Geo-spatial Electrification Planning for Myanmar

Geo-spatial Electrification Planning for Myanmar. Sustainable Engineering Lab Director: Vijay Modi Department of Mechanical Engineering (SEAS) and Earth Institute, Columbia University Nay Pyi Taw, Myanmar, November 22, 2013. Outline. Rationale

jon
Download Presentation

Geo-spatial Electrification Planning for Myanmar

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Geo-spatial Electrification Planning for Myanmar Sustainable Engineering Lab Director: Vijay Modi Department of Mechanical Engineering (SEAS) and Earth Institute, Columbia University Nay Pyi Taw, Myanmar, November 22, 2013

  2. Outline • Rationale • Our Approach: analysis platform for decision making: where what technology, prioritization, near-term decisions guided by long-term, least-cost • Not engineering designs, but rapid planning • Examples: village, region and national scales • Combine International Experience + Local Expertise • Our Project Plan and Starting Work in Myanmar

  3. Rationale • Organize information in a systematic digital form • Useful for • Quickly budgeting • Responding to internal and donor needs • Transmission upgrades/generation • Communication bet township/state/national • Co-ordination between grid and off-grid projects

  4. Benefits of National Geospatial Planning • Accelerate national access at scale: • access and service standards can be applied consistently • important for remote, under-served populations • Improve allocation of investments: • ensure on-grid generation benefits from economies of scale • efficient targeting of off-grid systems for smaller communities • enable rapid design and bulk procurement in roll-out • Provide a coordinated investment framework: • help donors & government prioritize according to local development goals • reduce risk for private sector investors and entrepreneurs • NOTE: The difference between design vs. planning

  5. Approach (1) • Acquire detailed geo-spatial, cost and technical information: • Demand points (settlements) • Electricity Infrastructure (MV distribution lines) • Demand level • Growth rates (population, economic) • Cost Factors (grid and off-grid, initial & recurring) (with off-grid)

  6. Approach (2) • Project demand and cost for a defined time-horizon: • Apply growth rates, wealth / income mapping • Algorithmic computation of least-cost electricity system: • Grid extension • Mini- or Micro-grids (renewable, hybrid) • Household Systems (solar) • Generate phased Roll-Out plan for grid and distributed systems (with off-grid)

  7. NetworkPlanner:An Algorithmic Planning System

  8. NetworkPlannerHow it Works • A free, web-based tool(no license fees) Designed by our lab at the Earth Institute • Accepts essential local inputs of geospatial demand points, costs for electricity technologies, growth rates and other key parameters. • Algorithmically plans least-cost electricity systems in these steps: • Computes the lifetime costs (initial and recurring) for meeting projected electricity demand at every point for all electricity options • Chooses the lowest-cost electricity technology for each point • Creates detailed map outputs for the least-cost grid and all standalone systems. • Creates detailed tabular outputs describing investment needs, recurring costs, additional generation required, and many other planning outputs.

  9. Kenya – The First Major Use of Geospatial Planning Kenya / EI Electricity Planning Project: • Results highlighted the need to electrify western, under-served areas • Region specific generation req. and transmission upgrades • Ultimately led to major loan 1.3B from World Bank

  10. Example: Electrification Planning at the Regional scale Flores, Indonesia: 6,300 settlements in Eastern Indonesia

  11. Inputs that went into access planning • Location of each settlements • Population of each settlement • Where is the existing medium-voltage network? • Unit costs of utility infrastructure, off-grid • New customer demand

  12. Essential Local Contribution: Technical and Cost Parameters

  13. Example of Grid-Rollout over 20 Years(Flores Island, Eastern Indonesia)

  14. A complete electricity plan specifies locations with grid access, mini-grids, and off-grid (solar home systems)

  15. Proposed Grid: 166,000 HHsVillage Solar Mini-Grid: 84,000 HHs Model results provide quantitative outputs for locations served by all system types, with capacities and costs.

  16. Investments (250,000 new HH with elec)

  17. Grid: Metrics

  18. Solar Mini-Grid: Metrics Solar Mini-Grid: Costs 10% of the kWh from diesel backup for solar mini-grids brings reliability from 80% to 90%

  19. Solar Home Systems: Metrics and Costs Solar Home Systems Solar: Costs

  20. Background Population Modeling GIS Platform Model Results Solar MicroGrids Talking Points Marginal costs of grid connections can increase with roll-out Mini-grid

  21. Mini-Grid Rollout: An example prioritizing higher demand villages

  22. Mini-grid Solar home System Grid? Planning at Township Level High Voltage

  23. Solar Mini Grid Algorithm Results Technology Options

  24. Grid Rollout: An example prioritizing most cost-effective branches Investment in MV line per connection (meters shown) Phase 1 < 20 Phase 2 20 – 25 Phase 3 > 25

  25. Incremental Infrastructure • one could start local and where/when demand grows and grid comes closer connect to the grid • Keeps initial investments small and modular • Does not strain utility immediately • Allows demand grows and entrepreneurship to emerge organically

  26. Our Project Plan • The Earth Institute’s approach to Electrification Planning in Myanmar will include three phases with an in-country workshop roughly marking each phase, as outlined below.

  27. Our Project Plan 1. Data Gathering • Milestone 1: Inception Workshop • Deliverable 1: Inception Report • Milestone 2: Formation of a GIS dataset with acceptable resolution of population and MV network representation • Deliverable 2: Interim Report

  28. Our Project Plan 2. Demand Analysis & Quantify Supply Needed • Milestone 3: Workshop on Initial Results • Deliverable 3: Draft Final Geospatial Rollout Plan 3. Final Scaled-Analysis and Knowledge Transfer • Milestone 4: Final Results Workshop • Milestone 5: GOM feedback on Draft Report • Deliverable 4: Final Geospatial Rollout Plan & accompanying datasets developed

  29. Starting Work For Myanmar: Data Sets Needed for Electricity Modeling • Settlement Data from Village or Village Tracts • Locations • Populations • Existing Grid Distribution Data • map or digital file for medium-voltage lines • Other drivers • Supply options, current/future • Demand/hh, population and demand growth, • unit costs of options

  30. Village locations within Village Tracts Electrification Planning benefits from village level data. Village Tract data may be supplemented in some cases

  31. Settlement Data • From MOLFRD, DRD • Village location and population, 2001 • In absence of more recent data, an excellent starting point • Project to future • Can we updated as new figures become available

  32. EXAMPLE: State: Magway Township: Pakoku

  33. Existing distribution grid • Transmission Lines • Available through MEPE, up to 66 kV • Medium Voltage lines, ESE, YESB • 33 kV and 11 kV lines • Currently not available in digital geo-spatial form • ESE is compiling paper/scan images from all states/regions, estimated avai: 1 month • Smaller off-grid systems • Expect to report later

  34. Other drivers • Large generation Sources • Hydropower, HGPE (generation), DHP (planning) • Cost of Grid Generation in the future • Some uncertainty due to variable international fuel supply, scale of demand growth • JICA study • Hydro potentials, thru MOPE • Hydro <5MW, from ESE • Unit costs, demand

  35. Original:jpeg with hand-drawn MV lines (red) GIS product:shapefile with digitized MV lines (blue)

  36. Training and Capacity Building : Example: Data collection with smartphones Training and detailed work with local electricity technicians and managers resulted in completion of a detailed local medium-voltage distribution grid map for a region in Eastern Indonesia Training & mapping of MV grid lines (IDN) Training & mapping of MV grid lines (IDN) West Timor (IDN) MV grid initial estimate West Timor (IDN), MV grid lines following EI training & mapping

  37. Approach to data • Settlement Data valuable for electricity, gas, roads, water, and other services • Tools to gather and “maintain” data. • How to rapidly capture planning grade data for existing lines • Work closely with Government/Utility to embed tools/processes in their systems

  38. Working with Ministries, Utilities, Enterprises • We would like to begin here in Nay Pyi Taw, possibly following up in other regions or offices. We ask your permission and support • Our plan and approach is to work side-by-side with local experts and practitioners to ensure the relevance, completeness and accuracy of all data and outputs. • Workshop tomorrow