An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BE/BI Consolidation Plans 2014-2019 Rhodri Jones Consolidation Day – 12th September 2013

  2. Work foreseen in the LHC #1 • BPM System • Rack cooling for surface electronics • Approved CONS • 420kCHF in 2013/2014 to be completed during LS1 • Consolidation of standard BPM system for 2023+ (RISK SCORE 8) • Existing system will be 20 years old • already low on some spare components • Need to develop new electronics to install in LS3 or shortly afterwards • Current system took 10 years from conception to installation • Cost estimated at ~6MCHF • if solution can be found to replace only electronics (i.e. no re-cabling) • Production costs needed from 2016 onwards • Not yet included in CONS or HL-LHC

  3. Work foreseen in the LHC #2 • BLM System • LHC BLM dismantling & remounting for LS1 • Approved CONS – 670kCHF in 2013/2014 • Development of rad-hard electronics • Required to move front-end closer to detector to counter noise on cables • Some detectors in LHC LSS have quench level close to noise level at 7TeV • Approved CONS – 250kCHF in 2013-2015 • LHC BLM consolidation for LS2 (RISK SCORE 8) • Replacement of threshold comparator cards • These have issues with the optical receivers, leading to spurious dumps • 2 options with first preferred by BE/BI • Complete replacement of surface electronics with new digital acquisition system • Also allows implementation of more robust firmware design • Would allow additional BLM functionality not possible with today’s system • Pre-empts replacement of these cards probably necessary in LS3 • COST estimated at 1MCHF 2014-2018 (bulk in 2015-2016) • Replace only mezzanine cards keeping existing digital acquisition cards • Whole system would still need replacement by LS3 or sometime thereafter • Would double amount of work required • Initial cost 300kCHF 2014-2015 with additional 1MCHF in 2018-2023

  4. Work foreseen in the LHC #3 • VME Fan Replacement(RISK SCORE 10) • Replacement of power supply fans (LS1) & main fans (LS2) (already underway in PH) • COST 200kCHF 2014 & 200kCHF in 2018 (only identified issue in BI this week) • Consolidation of Fast BCT System • Development of new transformers with less position dependency • Required for fast beam current change monitor & for better calibration • Approved CONS : 200kCHF in 2013-2015 • BGI System (RISK SCORE 4) • Need replacement cameras (radiation damage) • COST 200kCHF 2014-2016 • Current system only useable with ions (as designed) • for protons needs new magnet system for installation in LS2 • Estimated COST 1MCHF 2015-2018 • Decision depends on performance of new BGV monitor • Head-Tail System (RISK SCORE 6) • Important consolidation essential to fulfill requirements for understanding instabilities in the LHC • New readout acquisition system & RF front-ends • COST 400kCHF 2014 – 2016 (increase in cost & duration)

  5. Work foreseen in the PS Complex #1 • Ongoing consolidation • Wirescanner & SEM electronics completed next year • BLM electronic consolidation ongoing • This code should pass to LIU as part of wider BLM upgrade programme • Beam Current Transformer consolidation nearing completion • Additional 100kCHF required for LINAC 3 • Currently available in 2015 – would like to advance to 2014 • Mechanical Spares for Critical Injector Complex Monitors (RISK SCORE 8) • Much equipment more than 20 years old • Technical Fellow collecting information during LS1 • Identify main components & proceed to procure necessary parts • Recent example • 30+ year old PSB ceramic chamber developed leak with no spare available • Expertise to manufacture such a unit no longer at CERN • INITIAL COST 300kCHF 2014-2016

  6. Work foreseen in the PS Complex #2 • Stepping Motor Renovation(RISK SCORE 4) • Over 100 such motors installed in the injector complex • Controlled by outdated MIDI system • Only spares come from LEP & are quickly running out • Complete renovation of controller electronics proposed • COST 100kCHF in 2015 • BTV Electronics Renovation (RISK SCORE 4) • Replacement of outdated acquisition for new digital cameras • COST 300kCHF in 2015-2016 • LEIR Electron Cooler (RISK SCORE 10) • Only one spare electron gun and no spare collector • If vacuum leak develops on any of these elements then the ion run (LHC and fixed target) will be seriously compromised • COST 150kCHF in 2014-2015

  7. Work foreseen in SPS-NA • Replacement of MWPC by GEM Detectors (RISK SCORE 4) • Multi Wire Proportional Chambers require regular repair of wires • Tricky & time consuming • Not possible to make new chambers • Wire winding machines no longer operational • Gas Electron Multipliers successfully replaced MWPC in AD • GEM Prototypes to replace MPWC in SPS-NA already tested • COST 200kCHF over 2014-2016

  8. Work foreseen in the AD #1 • Requirements studied in detail & summarised in • https://edms.cern.ch/document/1159784/2 • AD Orbit System (RISK SCORE 6) • Currently has single read-out channel for all pick-ups • Read-out based on expensive , outdated network analyser • Proposal to replace with same system being developed for ELENA • COST 250kCHF in 2014-2015 • Additional 100kCHF required with respect to initial estimate • AD BCT System (RISK SCORE 6) • Refurbishment or replacement of all 4 monitors • Electronics & irradiated toroids • COST 200kCHF in 2015 • Installation of Cryogenic Current Comparator for replacement of obsolete DCCT • Allows current resolution down to the 10nA level • Collaboration with FAIR (GSI) starting • ESTIMATED COST 250kCHF 2014-2016

  9. Work foreseen in the AD #2 • AD Electron Cooler (RISK SCORE 10) • Dates from ICE  many components over 30 years old • No spares exists for the magnetic elements • Issue with toroid would put cooler out of action for a year • 2 Options: • Construct a new state of the art cooler for the ELENA era • incorporating: • adiabatic expansion of the electron beam • electrostatic deflectors in the toroid sections • new position pick-ups for the alignment of the beams • COST 2.5MCHF over 2014-2018 • Manufacture a spare of each magnetic element • gun solenoid, collector solenoid and toroid • COST 380kCHF in 2014-2015 • Option 1 preferable for BE/BI if AD to run reliably for ELENA

  10. Summary • BE/BI Requests 2014-2020+