1 / 12

Report from Technical Coordination

Report from Technical Coordination. Muon System Magnet status Tracking chamber status ITS Issues Pixels Drift Strips TPC Field Cage Electronics. Muon Magnet. Coils Finished Nice celebration at Nantes Fine example of Technology Transfer CERN-Industry Yoke

kana
Download Presentation

Report from Technical Coordination

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Report from Technical Coordination • Muon System • Magnet status • Tracking chamber status • ITS Issues • Pixels • Drift • Strips • TPC • Field Cage • Electronics C.W.Fabjan

  2. Muon Magnet • Coils • Finished • Nice celebration at Nantes • Fine example of Technology Transfer CERN-Industry • Yoke • Finally with a further three week delay ( compared to last contract) railroad cars are being loaded • We have lost unfortunately 8 months total due to these…(do not know word for it…) C.W.Fabjan

  3. C.W.Fabjan

  4. Status of Tracking Chambers • Chambers of Station 1,2 • Station 1 : redesigned; 1st quadrant available end Oct. • Station 2: Kalkotta group to start testing end Oct ’03 • Chambers of Station 3,4,5 • The four production sites (Cagliari, Gatchina, Nantes, Saclay) on track for start of production from Oct, Nov ’03 onwards • Tracking Electronics • Indian flavor of Gassiplex (‘MANAS’) requires channel-by-channel calibration (also done in other systems : HMPID,ALTRO) • Procedure under development by Orsay; needs resolve before MANAS production can be launched • Tracking electronics is large and complex system; personally I believe that this is on the critical path and not enough personnel involved in the R/O system C.W.Fabjan

  5. ITS Issues • Pixels • Order for final production for FEE chip being issued (waited for HAL25 success; see later) • Order for bump bonding being prepared • (expect no further delays from other clients) • Bari (half stave assembly) basically ready • Padua (ladder production basically ready • Catania ( wafer probing) needs final push… • Critical ( as ever): • Pixel bus production • MCM production C.W.Fabjan

  6. ITS Issues • Drift • Very successful test with complete and final readout chain during 8/03 • Production of sensors still under study: • 2 * 25 sensors in production; to be evaluated 12/03 • Series production could start 2/04 • Preparing for engineering run of FEE (10/03) • 1st module for production qualification : 12/03 C.W.Fabjan

  7. ITS Issues • Strips • HAL25 : finally…90 % yield in engineering run ! • ( also good news for pixels, drift and many other ….) • Helsinki and Strasbourg have produced 3*2 modules → production sites certified • Production to start (incl.3rd Italian site) in Oct/Nov • Beam test ongoing; globally progressing well; certain differences in performance seen between Canberra and ITS sensors; Canberra sensors used to perform well, but now barely acceptable; obviously needs study • CRITICAL : • Mass production of Al/Kapton cables in Ukrainian industry C.W.Fabjan

  8. HAL25 V4 engineering runWafer 1: yield=89.6% Wafer 2: yield=92.6% C.W.Fabjan

  9. TPC Field Cage Status • Inner Field Cage • Re-manufactured; load-,leak-tested : OK • Rod Production (supporting potential strips + other…) • Standard rods (54) : finished • ‘laser’ rods (12): in production;finished:15/11 • HV rods: in production • Resistor rods (exchangeable and water-cooled): • Prototype under HV test • 1st final RR rod :15/11 C.W.Fabjan

  10. TPC Field Cage Status • Assembly of all four cylinders: • Sept. to Nov. 03 • Central Membrane manufactured,installed:12/03 • Potential strips • Jan. 04 to April 04 • Final tests • May-June 04 • Aggressive schedule, aimed to recover time • Consistent with work and personnel, but bad surprises not scheduled C.W.Fabjan

  11. TPC Electronics • PASA: • Samples from Engineering run received; tested • Results to specification; no modification needed • Final production launched; all wafers available by end ‘03 • ALTRO Testing: • Progressing well; more than 20% tested; • Test infrastructure ( robot,..) will be used for PASA testing • RCU: • Final unit in production; will be available by Oct. 10th Tests to follow C.W.Fabjan

  12. Summary • Infrastructure • Due to muon yoke delay 6 month shift in certain integration tasks: program until mid-05 still possible, but no contingency left (most recent issue: procurement of Muon Filter in Russia via Gatchina) • Installation of services proceeding in timely way • Detector systems • ITS; without contingency • TPC: Fieldcage, R/O chambers, electronics advancing correctly • Muons : electronics, cooling require full attention • Updated production schedules: CRIV • From IRII to IRIII • Full attention to commissioning issues, cable installation C.W.Fabjan

More Related