An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mission Support Construction Update Mr. Jim Schaefer HQ PACAF/CEC

  2. Major Construction Funding $1.26 Billion Total Construction In Progress Mission Support Portion That Affects Airfield Ops

  3. Mission Support Construction Repair Runway, $14M Repair Parking Ramp, $4M Hydrant Fueling Sys, DLA $26M Bulk Fuel Storage, DLA $21.7M Hydrt Fuel Sys-Ph1, DLA $19.5M Hydrt Fuel Sys-Ph2, DLA $23.5M C-130 Parking Ramp, $17M MISAWA AB EIELSON AFB Widen Taxiway Alpha, JFIP OSAN AB KUNSAN AB Contingcy Pamnt, CDIP, $4.5M ELMENDORF AFB Access Taxiway, CDIP, $3.9M YOKOTA AB Repair Runway, JFIP $36.6M KADENA AB ANDERSEN AFB HICKAM AFB Hydrt Fuel Sys-Ph1, DLA $24.3M Repair Airfield Pvmnt, $5.9M DIEGO GARCIA

  4. Eielson Repair Runway • FY00 MILCON, $14M Replace old asphalt runway with 75’ concrete keel • Planned construction: 1 May - 13 Sep 00 • Mission Implications: Runway shutdown for 135 days

  5. Eielson Repair Parking Ramp • FY00 MILCON, $4M Replace old asphalt ramp (concurrent w/ $26M DLA FY00 Refuel Hydrant project) • Planned construction 1 May - 13 Sep 00 • Mission Implications: Ramp down 135 days

  6. Eielson Hydrant Fueling Sys • FY00 DLA MCP,$26M Install 20 fueling hydrants on main ramp (concurrent w/ repair KC-135 ramp) • Planned construction 1 May - 13 Sep 00 • Mission Implications: 5-month ramp disruption

  7. Elmendorf Bulk Fuel Storage • FY98 DLA MCP,$21.7M Adds 3 new 83,000 BL JP-8 bulk fuel storage tanks on-base • Status: 96% Cns/ECD Dec 99 • Mission Implications: Doubles on-base fuel storage for air bridge

  8. Elmendorf Hydrt Fuel Sys, Ph 1 • FY99 DLA MCP,$19.5M Remove 14/Install 15 fueling hydrants on North ramp (airbridge) • Status: 38% Cns/ECD Feb 00 • Mission Implications: Reduced parking during construction N

  9. Elmendorf Hydrt Fuel Sys, Ph 2 • FY00 DLA MCP,$23.5M Replace 15 fueling hydrants on North ramp (airbridge) • Planned construction Dec 99 - Dec 01 • Mission Implications: Reduced parking during construction

  10. Elmendorf C-130 Parking Ramp • FY00 MILCON, $17M Constructs new C-130 parking ramp w/11 fuel hydrants • Planned construction Dec 99 - Dec 01 • Mission Implications: Minimal impact during construction; will enhance capability

  11. Hickam Repair Airfield Pvmnt • FY99 MILCON, $5.9M Parking ramp repair to preclude major FOD problems • Status: 80% Cns/ECD Dec 99 • Mission Implications: 15% reduced parking during construction

  12. Yokota Replace Runway • JFIP HNFC, $36.6M Overlay runway with 13.5” thick concrete • Planned construction Oct 00 - Apr 01 (2 Phases) • Mission Implications: Only partial runway accessible to C-17, C-21, C-130

  13. Andersen Hydrt Fuel Sys, Ph 1 • FY00 DLA MCP,$24.3M Replace 20 fueling hydrants, Southwest ramp • Planned construction Dec 99 - Dec 01 • Mission Implications: Limited hydrants for surge capability

  14. Kunsan Contingency Pavement • CY96 CDIP $4.5M New fighter parking ramp at Taxiway “6” • Status: 22% Cns/ECD Apr 00 • Mission Implications: New contingency parking for 16 fighter aircraft (in revetments) N

  15. Kunsan Access Taxiway • CY97 CDIP $3.9M New taxiway to connect Contingency Runway and north loop aircraft parking area • Planned construction Dec 99 - Apr 00 • Mission Implications: Improved use of alternate runway and aircraft movement

  16. Misawa Widen Taxiway Alpha • JFY00 Japanese Facilities Improvement Program • HQ AFCEE Site Study in Dec 99 to determine if parallel runway feasible • Cost/Scope: TBD • Criteria Package to be completed by Jun 00 • Construction Period: TBD • Mission Implications: TBD