An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UET MultiprocessorScheduling Problems Nan Zang nzang@cs.ucsd.edu

  2. Overview of the paper • Introduction • Classification • Complexity results for Pm | prec, pj = 1 | Cmax • Algorithms for Pk | prec, pj = 1 | Cmax • Future research directions and conclusions Nan Zang

  3. Scheduling • Scheduling concerns optimal allocation of scarce resources to activities. • For example Class scheduling problems • Courses • Classrooms • Teachers Nan Zang

  4. Problem notation (1) • A set of n jobs J = { J1, J2, ……, Jn} The execution time of the job Jj is p(Jj). • A set of processors P = {P1 , P2, ……} • Schedule Specify which job should be executed by which processor at what time. • Objective Optimize one or more performance criteria Nan Zang

  5. Problem Notation (2) • αdescribes the processor environment Number of processors, speed, … • β provides the job characteristics release time, precedence constraints, preemption,… • γ represents the objective function to be optimized The finishing time of the last job (makespan) The total waiting time of the jobs 3-field notation α|β|γ (Graham et al.) Nan Zang

  6. Job Characteristics • Release time (rj) - earliest time at which job Jj can start processing. - available job • Preemption (prmp) - jobs can be interrupted during processing. • Precedence constraints (prec) - before certain jobs are allowed to start processing, one or more jobs first have to be completed. - a ready job Nan Zang

  7. Precedence constraints (prec) Definition • Successor • Predecessor • Immediate successor • Immediate predecessor • Transitive Reduction Before certain jobs are allowed to start processing, one or more jobs first have to be completed. Nan Zang

  8. Precedence constraints (prec) Definition • Successor • Predecessor • Immediate successor • Immediate predecessor • Transitive Reduction One or more job have to be completed before another job is allowed to start processing. Nan Zang

  9. Precedence constraints (prec) Definition • Successor • Predecessor • Immediate successor • Immediate predecessor • Transitive Reduction One or more job have to be completed before another job is allowed to start processing. Nan Zang

  10. Special precedence constraints (1) • In-tree (Out-tree) • In-forest (Out-forest) • Opposing forest • Interval orders • Quasi-interval orders • Over-interval orders • Series-parallel orders • Level orders Nan Zang

  11. In-tree Out-tree Opposing forest In-forest Special precedence constraints (2) Out-forest Nan Zang

  12. UET scheduling problem formal definition Pm| prec, pj = 1 | Cmax (m≥1) • Processor Environment • m identical processors are in the system. • Job characteristics • Precedence constraints are given by a precedence graph; • Preemption is not allowed; • The release time of all the jobs is 0. • Objective function • Cmax : the time the last job finishes execution. ( If cj denotes the finishing time of Jj in a schedule S, ) Nan Zang

  13. Slot 1 Slot 2 P1 P2 P3 Time axis Gantt Chart A Gantt chart indicates the time each job spends in execution, as well as the processor on which it executes Nan Zang

  14. Overview of the paper • Introduction • Classification • Complexity results for Pm | prec, pj = 1 | Cmax • Algorithms for Pk | prec, pj = 1 | Cmax • Future research directions and conclusions Nan Zang

  15. Classification Due to the number of processors • Number of processors is a variable (m) Pm | prec, pj = 1 | Cmax • Number of processors is a constant (k) Pk | prec, pj = 1 | Cmax Nan Zang

  16. Classification Due to the number of processors • Number of processors is a variable (m) Pm| prec, pj = 1 | Cmax • Number of processors is a constant (k) Pk| prec, pj = 1 | Cmax Nan Zang

  17. Pm| prec, pj = 1 | Cmax (1) Theorem 1 Pm| prec, pj = 1 | Cmax is NP-complete. • Ullman (1976) 3SAT ≤ Pm | prec, pj = 1 | Cmax 2. Lenstra and Rinooy Kan (1978) k-clique ≤ Pm| prec, pj = 1 | Cmax • Corollary 1.1 • The problem of determining the existence of a schedule with Cmax ≤3 for the problem • Pm| prec, pj = 1 | Cmax is NP-complete. Nan Zang

  18. Pm| prec, pj = 1 | Cmax (2) Mayr (1985) • Theorem 2 Pm | pj =1, SP | Cmax is NP-complete. SP: Series - parallel • Theorem 3 Pm | pj =1, OF | Cmax is NP-complete. OF: Opposing - forest Nan Zang

  19. a b c d SP and OF • Series-parallel orders Does NOT have a substructure isomorphic to Fig 1. • Opposing-forest orders Is a disjoint union of in-tree orders and out-tree orders. Fig 1 Fig 2: Opposing forest Nan Zang

  20. Conclusion on Pm| prec, pj = 1 | Cmax • 3SAT is reducible to the corresponding scheduling problem. • m is a function of the number of clauses in the 3SAT problem. • Results and techniques do not hold for the case Pk | prec, pj = 1 | Cmax Nan Zang

  21. Classification • Number of processors is a variable (m) Pm | prec, pj = 1 | Cmax • Number of processors is a constant (k) Pk | prec, pj = 1 | Cmax Nan Zang

  22. Optimal Schedule for Pk | prec, pj = 1 | Cmax • The complexity of Pk | prec, pj = 1 | Cmax is open. • 8th problem in Garey and Johnson’s open problems list.(1979) • One of the three problems remaining unsolved in that list • If k = 2, P2 | prec, pj = 1 | Cmax is solvable in polynomial time. • Fujii, Kasami and Ninomiya (1969) • Coffman and Graham (1972) • For any fixed k, when the precedence graph is restricted to certain special forms, Pk | prec, pj = 1 | Cmax turns out to be solvable in polynomial time. • In-tree, Out-tree, Opposing-forest, Interval orders… Nan Zang

  23. Special precedence constraints • In-tree (Out-tree) • In-forest (Out-forest) • Opposing forest • Interval orders • Quasi-interval orders • Over-interval orders • Level orders Nan Zang

  24. Algorithms for Pk | prec, pj = 1 | Cmax • List scheduling policies • Graham’s list algorithm • HLF algorithm • MSF algorithm • CG algorithm • FKN algorithm (Matching algorithm) • Merge algorithm Nan Zang

  25. Algorithms for Pk | prec, pj = 1 | Cmax • List scheduling policies • Graham’s list algorithm • HLF algorithm • MSF algorithm • CG algorithm • FKN algorithm (Matching algorithm) • Merge algorithm Nan Zang

  26. List scheduling policies (1) • Set up a priority list L of jobs. • When a processor is idle, assign the first ready job to the processor and remove it from the list L. Nan Zang

  27. Algorithms for Pk | prec, pj = 1 | Cmax • List scheduling policies • Graham’s list algorithm • HLF algorithm • MSF algorithm • CG algorithm • FKN algorithm (Matching algorithm) • Merge algorithm Nan Zang

  28. Graham’s list algorithm • Graham first analyzed the performance of the simplest list scheduling algorithm. • List scheduling algorithm with an arbitrary job list is called Graham’s list algorithm. • Approximation ratio for Pk | prec, pj = 1 | Cmax δ = 2-1/k. (Tight!) • Approximation ratio is δ if for each input instance, the makespan produced by the algorithm is at most δ times of the optimal makespan. Nan Zang

  29. Algorithms for Pk| prec, pj = 1 | Cmax • List scheduling policies • Graham’s list algorithm • HLF algorithm • MSF algorithm • CG algorithm • FKN algorithm (Matching algorithm) • Merge algorithm Nan Zang

  30. HLF algorithm (1) • T. C. Hu (1961) • Critical Path algorithm or Hu’s algorithm • Algorithm • Assign a level h to each job. • If job has no successors, h(j) equals 1. • Otherwise, h(j) equals one plus the maximum level of its immediate successors. • Set up a priority list L by nonincreasing order of the jobs’ levels. • Execute the list scheduling policy on this level based priority list L. Nan Zang

  31. Level 3 Level 2 Level 1 HLF algorithm (2) 3 3 3 3 2 2 1 1 1 1 1 1 1 Nan Zang

  32. HLF algorithm (3) • Time complexity O(|V|+|E|) (|V| is the number of jobs and |E| is the number of edges in the precedence graph) • Theorem 4 (Hu, 1961) The HLF algorithm is optimal for Pk | pj = 1 , in-tree (out-tree) | Cmax. • Corollary 4.1 The HLF algorithm is optimal for Pk | pj = 1 , in-forest (out-forest) | Cmax. Nan Zang

  33. HLF algorithm (4) • N.F. Chen & C.L. Liu (1975) The approximation ratio of HLF algorithm for the problem with general precedence constraints: If k = 2, δHLF ≤ 4/3. If k ≥ 3, δHLF ≤ 2 – 1/(k-1). Tight! Nan Zang

  34. Algorithms for Pk | prec, pj = 1 | Cmax • List scheduling policies • Graham’s list algorithm • HLF algorithm • MSF algorithm • CG algorithm • FKN algorithm (Matching algorithm) • Merge algorithm Nan Zang

  35. MSF algorithm (1) • Algorithm: • Set up a priority list L by nonincreasing order of the jobs’ successors numbers. (i.e. the job having more successors should have a higher priority in L than the job having fewer successors) • Execute the list scheduling policy based on this priority list L. Nan Zang

  36. MSF algorithm (2) 2 2 2 7 1 6 0 0 0 0 0 0 0 7 6 2 2 2 1 0 0 0 0 0 0 0 Nan Zang

  37. MSF algorithm (3) • Time complexity O(|V|+|E|) • Theorem 5(Papadimitriou and Yannakakis, 1979) The MSF algorithm is optimal for Pk | pj = 1, interval | Cmax. • Theorem 6 (Moukrim, 1999) The MSF algorithm is optimal for Pk | pj = 1, quasi-interval | Cmax. Nan Zang

  38. a b a b c b c d a b a c e d d e e d c Special precedence constraints • Interval orders Does NOT have a substructure isomorphic to Fig 1. • Quasi – interval orders Does NOT have a substructure isomorphic to TYPE I, II or III. Type II Fig 1 Type III Type I Nan Zang

  39. Algorithms for Pk | prec, pj = 1 | Cmax • List scheduling policies • Graham’s list algorithm • HLF algorithm • MSF algorithm • CG algorithm • FKN algorithm (Matching algorithm) • Merge algorithm Nan Zang

  40. CG algorithm (1) • Coffman and Graham (1972) • An optimal algorithm for P2 | prec, pj = 1 | Cmax. • Best approximation algorithm known for Pk | prec, pj = 1 | Cmax, where k ≥ 3. Nan Zang

  41. CG algorithm (2) • Definitions • Let IS(Jj) denote the immediate successors set of Jj. • A job is ready to label, if all its immediate successors are labeled and it has not been labeled yet. • N(Jj) denotes the decreasing sequence of integers formed by ordering of the set { label (Ji) | Ji IS(Jj) }. • Let label(Jj) be an integer label assigned to Jj. Nan Zang

  42. CG algorithm (3) • Assign a label to each job: • Choose an arbitrary task Jk such that IS(Jk) = 0, and define label(Jk) to be 1 • for i  2 to n do • R be the set of jobs that are ready to label. • Let J* be the task in R such that N(J*) is lexicographically smaller than N(J) for all J in R • Let label(J*)  i end for 2. Construct a list of jobs L = {Jn, Jn-1,…, J2, J1} according to the decreasing order of the labels of the jobs. 3. Execute the list scheduling policy on this priority list L. Nan Zang

  43. 13 12 11 10 9 8 7 6 5 4 3 2 1 CG algorithm (4) N(J10)= N(J11)=N(J12)=(8) 10 11 12 13 N(J8)=(7,6,5,4,3,2) 8 9 N(J9)=(1) 1 2 3 4 5 6 7 Nan Zang

  44. CG algorithm (4) 10 11 12 13 8 9 1 2 3 4 5 6 7 13 12 11 10 9 8 7 6 5 4 3 2 1 Nan Zang

  45. CG algorithm (5) • Time complexity O(|V|+|E|) • Theorem 5(Coffman and Graham, 1972) The CG algorithm is optimal for P2 | prec, pj = 1| Cmax. • Theorem 6 (Moukrim, 2005) The CG algorithm is optimal for Pk | pj = 1, over-interval | Cmax. Nan Zang

  46. a b c b a b a c d e d e e d c Special precedence constraints • Quasi – interval orders Does NOT have a substructure isomorphic to TYPE I, II or III. • Over – interval orders Does NOT have a substructure isomorphic to TYPE I or II. Type II Type I Type III Nan Zang

  47. CG algorithm (6) The performance of CG algorithm when k≥3 • Lam and Sethi (1978) δCG ≤ 2 – 2/k • Braschi and Trystram (1994) Cmax(S) ≤ (2 – 2/k) Cmax(S*) – (k – 2 – odd(k))/k (tight!) Note: S is a CG schedule. S* is an optimal schedule. If k is an odd, odd(k):=1; otherwise, odd(k):=0. Nan Zang

  48. List Scheduling Policy Conclusions • List scheduling policies • Graham’s list algorithm • HLF algorithm • MSF algorithm • CG algorithm • Property • easy to implement • extended to the problem Pm | prec, pj = 1| Cmax • Research directions: • Allow priority lists to depend on the number k of processors. Nan Zang

  49. Algorithms for Pk | prec, pj = 1 | Cmax • List scheduling policy algorithm • Graham’s list algorithm • HLF algorithm • MSF algorithm • CG algorithm • FKN algorithm (Matching algorithm) • Merge algorithm Nan Zang

  50. FKN algorithm (1) • Fujii, Kasami and Ninomiya (1969) • First optimal algorithm for P2 | prec, pj = 1 | Cmax. • Basic Idea • Find a minimum partition of the jobs • There are at most two jobs in each set. • The pair of jobs in the same set can be executed together. • Make a valid schedule according to a particular order of the partition. (Some clever swap work needed!) • The length of the result schedule = value of the min partition • Can be solved by some maximum matching algorithm. Nan Zang