520 likes | 799 Views
North East Pacific Time-series Underwater Networked Experiment (NEPTUNE): Power System Design, Modeling and Analysis. Aditya Upadhye. Outline. NEPTUNE Power system requirements Two design alternatives Version 1 Version 2 Cable analysis Models Simulation results
E N D
North East Pacific Time-series Underwater Networked Experiment (NEPTUNE):Power System Design, Modeling and Analysis Aditya Upadhye
Outline • NEPTUNE • Power system requirements • Two design alternatives • Version 1 • Version 2 • Cable analysis • Models • Simulation results • Conclusions and future work
Science requirements • Communication bandwidth - Gb/s • Power – 200kW • Reliability • Robustness of design • Thirty year lifetime • Maintenance and support
Power System Design • Basic tradeoffs • Frequency: ac versus dc • Network: radial versus interconnected • Loads: series versus parallel • Shore station supply at 10kV, 200kW • Max. current-carrying capacity = 10A • User voltage = 400V / 48V • Max. power at each node = 10kW
Power System Design • Protection • Sectionalizing circuit breaker • Breaker control • Monitoring and control • Current – voltage measurements • State estimation • Shore station control hardware / software
DC Circuit Breaker Need • During initial energization • For fault isolation Required features • To force a current zero and minimize arcing • To prevent breaker restrikes
S2 S3 R1 R2 S4 S1 C DC Circuit Breaker Open Circuit
S2 S3 S4 R1 R2 S1 C DC Circuit Breaker Soft Closing
S2 S3 S1 S4 R1 R2 C DC Circuit Breaker Closed circuit
S3 S2 S4 R1 R2 S1 C DC Circuit Breaker Capacitor charging
S2 S3 S4 R1 R2 S1 C DC Circuit Breaker Capacitor discharging
DC Circuit Breaker Hardware prototype • 125V, 5A breaker circuit • Breaker control • MOSFETs drive the switch solenoids • Opto-isolator between logic circuit and driver circuit • Control logic has a counter, which continuously cycles through the breaker operations
DC Circuit Breaker Hardware prototype test results • Continuous Voltage: 125V • Continuous Current: 4.5A • Total Breaker Cycles: 125,000 • Normal cycle switching frequency: 20Hz • Maximum cycle switching frequency: 100Hz • Maximum tested voltage: 200V • Maximum tested current: 5A
Series Power Supply • Indigenous power supply for each BU • Less reliance on node converter • Use of zener diodes in reverse region • Back-to-back zener diodes
Modes of Operation • Normal • Fault • Fault-locating • Restoration Special case • System startup
Comparison of Version 1 and Version 2
Version 1 Version 2 Conventional approach to power system design Based on the philosophy that cable faults are rare but possible Response to a fault is at the system level by the shore station controls Response to a fault is at the local level by the nearest circuit breaker Circuit breaker is complicated with many components Complexity of circuit breaker is greatly reduced Fault current is interrupted; arcing and restrikes are possible Fault current is not interrupted; arcing and restrikes are not possible Single node failure can cause failure in a large section of the network Single node failure is not catastrophic for the system as that node only will be out of service Reliability is low Reliability is increased
ATP Theory • ATP is a universal program system for digital simulation of transient phenomena of electromagnetic as well as electromechanical nature • With this digital program, complex networks and control systems of arbitrary structure can be simulated • Trapezoidal rule of integration
Inductance Calculations • The generalized formulae were applied to the OALC4 cable • The core (steel) current caused flux linkages within a) the core b) the sheath c) the insulation • The sheath (copper) current caused magnetic flux linkages within: a) the sheath b) the insulation
Inductance Calculations Where T is the total flux linkage associated with the conductor, i is the flux linkage internal to the conductor, and e is the flux linkage external to the conductor Where icable is the total current in the cable
t = topen t = (topen-t) t =( topen +t) Switch closed Switch open: initial arcing Capacitor charging Version 1: Opening of Circuit Breaker
RESTRIKE!!! Vmax Initial Arcing Period topen Simulation of Restrikes
Capacitor Current Restrike No Restrike
Capacitor Voltage Restrike No Restrike
Current Limiting Operation • The shore station power supplies are rated at 200kW, 10kV • The steady-state system current = 10A • Under certain conditions, the system current may increase due to • Cable faults • Topology changes • Load fluctuations
Current Limiting Operation • The system current is limited to a value below 10A using the control circuitry in the shore station • This is done by dropping the shore voltage which in turn reduces the current • The control action is initiated only for steady-state overcurrents and not transient overcurrents.
Results of Current Limiting: Shore Output voltage and Current Voltage Current
Voltage and Current at Node 2: No Current Limiting Voltage Current
Version 2: Fault Studies • A pre-insertion resistance may be placed at the shore station to limit the fault current • This resistance will limit the fault current before the shore controls take the appropriate mode-dependant control action • Three controllable parameters in simulations: • Value of pre-insertion resistance • Response time of control circuitry • Distance of fault from the shore station
Simulation Circuit X=100km/1200km