Spending money, saving money A4 section Zgorzelec – Krzyżowa business case Monika Milwicz

Spending money, saving money A4 section Zgorzelec – Krzyżowa business case Monika Milwicz EU Projects Department. Goals of motorway construction. Goals of motorway construction: Cohesion of European TENT networ k (all motorways in Poland are part of TENT) Shorter travel times

kale
Download Presentation

Spending money, saving money A4 section Zgorzelec – Krzyżowa business case Monika Milwicz

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Spending money, saving money A4 section Zgorzelec – Krzyżowa business case Monika Milwicz EU Projects Department

  2. Goals of motorway construction • Goals of motorway construction: • Cohesion of European TENT network (all motorways in Poland are part of TENT) • Shorter travel times • Improved road safty

  3. A4 Motorway Basic information on A4 Motorway: Part of 3rd TENT corridor Part of E40; Ostenda (Brusselss_ - Aachen – Koln – Dresden – Wrocław – Kraków - Kijev

  4. A4 Motorway; section Zgorzelec - Krzyżowa • Basic information on A4 Motorway; section Zgorzelec – Krzyżowa: • Length – 51,4 km • Number of motorway junctions – 4 • Designed speed – 120km/h • Cement concrete pavement • Number of carriageways – 2 • Number of traffic lanes – 2x2 (target 2x3) • Maximum axle load – 115kN

  5. Short history of construction section Zgorzelec - Krzyżowa The history of A4 section Zgorzelec - Krzyżowa construction: 1930s – Preliminary design and preparation work. (earth works for German Wrocław – Dresden motorway still exist) 1997 – Preliminary design completed 1998 – Administrative decisions on the motorway route 2005 – Final administrative decision on the motorway route 2007 – Environmental impact study approval 2007 – Construction permit 2007 – 2009 Construction 14/08/2009 Grand opening

  6. Project 2 projects implemented with EU co-financing 2002/PL/16/P/PA/007 Development of the project: Construction of A4 motorway; section Zgorzelec – Krzyżowa Project budget according to the Financing Memorandum: 6 625 000 EURO Cohesion Fund contribution: 4 968 750 EURO 2004/PL/16/P/PT/004 Construction of Ar motorway; section Zgorzelec – Krzyżowa Project budget according to the Financing Memorandum: 317 567 000 Euro Cohesion Fund contribution: 252 040 940 EURO

  7. Costs • Project costs • Study and analyses - 8 000 000 EURO • Land acquisition – 6 500 000 EURO • Works – 334 000 000 EURO • Management and supervision – 6 000 000 EURO • TOTAL: 354 000 000 EURO

  8. Costs • Economical costs • Traffic jam on the existing national road number 4 (DK 4) • Accidents (only in 2006 – 2008 there were 100 accidents with 27 killed and 124 injured)

  9. Benefits • Project benefits according to the feasibility study: • Savings in vehicle operating costs • Savings of time • Savings due to lower accident frequency • Management and supervision

  10. Benefits Results of economic analyse: Pessimistic scenario: NPV – 452.000.000,00 EURO (8%) IRR- 22,4% Optimistic scenario: NPV – 1.196.000.000,00 EURO (8%) IRR – 39,3%

  11. Verified Benefits • Benefits of the new motorway construction 17 500 000 EURO per year • The economic benefits include: • savings on fuel and vehicle maintenance – 5 700 000 EURO • savings on time of freeway users – 9 100 000 EURO • savings on traffic accidents costs – 400 000 EURO • cost on emissions + 100 000 EURO

  12. Spending money – Saving money • Spending money: • Bad menagement argument by the Cmmision: • - cost over-runs on the PA/007 project preparation around 800 000 EURO • - cost over-runs on the PT/004 (construction of motorwa) around 30 000 000 EURO • Saving money: • (and time) • 17 500 000 EURO per year – total economical savings • shorten time of journey – to 30 minute-drive

  13. Thank you