1 / 14

Chapter 6 – Problem #20

Chapter 6 – Problem #20. Target duration is 14d. Critical path: A-C-D-E-G. Chapter 6 – Problem #20. Resource X is over utilized on 3 days shown. Resource W is over utilized on the one day shown. Chapter 6 – Problem #20.

jody
Download Presentation

Chapter 6 – Problem #20

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 6 – Problem #20 Target duration is 14d. Critical path: A-C-D-E-G.

  2. Chapter 6 – Problem #20 Resource X is over utilized on 3 days shown. Resource W is over utilized on the one day shown.

  3. Chapter 6 – Problem #20 After leveling the project duration is 17 days. Critical path is A-B-D-F-G. Skip part (e).

  4. Chapter 6 – Problem #21 Critical path is B-C-E-H. The project duration and cost for the all normal levels of project activity is 20 days and $400. 18-day delivery time, cost = $480. Crash H (-2). 16-day delivery time, cost = $630. Crash H (-3), B(-1), D(-1). 14-day delivery time, cost = $800. Crash H (-3), B(-1), D(-1), C(-1).

  5. Chapter 6 – Problem #21 4 d g 2 e a 6 1 c 5 h b 3 f

  6. Chapter 6 – Problem #21

  7. Chapter 6 – Problem #21, Excel Solver (grad students)

  8. Chapter 6 – Problem #21, Excel Solver (grad students)

  9. Chapter 6 – Problem #21, Excel Solver (grad students)

  10. Chapter 6 – Problem #21, Excel Solver (grad students)

  11. Chapter 6 – Problem #21, Excel Solver (grad students)

  12. Chapter 7 – Problem #25 ACWP=AC=$270,000 BCWP=EV=$272,000 BCWS=PV=$261,000 Cost/spending variance=EV-AC= + $2,000 Schedule variance=EV-PV= + $11,000 SPI=EV/PV=1.042 CPI=EV/AC=1.007 Less has been spent than the baseline plan, and given what has been spent, more progress has been made than was anticipated.

  13. Chapter 7 – Problem #26 ACWP=AC=$156,000 BCWP=EV=$162,000 BCWS=PV=$168,000 Cost/spending variance=EV-AC= + $6,000 Schedule variance=EV-PV= - $6,000 SPI=EV/PV=0.964 CPI=EV/AC=1.038 Less has been spent than the baseline plan, and given what has been spent, less progress has been made than should have been made.

  14. Chapter 7 – Problem #27 & 28 ACWP=AC=$1,480 BCWP=EV=$950 BCWS=PV=$1,430 Cost/spending variance=EV-AC= - $530 Schedule variance=EV-PV= - $480 SPI=EV/PV=0.664 CPI=EV/AC=0.642 BAC=$1,750 ETC=$1,246.11 EAC=$2,726.11

More Related