50 likes | 271 Views
DOTS+ Online. Status Update. CPWG. Tim McHale, ATCSCC. June 1, 2009. Current Status. DPO Build has been installed in all oceanic centers DPO User Manual has been updated and is available on-line DPO Training Server is still available for airline use. Stakeholder Participation.
E N D
DOTS+ Online Status Update CPWG Tim McHale, ATCSCC June 1, 2009
Current Status DPO Build has been installed in all oceanic centers DPO User Manual has been updated and is available on-line DPO Training Server is still available for airline use
Stakeholder Participation • UPS began FTI testing in mid-April 2009 • Testing required due to unique configuration for UPS • UAL connection information has been forwarded to the FTI Program Office • UAL is coordinating directly with FTI/Harris to begin use • Delta is working with CSSI to begin coordination process with FTI • Continental has been in contact with CSSI and is working internal issues to use the VPN connection
What Next • An operational demonstration for Anchorage ARTCC operations was targeted for the fourth quarter 2009. United Parcel Service (UPS) was expected to participate as the lead airline for the demonstration. • The on-line capability of DOTS Plus is available to all airlines immediately upon successful establishment of VPN connections to FTI
Summary Stakeholders may begin operational use as soon as they can complete connection process with FTI UPS, UAL and DAL have initiated the DPO/FTI connection process and COA is currently working on starting this process Airlines can immediately start this process by contacting CSSI, Inc. POC is Eric Schoell at eschoell@cssiinc.com