Develop associated resources required for the activities • Develop durations for each activity Thus, you have a resource-loaded life-cycle schedule for each piece of R&D • Update as needed

  8. Sample high level fuel schedule

  9. TDRM for Fuels as an Example

  10. Development of Project Schedule Engineering • Establish WBS, WBS Dictionary etc. • Link all R&D life-cycle schedules into the master project schedule • Develop interfaces between R&D activities and key project drivers: • Data needed for preliminary and final design • Data for design verification • Data for safety analysis/licensing • This is an enormous time-intensive activity to make sure everything is correct • Schedule might be 20 to 50 pages long depending on level • Overly simplified schedule developed from detailed PRIMAVERA schedule R&D Licensing

  11. Optimize the Schedule to Meet Project Objectives and then Execute • Understand critical paths • If cannot meet key project deadlines, iterate • Can more money reduce schedule duration? • Can different approaches reduce duration? • Can activities that are in series be done in parallel to reduce schedule? • Can Project live with the delay? • Having well thought out plans can help this a phase a lot • Plan the work and work the plan. This is the hard part… • Using earned value management as a tool to communicate status to higher level management

  12. Prioritization • Based on critical path and state of the technology • In some cases R&D can proceed in advance of the design (qualifying operating envelopes for fuels, graphite and materials) and in other cases the design needs to proceed the R&D • Low TRLs (e.g. IHX for NGNP) will require a lot of time to develop and is thus high risk • Neutrons – testing of irradiated components take a long time given the limited number of reactors and hot cells

  13. Using TDRMs to advance TRLs and reduce risk