An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Outline • Short overview of ToF-L/R HV system • Reason for upgrade of HV system • Possible solutions for upgrade • Description of chosen solution • Current status of HV upgrade

  2. HV System Components 1) Main control unit – CAEN SY527 (10 units – working well – some aging problems) 2) HV Generator modules – CAEN 753 (10 units – 90 channels - working well) 3) HV Distributors modules – CAEN 933 (80 units – 1920 channels - lot of problems due to aging) 4) PC for control and monitoring (working well)

  3. System topology

  4. HV System Status • Falling rate of HV distributors increase during last year • During the November Be run (one month) we lose 4 distributors! • 6 broken distributors sent to CAEN for reparation • When we get themback, we will have only 4 spares, which is not enough to be safe for this year run

  5. Plan for upgrade • Replace two crates in the pit (480 channels) with the new system (first phase - 2012) • Replace another two crates (480 channels) with the new system (second phase – 2013 or 2014) 3) Use replaced crates as source of spare parts for the remaining crates

  6. Plan for upgrade QUESTION buy a new system from manufacturer (CAEN,…) OR produce a custom made, based on resistor divider

  7. CAEN System 1) SY4527 - Universal Multichannel Power Supply System – BASIC 5680 EUR 2) A1932AP - SY1527 H.V. channels +3 KV/500 μA Distributor (48 ch) (Double width) 6,085 EUR 3) A2932AP - SY1527 H.V. channels +3 KV/250 μA Distributor (48 ch) (Single width) 6,085 EUR 4) SW4536 - SY4527 Control software 1,250 EUR

  8. CAEN System

  9. Price for CAEN system 1) 480 channels, phase 1 (two old crates) (5680+10*6085+1250+2*2000) ~72000EUR (150 EUR/ch) 2) 960 channels, phase 2 (four old crates) ~144000EUR (150 EUR/ch) FAR BEYOND OUR POSSIBILITIES! (and still have connectors problems!)

  10. Custom made system • Distributor made as a passive resistors divider • Setting of HV by hand (choosing R) • Basic idea originate from Dubna

  11. Custom made system • Distributor made as a passive resistors divider • Setting of HV by hand (choosing R) • Include monitoring of HV by implementing microcontroller inside every distributor! • Use the same connectors on the back as we already use • Made the standard housing (bin) compatible with standard rack

  12. Price for custom system • 480 channels, phase 1 (two old crates) 15000EUR (~31 EUR/ch) (two crates+20 distributors+4 spare) 2) 960 channels, phase 2 (four old crates) ~30000EUR (~31 EUR/ch) (four crates+40 distributors+8 spare)

  13. Advantage • Electronics is not complicate, expecting robust design, stable work and lower falling rate • Price is ~5 times less comparing to new CAEN system needed to replace the old one • High voltage level can be monitored by control logic in crate by using already existed cables and software in PC located in counting room • Without monitoring can be run in passive mode in old CAEN crate!

  14. Disadvantage • Complicate procedure of setting and calibration • Every distributor board will be unique (according to HV specification for their set of channels) • Control electronic will not be finished until start of the summer run! (But distributor boards can run without monitoring!)

  15. Crate - front

  16. Crate - top

  17. Front panel

  18. Communication

  19. Shematic

  20. Current status • Contract between NA61 and IPB (Institute for Physics, Belgrade) already signed • Mechanical parts ordered, expecting to be delivered till the end of the May • Amphenol connectors ordered from CAEN, will be delivered to the end of June (90 days!) • Electrical design finished • PCB design in progress, will be finish in next few days • PCBs expected at the beginning of June

  21. Conclusion • First working modules (without HV monitoring) expected for mid of July (needed in case of emergency) • Full functionality at the beginning of September • ToF-L/R readout upgrade have to be discuss!