2004-03-11 IEEE C802.20-03/40R1. IEEE 802.20 Project Development Timeline. Project Launch Process: ECSG Approval of PAR/5C September 2002 Approval of PAR/5C by LMSC Executive Committee Nov 15, 2002 Approval of PAR by IEEE-SA Board Dec 12, 2002
E N D
2004-03-11 IEEE C802.20-03/40R1
IEEE 802.20 Project Development Timeline • Project Launch Process: • ECSG Approval of PAR/5C September 2002 • Approval of PAR/5C by LMSC Executive Committee Nov 15, 2002 • Approval of PAR by IEEE-SA Board Dec 12, 2002 • Stage Setting: • Initial Membership Meeting March 10-14, 2003 • Finalize Requirements March 15-18, 2004 • Closure on Channel Models March/May 2004 • Closure on Evaluation Criteria May 2004 • Establishment of 802.20 Organizational Substructure May 2004 • Specification development • Call for Proposals May 2004 • Presentation of proposals and simulation results July/September 2004 • First WG Ballot Jan 2005/March 2005 • Second WG Ballot May2005/July 2005 • Sponsor Ballot Sept 2005/Nov 2005 • Sponsor Recirc Nov2005/Jan 2006 • IEEE-SA Approval Jan2006/March 2006 Optimistic Target DateLess optimistic target date
802.20 Proposed Standards Development Timeline MAY JUL SEP NOV JAN JUL MAR MAR JAN MAY MAR JAN SEP NOV Requirements Call for Proposals Proposal Submittals and Evaluation Channel Models Further Evaluations and Draft Preparation Evaluation Criteria 1st WG Ballot Structuring for Progress Comment Resolution 2nd WG Ballot Comment Resolution/Slip Margin Sponsor Ballot Comment Resolution IEEE-SA Approval