130 likes | 140 Views
Renovation Post-industral Area – Nowe Gliwice 2003/004-379/05.33. Phare 2003 ESC. Formerly – Industry, Currently - Knowledge. Agenda. Objectives of the Project Location Financing of the project Scope of works Investment process parties Pre-investment phase Investment phase Problems
E N D
Renovation Post-industral Area – Nowe Gliwice2003/004-379/05.33 Phare 2003 ESC Formerly – Industry, Currently - Knowledge
Agenda • Objectives of the Project • Location • Financing of the project • Scope of works • Investment process parties • Pre-investment phase • Investment phase • Problems • Results
Objectives of the project • Trasformation of a former coal mine plant into a zone of education and entrepreneurship • Establishing of a business incubator and investment zone for creating favourable conditions for SME development • Creation of a higher education infrastructure (campus) – for the Gliwice High School of Entrepreneurship
South-eastern part of Gliwice (Trynek district) Bojkowska, Pszczynska and Kopaniana street. The land of total area of 25,2ha was donated to the Municipality of Gliwice by the Voivode of Silesia 15,86 ha – total investment area Location of the project
Project financing • European Union Pre-accession Programme Phare 2003 Economic and Social Cohesion: 9,51 mEUR • Municipal Budget of Gliwice: ca. 4,2 mEUR
Object no. 1 Transformation of a former villa into the Vice-Chancellor’s Office and guest rooms
Object no. 2Conversion of a former administration building to didactic purposes • Office space for professors • Tutorial rooms • Canteen for employees
Object no. 3Adaptation of a former briefing building for educational purposes • Lecture and tutorial rooms • Computer Labs • Library • Reading room • Bistro
Office space for rent (on commercial conditions and for start-ups) Laboratories and storage rooms Conference rooms Auditorium Exhibition hall Buffet Object no. 4Adaptation of a former machinery building to purposes of a business incubator
Brief history of the project • June 2003 – signing of the Financing Memorandum • 23.11.2004 – singing of an agreement with the Contract Engineer • 28.12.2004 – commencement of a public procurement procedure for selecting the Contractor • 19.05.2005 – signing of the contract with the Contractor • 31.05.2005 – transferring of the site to the Contractor • 01.06.2005 – commencement of works
J&P – AVAX S.A. Contractor Project management structure Municipality of Gliwice Contracting Authority Local Development Agency Ltd. Project Implementation Unit Representative of the Contracting Authority Consortium of SAFEGE Societe Anonyme And Inwest-Complex Ltd. Contract Engineer
Expected results of the project • 15,86 ha of reclaimed land: • 5,75 ha entreprenueurship and education zone • 10,11 ha inestment zone • 4 structures adapted to their new functions of net area totalling to 20 983m2 (business incubator: 9 164m2, university 11 819 m2) • 20 – 50 SMEs in the investment zone in 2 years after completion of the project • 1510 – 1750 new employment places • 2350 students using educational infrastructure in 2 years after completion of the project
Thank you for your attention Andrzej Szymborski CEO a.szymborski@arl.pl Local Development Agency, Ltd. PL 44-100 Gliwice, ul. W. Pola 16 www.arl.pl arlinfo@arl.pl