XTRP Hardware. Mike Kasten University of Illinois 2/24/00. 2 XFT linkers. CDF clock. L1 calorimetry. L1 muon. L2 trigger. SVT. Data board transition module (x12). Clock/control transition module. Level1 Request. Clock/control board. Track Data. Data board (x12). 30 ° (2 wedges).
E N D
XTRP Hardware Mike Kasten University of Illinois 2/24/00
2 XFT linkers CDF clock L1 calorimetry L1 muon L2 trigger SVT Data board transition module (x12) Clock/control transition module Level1 Request Clock/control board Track Data Data board (x12) 30° (2 wedges) Data boards (duplicates) 132 ns + 33ns clocks 12 data boards XTRP I/O The core XTRP System Internal communication
XTRP Teststand #1: Pre-crate • Custom Backplane • Initial power-up • Boot PROM • VME emulation • Signals via Unidig Module • C code • Power measurement U of Illinois
XTRP Teststand #1: VME crate • Successfully completed VME transactions • Write/Read registers • Load extrapolation RAMs • Benchtop accessibility & VME emulation were extremely helpful for initial debugging • This teststand will provide initial testing infrastructure for new VME boards
XTRP Teststand #2: VME crate • VIPA-style Test Crate at U of Illinois • VME access • Write/Read registers • Load extrapolation RAMs • Multi-board system • Controller / TestClock / Clock Control / Data • Send clock signals from Clock Board to Data Board • Step data through Data Board (slow clock) • Software Development • DataBSim.java (Data Board simulator) • XtrpExpertPanel.java (Test engine)
XTRP Functional Clock Test TestClock CLOCK TEST 132ns, 33ns, Sync Signals 132ns Clock Data Board Clock Board VME write (+Test Clock) 132ns, 33ns, Sync Signals
Functional DataTestProcedure • Set up Data Board & Clock Board • Repeat N times: • Load XFT Simulation data into Data Board • Increment Data Board clock via Clock Board • Increment Simulator • Compare Data Board versus Simulator • Debug
XTRP Functional Data Test VME write XFT Simulation Data VME write Test Clock Data Board Clock Board STEPPED 132ns, 33ns, Sync Signals VME read & compare to Simulation
XTRP Teststand #2: VME crate • Data Board II is necessary • simple reroutes: ~100 • power supply pins (64 identical ICs ) • various • Mechanical compliance • Improvements (JTAG & buffering) • Data Board I lives on… • Completely Functional • Acceptable to use for B0 integration tests • Clock Control Board is OK (so far) • Corrections do exist: ~25 total wires • Relayout not planned
XTRP Teststand #3: Wilson Hall • Multi-crate system • XFT CDF-style Crate • Test Clock / Clock Splitter / Controller / TRACER • LinkerTester • Linker / Output Modules • XTRP VIPA-style Crate • Controller / TRACER • Data Board • Clock Control Board • Much much more Software Development
XTRP Tests DATA TEST >1,000,000 clocks error free Linker(2) Output Formatters VME write VME read & compare to Simulation Data transferred at full speed for 250 clocks VME read from Pipe FPGAs Linkertester Input Fifos Data Board CAL/MUON Data INPUT TEST >100,000,000 clocks errors: x000000 to xFFFFFF
XTRP Tests VME write Output Fifos Linkers (2) Linkertesters (2) Data transferred at full speed for 10k clocks VME read & compare to Simulation Data Board Input Fifos >10,000,000 clocks error free
XTRP Tests VME write Output Fifos Linkertester Data Board Data transferred at full speed for 10k clocks VME read & compare to Simulation Input Fifos Software under development
XTRP Teststand #3: Wilson Hall • Data Board I • No more layout errors found • Data Board Transition Module - new board necessary • wiring corrections: ~5 • PCB footprint for Muon connector is wrong • Clock Board • No more layout errors found • Clock Board Transition Module - new board necessary • Errors found independent of testing
Plan for New Hardware • Data Board II • Quotes requested, waiting for responses • Contract Assembler reviewing BOM • Target date for 1st DBII: April 1, 2000 • Data Board Transition Module • Want to connect to Muon & Calorimetry systems first • Target date for new TM: April 15, 2000 • Clock Board Transition Module • Need a new board for SVT & L2P integration • Target date for new TM: May 1, 2000
Input Test Error x000000 to xFFFFFF Linker(2) Output Formatters Backplane Data Board Transition Module Data Board 3.3V LVDS Receiver 3.3V LVTH Latch xFFFFEF Error seen on only 1 out of 96 bits xFFFFFF