640 likes | 863 Views
Spliced Girders A Producer’s Perspective. by Chad Saunders Chief Engineer Bayshore Concrete Products presented at the Virginia Concrete Conference Richmond, Virginia March 11, 2005. Bayshore Concrete Products Cape Charles, VA.
E N D
Spliced GirdersA Producer’s Perspective by Chad Saunders Chief Engineer Bayshore Concrete Products presented at the Virginia Concrete Conference Richmond, Virginia March 11, 2005
Bayshore Concrete ProductsCape Charles, VA 90 acre casting facility on Cape Charles Harbor and Chesapeake Bay
The shape. How did we get here? PCEF Prestressed Concrete Committee for Economic Fabrication • A committee established by FHWA for economic fabrication of prestressed/precast concrete • Consists of Mid Atlantic states
PCEF Cross Section Variability 6” 7” 8” Different web thicknesses = diff. soffit
PCEF Cross Section Variability 58” 59” 60” 12” wider top flange = same side form with blockout removed
VDOT PCBT • 32” bottom flange width • 7” thick bottom flange • 7” web • 47” top flange width
Rte 123 over the Occoquan RiverFairfax and Prince William Counties VDOT’s first PCBT spliced girder bridge
Location Close proximity to I-95 and Route 1 = detour = high traffic
Town of Occoquan Affluent neighborhood = pressure for aesthetic design
Who’s Who • Owner – VDOT • Designer – Moffatt & Nichol • General Contractor – Archer Western • Erection Engineer – McNary Bergeron • Precast – Bayshore Concrete Products • PT Hardware - VSL
Erection plan Approach Girders (4 spans) End Span Haunch Drop In Haunch End Span
Bridge Cross Section At Haunch Piers Other piers
Concrete • Concrete – 28 day: 8000 psi • Concrete - release: 5800 psi • Low permeability • Release strength cylinders matched cured
Approach Girders • 4 span unit • Pieces: 58 total beams • Type: PCBT-77 • Length: 144 ft • Weight: 73 tons • Strand: 0.6” LRS • Cast two per pour Cross section
Approach Girder Casting setup Gravity abutment to withstand prestress force Conventionally prestressed with draped strands
Maturity meter testing Research for more accurate prediction and control of camber by VA Tech
Forms and casting Side forms with fall protection rail Placing concrete with Tuckerbuilt
Storage 300 ton twin gantry crane in background
Spliced Girders End span • Pieces: 28 total beams • Length: 127 ft • Weight: 88 tons Haunch • Pieces: 28 total beams • Length: 98.5 ft • Weight: 77 tons Drop-In • Pieces: 14 total beams • Length: 137 ft • Weight: 87 tons
Special form needs End span and Drop-In • 34” soffit • (4) sections of end block form (end span only) • Extra 2” angle full length of side forms to create 6” thick top flange Haunch • Complete form system including soffit and side forms Approach • Standard PCBT-77
Erection Sequence Temporary support Erect haunch segment then end span segment Back span = 185 ft Erect drop-in segment Main span = 225 ft
Erection Sequence Make closures and begin PT Remove strong backs Cast deck and complete PT
End Span and Drop Incross sections Type: Modified PCBT-77 Depth: 79” Strand: 0.6” LRS Variations: 6” thick top flange 9” wide web for PT tendons = 34” wide bottom flange & 49” wide top flange Cast two per pour End Span and Drop-In End Block at End Span
End Span end condition PT ducts: (3) 4” OD for 0.6” LRS Extremely congested area due to bursting reinforcement
End Span and Drop-In connection at splice with haunch Very congested area due to splice plates with welded rebar and projecting rebar
Casting setup Ducts in place Setting ducts
End block Up close near anchorage Horizontal reinforcement
End block Termination of end block Pre-assembly of end cages
Splice End Top splice plates Bottom plates and projecting bars
Haunch Type: Modified PCBT-77 Depth: varies from 79” to 12’-6” Strand: 0.6” LRS Variations: 6” thick top flange 9” wide web for PT tendons = 34” wide bottom flange & 49” wide top flange Cast one per pour
Haunch Challenges: • 12’-6” depth at midpoint = extreme height full length • Most strands located in top flange • Location of the PT tendons makes concrete placement and consolidation difficult = addition of pour windows • Extra setup required for storing and handling of variable depth side forms and beams NTS nts
Grout vents Top Splice Plate
Look at the view from up here. Pouring with buckets
First casting is a success Girder bracing
Shipping • All beams to be shipped by barge starting early April 2005
Erection Phase I – setting beams from the existing bridge
Erection Phase II – setting beams from the phase I bridge
Lessons learned • Producer - Seek possible use of SCC concrete for heavily congested area • Contractor - Get “construction engineer” involved early to ensure means and methods are established (i.e. temporary bracing embedments, special lifting requirements, strong back design, etc.) • Engineer - Require complete shop drawings from PT supplier • DOT – consider having a notch in back span girder(s) designed and included in plans to ensure maximum flexibility in construction sequence
Rte 33 over the Pamunkey RiverWest Point and New Kent County What’s Next?