1 / 9

Automated Testing Plan

BCS Top-Off Interlock. Automated Testing Plan. Automated Testing Plan (Overview). The SPEAR control system has access to a large number of “test points” and status information of the BCS Top-Off Interlock. All outputs of the summary chassis Output status of all threshold detectors

jhankins
Download Presentation

Automated Testing Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BCS Top-Off Interlock Automated Testing Plan SSRL BCS Top-Off Review February 15th, 2008

  2. Automated Testing Plan(Overview) • The SPEAR control system has access to a large number of “test points” and status information of the BCS Top-Off Interlock. • All outputs of the summary chassis • Output status of all threshold detectors • The SPEAR control system controls all power supplies and monitors the SPEAR beam current. SSRL BCS Top-Off Review February 15th, 2008

  3. Automated Testing Plan(Power Supply Verification) • The control system • Gets updated readbacks somewhat faster than every second • Ramps the individual supplies with a slope that allows measurement of voltage and current within the required precision • Verifies the measured trip currents and voltages against correct trip values • Verifies the status changes on the summary chassis for the individual power supply thresholds • Maintains the correct trip levels in a database SSRL BCS Top-Off Review February 15th, 2008

  4. Automated Testing Plan(Power Supply Verification) current/voltage upper thresholds nominal value lower thresholds chain A (V): F T F chain B (V): F T F chain A (I): F T F T F chain B (I): F T F T F 0 0 time SSRL BCS Top-Off Review February 15th, 2008

  5. Automated Testing Plan(TOSCI Verification) • The control system • Monitors the beam current during every fill from zero • Verifies the TOSCI chassis by comparing the measured DCCT beam current at the TOSCI state change times with the correct current value • maintains the correct trip levels in a database SSRL BCS Top-Off Review February 15th, 2008

  6. Automated Testing Plan(TOSCI Verification) DCCT beam current threshold chain A (DCCT): F T chain B (BPM): F T 0 0 time SSRL BCS Top-Off Review February 15th, 2008

  7. Automated Testing Plan(Reporting and Actions) • The control system will generate a printed report for each verification (e-mails can also be sent) • In case of detected anomalies (non-functioning signal chains or threshold deviations), the control system will apply a fault to the summary chassis and will NOT allow a summary chassis reset. SSRL BCS Top-Off Review February 15th, 2008

  8. Non BCS Interlock(Control System Components) BTS Stoppers and Chopper Power Supply Power Supply Controller (EtherPSC) BCS High Speed Fan In Server 1 (Interlock) Server 2 (Watchdog) IOC Software Interlock Database Interlock Limits (password protected) Modification Log SSRL BCS Top-Off Review February 15th, 2008

  9. Non BCS Interlock(Management) • The limits can be modified by authenticated and authorized personal via a web interface. • Any limit modification will be logged in the database (name, timestamp, value). • The log is accessible via a web interface. SSRL BCS Top-Off Review February 15th, 2008