1 / 6

June 8, 2011

Report on 7800 S. Finished Water Pipeline Phase III – 2700 W. to Bangerter. June 8, 2011. 7800 S. Phase III. Engineer: CH2M HILL Inc. Contractor: UDOT/Condie Construction Contract Award Date: November 12, 2008

Download Presentation

June 8, 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Report on 7800 S. Finished Water Pipeline Phase III – 2700 W. to Bangerter June 8, 2011

  2. 7800 S. Phase III Engineer: CH2M HILL Inc. Contractor: UDOT/Condie Construction Contract Award Date: November 12, 2008 Project Scope: Installation of 24-inch and 30-inch pipeline from 2700 West to Bangerter Highway and new vault at 3200 West.

  3. 7800 S. Phase III Change Order #3: $225,640 Change in depth of the bore underneath Bangerter Highway due to conflicting utilities. Change Order #4: $2,088 Additional potholing at Bangerter Highway. Change Order #7: $3,175 Changes to the connection to the existing pipe at 2700 West. Change Order #12: $7,014 Changes in the pressure rating of the pipe in the 3200 West vault and deletion of the interconnection to the old 16-inch pipe. Change Order #17: $61,811 Project Acceleration Costs. Change Order #20 $0 Changes to the Pipe Coating Specification

  4. 7800 S. Phase III Change Order #23: $22,626 Utility conflicts on the 24-inch and 30-inch pipeline and changes to the vault at 3200 West. Change Order #24: $58,825 Delay claims, traffic control credit, Bangerter jack and bore standby costs and liquidated damages.

  5. 7800 S. Phase III Jack and bore underneath Bangerter Highway 24-inch pipe being installed in 7800 S.

  6. 7800 S. Phase III 3200 West Vault under construction Final piece of 30-inch pipe being installed

More Related