An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 7 Inventory Management II Stochastic Models

  2. Supplier Customer Supply-Demand Management Relationship Relationship "Make, Move, Store" Management Management Plant "Buy" "Sell" Plant Warehouse Customers Suppliers Plant Managing the store side of a business

  3. Key questions • What is the cost trade-off captured by the single period model (SPM)? • In what settings is SPM analysis appropriate, & how can an order quantity be determined? • What is the definition of base stock level, & how does a base stock policy answer the questions of when & how much to order? • In what settings may a base stock policy be reasonable, & how can base stock be determined? • How do (Q, R) & (I, S) policies answer the questions of when & how much to order, when is each policy appropriate, & how can the values of policy parameters be determined ? • What is the difference between fill rate & service level, and how do these performance measures depend on policy parameters? • How can the return on investments to reduce uncertainty be estimated? • What are the managerial insights from the chapter?

  4. Road map • Fundamental Problem Type #2 • Single Period Model • Policies for When & How Much • Summary

  5. Trade-off Fundamental problem #1 From Chapter 6 • Need to pick a number • Economic incentives for picking a large number • E.g., transaction costs • Economic disincentives if number is too large • E.g., inventory carrying costs

  6. Trade-off Fundamental problem #2 • Need to pick a number • There are costs if the number is too high • Excess costs • There are costs if the number is too low • Shortage costs

  7. Trade-off A common trade-off • How many newspapers to order at a corner newsstand when demand is uncertain? • Cost of unsold newspapers versus cost of lost profit if not enough • How much capacity to reserve for a new line of summer wear when market potential is uncertain? • Cost of reserving unneeded capacity versus premium cost of secondary supplier if there is not enough capacity • How many extra seats to sell (overbook) when the # of no shows is uncertain? • Cost of compensating passengers to give up ticket versus lost opportunity to make a profit on an empty seat

  8. Road map • Fundamental Problem Type #2 • Single Period Model • Policies for When & How Much • Summary

  9. Single Period Model How many newspapers to order? • You are a newsvendor with some information • D = demand on Monday ~ Uniform[50,100] • Selling price = p = $1.00/paper • Purchase cost = c = $0.80/paper • Salvage value/paper (what you can get for a leftover paper) = s • What would you order if s = $0.80, s = $0.60, s = $0.60+?

  10. Single Period Model Concept of service level • For each order quantity Q, there is an associated service level (SL) • Relationship: P[D Q] = SL • Service level is the probability that we will have enough papers to satisfy all demand • E.g., what is SL if Q = 100, Q = 75 in the example? • What is the “best” long run service level if the excess cost per unit matches the shortage cost per unit?

  11. Single Period Model Balance point Optimal service level = service level with least expected cost Suppose ce = excess cost rate = 1, cs = shortage cost rate = 4: balance point at 4/5 = 80%  SL* = cs/(cs+ce) = optimal probability that will satisfy all demand = optimal service level = 4/5 = 0.8 1 4 0 .8 1

  12. Single Period Model Finding Q, given a service level target Want Q consistent with P[DQ] = SL 1. Continuous distributions for demand 1a. Uniform distribution, D ~ U[a,b] Area = SL Q = a + SL(b-a) a Q b

  13. Single Period Model Finding Q, given a service level target Want Q consistent with P[DQ] = SL 1. Continuous distributions for demand 1b. Normal distribution, D ~ N(D, D2) Area = SL Q = D + zSLD

  14. Single Period Model Finding Q, given a service level target 2. Discrete distributions for demand 2a. General discrete distribution xP[D=x] P[Dx] 10 10% 10% 20 30% 40% 30 30% 70% 40 30% 100% If SL* = 70%, then Q = ? If SL* = 75%, then Q = ? Round up: Q = 40 gives lower expected cost than Q = 30

  15. Single Period Model What have we just seen anyway? Analysis using the single period model Characteristics • Order or production quantity decision for a single period • Demand is unpredictable • There is cost for guessing high & for guessing low, & cost is proportional to deviation A fundamental & widespread problem type • Traced back to economist Edgeworth (1888) who applied to bank cash-flow planning • Spotting arbitrage opportunities in the stock market, dynamic product pricing, yield management, civil engineering,...

  16. Single Period Model Example – Sport Obermeyer Fisher, Hammond, Obermeyer, & Raman, Harvard Business Review cs = shortage cost/unit (e.g., gross margin) = $14.50 ce = excess cost/unit (e.g., cost less mark down) =$5.00 D ~ N(1200, 1302) SL* = cs/(cs+ce) = 14.5/(14.5 + 5)  0.743 From probability table, z0.74215 = 0.65 Q* = D + zSL*D = 1200 + 0.65(130) = 1,285  produce 1,285 parkas for upcoming season

  17. Road map • Fundamental Problem Type #2 • Single Period Model • Policies for When & How Much • Base stock • (Q, R) • (I, S) • Summary

  18. When & How Much - Base Stock Base stock policy A simple policy for answering when & how much • Whenever demand occurs, place an order to replenish the demand quantity • Is this a push or pull approach? • Base stock level = on hand + on order • If the policy defined above is strictly followed, then the base stock level is the same at any time • The answer to when? • Whenever demand occurs • The answer to how much? • Whatever demand was

  19. When & How Much - Base Stock Example – cash management • Background from Chapter 6: transfer fee = $25, high & low yield rates = 8% & 1%, D = $900,000/year • What concession did we get from the bank to make this policy a viable option? • D = $4,000/day (225 working days), L = lead time = 3 days • Suppose there is no variability in demand • Suggestions for the base stock level? • A picture on the board...

  20. When & How Much - Base Stock Optimal base stock level S* Back to fundamental problem #2 • With uncertainty • LD = demand during lead-time (uncertain) • Mechanics are same as single period model • S* satisfies P[LD S*] = SL* where SL* = cs/(cs + ce) • E.g., LD ~ N(12000, 10002), ce = 0.07, cs = 0.08 • SL* = 0.08/(0.08+0.07) = 0.5333 & z0.53586= 0.09 • S* = LD + zSL*(LD) = 12000 + 0.09(1000) = 12,090

  21. When & How Much Transition to alternative policies Two common variants of a pure base stock policy • Appropriate when there are benefits from fewer transactions, e.g., as a bar owner, it’s not especially practical to place an order every time someone buys a beer 1.Continually track sales - inventory reaches 10 cases, place an order for 15 cases • A (Q, R) policy, e.g., Q = 15 cases, R = 10 cases 2. Every Friday, we place an order for what was sold during the week (to bring on-hand + on-order up to 25 cases) • An (I, S) policy, e.g., I = 7 days, S = 25 Continuous review policy Periodic review policy

  22. Road map • Fundamental Problem Type #2 • Single Period Model • Policies for When & How Much • Base stock • (Q, R) • (I, S) • Summary

  23. When & How Much – (Q,R) (Q, R) policy • Continually track sales • When inventory reaches 10 cases, we place an order for 15 cases—is an example of a (Q,R) policy • Q = 15 = order quantity - reflects a balance of scale economies with associated costs • Fundamental problem #1 • R = 10 = reorder point - raises the number guessing issue • Fundamental problem #2

  24. When & How Much – (Q,R) Questions • Suppose demand is constant at $4,000/day in cash management problem (recall L = 3 days) • Suggestions for R assuming we aren’t worrying about the possibility of a negative balance? • What if demand is uncertain?

  25. When & How Much – (Q,R) Concept of fill rate • Reorder point could based on • service level target, or • a fill rate target • Fill rate = proportion of demand shipped on time (e.g., shipped from stock) • A common performance measure in industry • Lands’ End: 90% (ship within 24 hours) • Frito Lay: 99.5% (scanner data  forecasts R’s)

  26. When & How Much – (Q,R) Cash management example • Q = $25,000, D = $4,000/day, target FR = 98% • This means an average of (0.02)(4000) = $80 written out of negative balance per day • Q = $25,000 = average demand between receipt of funds • For 98% fill rate target, this means*… • Q(1-FR) = 25,000(0.02) = $500 = average negative balance when cash arrives *As long as there is no chance that demand during the leadtime will be greater than R+Q

  27. When & How Much – (Q,R) Example continued Suppose the estimated distribution of demand during lead-time is: xP[LD=x] What is the fill rate if R = $12,000? $10,000 10% $11,000 15% Average negative balance = 10%(0) + 15%(0)+ $12,000 50% 50%(0) + 15%(1000) + 10%(2000) = $350 $13,000 15% $14,000 10% 350/25000 = 1.4% FR = 98.6% Another view: Q = $25,000  36 transactions/year (36 = 900K/25K)  (36)($350) = $12,600 = average amount/year written out of negative balance  $12,600/$900,000 = 1.4% FR = 98.6%

  28. When & How Much – (Q,R) Example continued Suppose LD ~ N(LD,LD2), LD=12,000, LD2=4,0002 Reorder point can be expressed as R = LD + buffer stock1 = LD + zLD What value of z is consistent with FR = 98%? 1buffer stock & safety stock mean the same thing

  29. When & How Much – (Q,R) Example continued We can use the unit normal loss table (G(z) in Appendix 4) • From normal, R = LD + zLD & LD = 12000LD = 4000 • Just need the value of z • Can use the approximation formula: Q(1-FR)/LDG(z) = standardized average number of units short upon receipt of order • Know Q = 25000, FR = 0.98, & LD = 4000 • So Q(1-FR)/LD = $25000(1-0.98)/4000 = 500/4000 = 0.125 = G(z) • From table, G(0.78) = 0.1245, G(0.77) = 0.12669, so z = 0.78 or 0.77 • Plugging it in: R = LD + zLD = 12000 + (0.78)4000 = $15,120

  30. What is impact if able to cut uncertainty in half while FR is unchanged? FR = 0.98 = 1 - 0.02  1 – LDG(z)/Q LD = 4000 to LD = 2000  G(z) = 0.125 to G(z) = 0.25 (for constant FR) G(z) = .25  z  0.32 safety stock = zLD= (0.32)(2000) = 640 From 3120 to 640  80% reduction in safety stock What is impact if able to cut uncertainty in half while SS is unchanged? safety stock = zLD= (0.78)(4000) = 3120 LD = 4000 to LD = 2000  z = .78 to z = 1.56 (for constant SS) z = 1.56  G(z) = G(1.56) = 0.02552 From G(.78) = 0.1245 to G(1.56) = 0.02552  79.5% reduction in “standardized” backorder rate FR 1 – LDG(z)/Q = 1 – (2000)(0.02552)/25000 From FR = 98% to FR = 99.8%, or 90% reduction in backorder rate When & How Much – (Q,R) Example 2 – estimating ROI • In previous example, • safety stock = R - LD = zLD= 15,120 – 12,000 = 3,120 • LD = 4000, z = 0.78, Q = 25,000, & fill rate = FR = 98% Remaining step is compare cost with savings and/or profit increase

  31. When & How Much – (Q,R) Fill rate - buffer stock Q = 750, LD = 1,000,& buffer stock = zLD = z(1000) Managerial Insight:Each percentage increase in fill rate requires an increasing incremental investment in inventory

  32. Road map • Fundamental Problem Type #2 • Single Period Model • Policies for When & How Much • Base stock • (Q, R) • (I, S) • Summary

  33. (I, S) policy When & How Much – (I,S) • Periodic review policy • Every Friday, we place an order to bring on-hand + on-order up to 25 cases—is an example of a (I,S) policy • I = 7 days = order interval - reflects a balance of scale economies with associated costs • Fundamental problem #1 • S = 25 cases = order-up-to quantity - raises the number guessing issue • Fundamental problem #2

  34. Cash management example When & How Much – (I,S) Transfer is automatically made every 6.25 working days • I = 6.25 days, D = $4,000/day, target FR = 98% • Average transfer amount = 6.25 days  $4000/day = $25,000 • FR = 98% means an average of (0.02)(4000) = $80 written out of negative balance per day • ID = 6.25(4000) = $25,000 = average demand between receipt of funds • For 98% fill rate target, this means*… • ID(1-FR) = 25,000(.02) = $500 = average negative balance when cash arrives

  35. Example continued When & How Much – (I,S) I = 6.25 days, L = leadtime 3 days, I + L = 9.25 days ILD = random demand during the order interval plus leadtime (9.25 days) Suppose ILD ~ N(ILD,ILD2), ILD= 49,000, ILD2 = 8,1002 Order-up-to quantity can be expressed as S = ILD + buffer stock1 = ILD + zILD What value of z is consistent with FR = 98%? 1buffer stock & safety stock mean the same thing

  36. Example continued When & How Much – (I,S) We can use the unit normal loss table (G(z) in Appendix 4) • From normal, S = ILD + zILD & ILD = 49000ILD = 8100 • Just need the value of z • Can use the approximation formula: (ID)(1-FR)/ILDG(z) = standardized average number of units short upon receipt of order • Know ID = 25000, FR = 0.98, & ILD = 8100 • SoID(1-FR)/ILD = $25000(1-0.98)/8100 = 500/8100 = 0.0617 = G(z) • From table, G(1.15) = 0.0621, G(1.16) = 0.06086, so z = 1.15 or 1.16 • Plugging it in: S = ILD + zILD = 49000 + (1.15)8100 = $58,315

  37. (Q, R) Q = 25,000, e.g., balances $25/transaction with 7% loss of interest in low yield account R = 15,120, e.g., to hit target of 98% fill rate Safety stock = R - LD = 15120 – 12000 = 3,120 (I, S) I = 6.25 days, e.g., balances $25/transaction with 7% loss of interest in low yield account S = 58,315, e.g., to hit target of 98% fill rate Safety stock = S - ILD = 58315 – 49000 = 9,315 Example continued When & How Much – (I,S) (Q, R) versus (I, S) • (I, S) higher safety stock (& more expensive) for same FR • Illustrates the cost of not continuously monitoring, so why use? • One reason - combine orders to gain delivery efficiencies, e.g., all products ordered every Friday & delivered together

  38. Road map • Fundamental Problem Type #2 • Single Period Model • Policies for When & How Much • Summary

  39. SL* = cs/(cs+ce) Fundamental E.g., shows up in setting order quantities setting base stock levels setting reorder points setting overbooking levels Number guessing – burned if guess too high or too low Reducing demand uncertainty leads to reduced inventory investment Buffer stock = zLD Each percentage increase in fill rate requires an increasing incremental investment in inventory Ouch!! Summary Managerial insights

  40. Back to key questions • What is the cost trade-off captured by the single period model (SPM)? • In what settings is SPM analysis appropriate, & how can an order quantity be determined? • What is the definition of base stock level, & how does a base stock policy answer the questions of when & how much to order? • In what settings may a base stock policy be reasonable, & how can base stock be determined? • How do (Q, R) & (I, S) policies answer the questions of when & how much to order, when is each policy appropriate, & how can the values of policy parameters be determined ? • What is the difference between fill rate & service level, and how do these performance measures depend policy parameters? • How can the return on investments to reduce uncertainty be estimated? • What are the managerial insights from the chapter?