An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mezzanine Floor

  2. Mezzanine Floor Components Steel square hollow section 250 x 250 C channel bottom plate, 150 x 200 Floor Joists 90 x 200 @ 600 centres

  3. Mezzanine Floor Details: Special connection: Floor joist bolted and then welded to 250 x 250 hollow section. Floor Joist Connection: Plate inserted and bolted with M20 bolts. Welded to then increase rigidness. Bottom Plate Connection: Cut at a 45* angle, plate inserted and bolted temporarily and welded to complete connection.

  4. Detail To Canter lever:

  5. Canter lever Components: Cantilevered section of mezzanine floor is lined with insulation as this will be a very thermal conductive area of the mezzanine building. Outer cladding of building is fixed to C section studs of inner of building; see next slide.

  6. Fixing Of Cladding: C section studs are cut to align with top plate of the first floor building and are welded into place. Note all c sections face the same direction. Galvanised steel panels are fixed to the C section studs with metal screws and are sealed with a poly-urethane sealant at the junction of sheets. Insulation is also placed in-between the studs. Plasterboard lines the inside of the studded wall. The steel panel fixing is shown in the external wall frame detailing.

  7. Order Of Construction: 1: Fix all steel hollow sections into position and fix at ground level. 2: Fix steel C columns onto steel hollow sections. 3: Fix floor joists to C sections.

  8. 4: Fix into position studs directly under mezzanine floor. (Other studs are fixed into position at stage 3) 5: Fix Galvanised steel panels to each other and studs. Seal the gaps with waterproof ‘mastic’ sealant. 6: Once the mezzanine frame has been assembled, line the inside with tongue and groove floor boards on top of wooden battens 45 x 45. Secret nail and glue to adhere to the timber battens.

  9. Demonstrated Application: Show to the left is a picture taken from the Wool stores building, located in Deakin university, Geelong. Shown is a CAD 3D represented model of the actual application as shown on the left. The represented model shows similar a similar method of cladding with a similar fixing technique as explained earlier. This building can be found along Gheringhap St Geelong. Source: http://www.ab.deakin.edu.au/dotcp-submission/vgallery/project%202/leonard_j_project2/default.htm