LCLS Construction/Installation Planning • Integration • Planning • Planning schedules • Typical Installation plan • Detailed schedules
LCLS Construction/Installation Planning • Integrate all aspects of the LCLS project • Use P3 Schedule tools • Multi-calendar/multi-shift capability • Effort loaded • Official schedule for dates/timelines • Use Planning Schedules • High level schedules to review LCLS systems with SLAC programs
LCLS Construction Planning • Integrated Schedule – P3 • Controlled by PMCS group • Input from System managers • Planning Schedule • Overview of LCLS systems • Conventional Facilities & Technical Systems • Integrate with SLAC programs • Downtimes, FFTB, SSRL, etc. • LCLS installations, “what-if” scenarios
Planning Schedule - 2 FFTB shutdown date is subject to review and may move earlier Research yard work is shifted left 1 month relative to P3 for ‘what-if’ planning purposes
LCLS Installation Planning • Typical Tech Component Installation • Conventional Construction Schedule – B.O. dates • Cable Plant & Utilties (LCW, I&C, Bus, etc) • Alignment/Survey • Supports & Stands Install • Technical Components Install • Utilities connections to components
LCLS Installation Planning • Typical Tech Component Installation (cont) • Alignment/Survey, final • Test & Checkout, MPS/I&C • PPS Checkout & Verification • Lockdown & Power-On Checks • Commission
LCLS Installation Planning • Subcontract Installation • Subcontracts work extremely well (for SPEAR3) • Prepare scope of work well in advance, be detailed in subcontract description, review with SLAC purchasing early • Prepare installation plan, make it easy for subcontractors to do their work.. Quickly and safely; minimize field change orders • Have system engineer/UTR on site during all subcontractor work; work out issues in a timely manner
Installation Schedules • SLAC October downtime schedule • Input from LCLS • Lists Area and Shop • Shop sort done for all tasks • Integrates all SLAC shop requests • Weekly meetings • Run by Tech Div
LCLS Installation Schedules • SPEAR3 schedule used P3 • 5 calendars • Units in hours • As much detail as needed
RF Gun Load Lock L0-1 & L0-2 3-m SLAC Sections Gun Diagnostics Laser Heater Transverse RF Cavity DL1 Bend Straight Ahead Spectrometer Injector Installation • Injector installation to follow Sector 20 Facility B.O. • October installation: pipe in shield wall • Injector installation starts early ‘06
LCLS Installation Planning • What’s next? • Start Planning process • Begin routine installation meetings • Review work scope & safety aspects • Develop plan & implement process • Daily meetings during installation times • Prepare for October installations • SLAC downtime schedule • Begin August ’06 installation plans • SLAC downtime/P3 detailed schedule • Continue to integrate CF & Technical component installation plans