LHC-YETS 2017/18 Coordination meeting #17 9th January, 2018 AGENDA YETS planning follow-up Marta Alcaide Leon, Maria Barberan, Marzia Bernardini, Sebastien Bustamante LHC coordination meeting 9th January 2018
YETS 2017-2018: general informations • LHC-YETS main datesFromMonday 4thDecember @ 6am, to Friday 9th March (activitiescompleted)Poweringtests ph.1 from Saturday 3rd March (outside normal workinghours)From 4th March: machine patrolled and in restricted modeUnlock out W10 (5th March – 9th March)LHC back to BE-OP on Friday 9th March • IMPACT: intervention period YETS-LHC-2017-18 • Contacts:Phone ‘piquet’: 161669Outsideworkinghours: BE-OP-TI - 72201 • OSS website (planning, constraints, …):https://espace.cern.ch/en-dep-mef-lpc/YETS2017-18/SitePages/Home.aspx • INDICO:https://indico.cern.ch/category/9286/ • Access during AUG test isaccording to a list to access IN SURFACE need to bedeclared, NO access underground except EN-EL and EN-CV Dead line for AUG P18 on TUESDAY 9th January (today) LHC coordination meeting 9th January 2018
AUG tests at Point 18 on 11th January • Note de coupure AUG tests P18 LHC coordination meeting 9th January 2018
LHC-YETS 2017-2018 - Version 4 To beconfirmed LHC coordination meeting 9th January 2018
LHC-YETS 2017-2018 main activities LHC coordination meeting 9th January 2018
YETS 2017-2018: Baseline V3 OBSOLETE LHC coordination meeting 9th January 2018
YETS 2017-2018: new baseline V4 IF NEEDED LHC coordination meeting 9th January 2018
LHC-YETS: constraints (s.1-2 and s.2-3) LHC coordination meeting 9th January 2018
LHC-YETS: constraints (s.3-4 and s.4-5) LHC coordination meeting 9th January 2018
LHC-YETS: constraints (s.5-6 and s.6-7) LHC coordination meeting 9th January 2018
LHC-YETS: constraints (s.7-8 and s.8-1) LHC coordination meeting 9th January 2018
Reminder Point 8 - PM85 lift replacement: • From 16thDecembre to 23rdFebruary • Access of people (only ) through PZ85 – LHCb • Material transport withdedicated containers • Urgent issues contact S. Pelletier (163380) LHC coordination meeting 9th January 2018
Major changes during YETS 2017-18 status @ 20th Dec. 2017 *HL-LHC LHC coordination meeting 9th January 2018
YETS 2017-2018: open points & updates • Cryogenics calibration tests in sector 1-2 under discussion • Flushing of beam screen under discussion VSC & CRG • Cryogenics thermal load test in sectors 8-1 and 1-2 under discussion3 days per sector, suitable during the powering tests • PT 100 sensors & cables replacement on DFBX in sectors 1-2 and 8-1 under discussion with ELQA team and CRG • LHC 6 • UD62 dump activities: detailed planning to be validated and optimized after dump leak tests planned in W3 • N2 lines: detailed planning to be validated after X-rays (material delivery ok !) • Optimization of the planning of sector 1-2 in progress(cabling campaign, cabling rerouting, collimators activities, AFP, GGPSO, ….) • UL24 & 26 closed next week for crane tests (1/2 day) TBD • PR 711 in UX45 refurbishment so far so good but…PR714 in SX-4 is now out of order due to the breakage of one of the bearings might delay the PR711 refurbishment works if PR714 not operational by Thursday morning (!) • UL55 civil engineering works for lifting platform: under study LHC coordination meeting 9th January 2018
YETS 2017-2018: updates Requestfrom TE-EPC: upgrade of the SVC Control System in LHC PA6 Project background: • Installation and commissioning of a new control crate for the Static Var Compensator in LHC PA6. • The existing control system is from 1988, and has become obsolete. • LHC PA6 is the prototype installation. Once the new control crate is validated there, we will apply it for all our SVCs. Description of the request: • EN-EL to switch off the main 66 kV transformer in LHC PA6 for 1 or 2 days • This requires the transfer of the load in PA6 to the LHC 18 kV General Services Loop (switch-over and switch-back of the load)Transient disturbances possible during these two periods. Main impact on the following groups: EN-EL, EN-CV, TE-CRG, Others Planning: • Possible dates for the switch-over on PA6 for TE-EPC: • January from 9th Jan. @12h00 to 10th Jan. 15h00 (during test de secours) • Pre-commissioning in Week 4/2018 • Powering tests W6 between 6th and 9th FebruaryDuring the powering tests, some smaller disturbances are possible in the 18 kV network in PA6 Coordination with the users in PA6 are also required to find the best slot for the powering tests LHC coordination meeting 9th January 2018
Safety aspects for activities LHC coordination meeting 9th January 2018
All points & Point 1 9/01/2018 LHC coordination meeting 9th January 2018
LSS1R 9/01/2018 LHC coordination meeting 9th January 2018
Point 18 & Arc 1-2 9/01/2018 LHC coordination meeting 9th January 2018
LSS2L , Point 2 , LSS2R & Arc 2-3 9/01/2018 LHC coordination meeting 9th January 2018
LSS3 & Point 3 9/01/2018 LHC coordination meeting 9th January 2018
Arc 3-4 & LSS4L 9/01/2018 LHC coordination meeting 9th January 2018
Point 4 9/01/2018 LHC coordination meeting 9th January 2018
LSS4R & Arc4-5 9/01/2018 LHC coordination meeting 9th January 2018
LSS5L LHC coordination meeting 9th January 2018
Point 5 9/01/2018 LHC coordination meeting 9th January 2018
Arc 5-6 , LSS6L & Point 6 9/01/2018 LHC coordination meeting 9th January 2018
LSS6R & Arc 6-7 9/01/2018 LHC coordination meeting 9th January 2018
LSS7 & Point 7 9/01/2018 LHC coordination meeting 9th January 2018
LSS8, Point 8, & Ti8 9/01/2018 X Ray before and after RF fingers VMSIN ? LHC coordination meeting 9th January 2018
LSS1L 9/01/2018 LHC coordination meeting 9th January 2018
Agenda next meetings Week 3– 16th January YETS planning & accessconstraints – OSS team Week 4 – 23rdJanuary YETS planning & accessconstraints – OSS team Week 6 – 6th February YETS planning & accessconstraints – OSS team … LHC coordination meeting 9th January 2018
Spare slides LHC coordination meeting 9th January 2018
YETS 2017-2018: Broken line(8th January @4pm) LHC coordination meeting 9th January 2018
Reminder Activities in Point 4 • PR 711 in UX45 refurbishment from 4th Dec to 31st January (Including during Xmas closure) • So far so good but…PR714 in SX-4 out of order due to the breakage of one of the bearings that might delay the PR711 refurbishment works • UX 45 RF Powering Tests from 5th to 16th February • RF Cryo filling from 17th to 19th February NO ACCESS in LSS4 • RF DSO Test on 20th February NO ACCESS P4 • RF Reconditioning from 21st FebruaryNO ACCESS in LSS4 Courtesy of Helder Miguel Velez Lourenco LHC coordination meeting 9th January 2018
Major changes during YETS 2017-18 ECRs – status on 27th Nov.2017 Received from Anne Laure: “RF bridge in 6R8”, from VSC *HL-LHC LHC coordination meeting 9th January 2018
Lockout requests – Waiting for approval updated on Monday 18th December @15h00 Lockout requests – Waiting Unlock approval updated on Monday 18th December @15h00 LHC coordination meeting 9th January 2018
Lockout requests – Approved updated on Monday 18thDecember @15h00 LHC coordination meeting 9th January 2018
Work Frame Authorisation updated on Monday 18th December @15h00 LHC coordination meeting 9th January 2018
Exceptional : Work Frame Authorisation updated on Monday 18thDecember @15h00 LHC coordination meeting 9th January 2018