An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Test Monitoring CenterReport to the Mack Test Surveillance Panel October 23, 2003 Paulsboro, NJ

  2. Reference Oil Testing Summary • Test Activity • All Mack tests (T-8, T-9, T-10, and T-11) • Low • Semi-Annual summaries of recent activity are available from the TMC • Please let me know if you would like to be added to the distribution list

  3. T-11 Industry Charts – Soot at 12 cSt

  4. T-11 Industry Charts – MRV

  5. Liner Measurement Round Robin • All eight instruments (five labs) successfully calibrated through all three 2003 round robin • Fall ’03 round robin is in progress and will complete by end of year

  6. Liner Measurement Round Robin Results

  7. T-10 Intake Manifold Pressure • Min, Max, and Average of all tests

  8. T-10 Intake Manifold Pressure • Proposed Options • 1. Ranged parameter • Stage 1: 160 – 200 kPa • Stage 2: 210 – 250 kPa • 2. Minimum spec • Stage 1: 160 kPa • Stage 2: 210 kPa • 3. No spec

  9. T-11 O & H Issues • Intake Manifold Pressure Spec • Possibly develop in manner similar to the T-10 • Submit data to TMC • TMC to distribute to group with a proposal • Target resolution at December meeting or conference call

  10. T-11 O & H Issues • Oil Flush Injection Timing • What are labs currently running? • Should we specify?

  11. T-11 O & H Issues • Humidity Measurements • Measurement locations and sensors differ from lab to lab • Does it make sense to measure unless it is at the intake manifold?

  12. T-11 O & H Issues • Fuel pressure / pressure regulator • Pressure of 70 psi nominal (~480 kPa) • Regulator: 691GC227M2 • Should we • Include regulator p/n in procedure? • Report fuel pressure? • If so, should we put a spec on fuel pressure?