An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Shackleton Crater Reconnaissance Mission PDR Trevor Fedie Jason Breeggemann Brian Evans Mike Gavanda Matt Gildner Jeromie Hamann Brian Nackerud Andrew Smude Jordan Stewart

  2. Project Overview • Image 5 km annular region around Shackleton Crater (at Moon’s south pole) • 3 color imagery • 10 cm resolution • Image 80% of region in one month • Act as communication relay for lunar lander exploring interior of crater • 2.5 Mbps S-band from lander • Transmit to Earth once per day

  3. Project Overview • Baseline orbit of 30 x 216 km • Period approximately 120 minutes • 12 orbits each day • Spacecraft must fit into Taurus Launch Vehicle • Goal of 445 kg for everyday launch opportunities • Must handle spin stabilized upper stage (60 rpm) • Must interface with launch vehicle upper stage • Must fit into launch vehicle envelope

  4. Mission Profile • Launch using Taurus Launch Vehicle • De-spin, make burn for Earth-Moon transit • Burn to enter Lunar orbit • Begin imaging region around crater • Send data back to Earth once per day • Finish imaging crater in about 14 days • Lunar lander operations begin 4 months after launch and last for one year

  5. Spacecraft Data Flow Star Tracker Reaction Wheels Flight Computer Gyroscope Rocket Motor SSR Thrusters Transponders Camera Antennas Temp Sensors

  6. Camera Crater Imaging Strategy (Note: not to scale)

  7. Camera • HiRISE (used on Mars Reconnaissance Orbiter) • Pushbroom TDI imager (4,048 pixels across swath) • 0.5 m aperture • 28 Gbits internal data storage • Internal LUT image compression • Mass: 65 kg • Average power: 60 W

  8. Computing & Data Storage 3U Compact PCI PowerPC RAD750 Enhanced Power PCI Bridge SSR P9 family 160 Gbits BOL Built-in FELICS 256 Mb SDRAM

  9. Communications • Earth Comm. • Cassegrain Antenna • D=.98m • d=0.3m • Power usage 40 W • Double reflection

  10. Earth Communications Transmit high resolution photos Only one contact with White Sands per day Around 90 Gbits a day in pictures Ka-band 26 Ghz parabolic dish Data rate:100 Mbps Power: 40 W Gain: 44 db White Sands receiving: 45 db/T Similar to LRO

  11. Rover Communications • Relay for rover in crater • Required data rate of 2.5 Mbs • Required S-band from rover • 2.3 Ghz Omni-directional transmitter • Power: 5 W • Gain: 5 db • Rover Gain: 5 db • L3 T&C transceiver MSX-765 • Store Data onboard satellite until downlink to White Sands ground Station

  12. Communications • Earth • 4230 sec average daily window • Tracking • Azimuth: 0.01617 deg/s • Elevation: 0.0154 deg/s • Moon • 12 communication windows • 6.533 min over crater • 117.6 Gbits of data a day • 2 min required to send to earth

  13. Attitude Determination and Control • Pointing stability/accuracy • Torque disturbances must result in 10 cm or less ground displacements during exposure time • Attitude accuracy -Roll axis <2.5 arcmin -Pitch axis <8.6 arcmin -Yaw axis <2.7 arcmin • Maneuverability • 3-axis control • Pointing reassignment as fast as 90 deg in 6 minutes

  14. Attitude Determination and Control • SED 16 Autonomous Star Tracker by Sodern • 36 arcsec in pitch/yaw, 108 arcsec roll (bias plus noise) • 10 Hz update • 25x25 deg field of view • Mass: 2.9 kg (with Baffle) • Average power: 10.7 W

  15. Attitude Determination and Control • Scalable SIRU (gyro) by Northrop Grumman • Achieves Gyro Bias stability of 0.0003 deg/hr • Four HRGs (Hemispherical Resonator Gyro), with associated loop control/readout/thermal control electronics, and sensing along the octahedral-tetrad axes • Low noise • Mass: 7.1 kg • Average power: 38 W

  16. Attitude Determination and Control • Momentum build up •Disturbance Torques - Gravity gradients - Solar pressure - Internal - Deployables •Slewing Maneuvers - Minimum twice a day • HR14 Constellation Series Reaction Wheels by Honeywell • Max Reaction Torque 0.2 N-m • Momentum Capacity 50 N-m-s • Mass: 8.5 kg

  17. Propulsion System Rocket Motor: -EADS Astrium S400-12 -MMH/MON-1 -420N Isp:318s -Total V needed: 1011m/s

  18. Propulsion System • Twelve 4N thrusters • MMH/MON-1 Fuel/Oxidizer • EADS Astrium S4 • Two 0.05 cubic meter tanks • Composite structure • 3600 psi rated • Lincoln Composites

  19. Determination of Thermal Environment • Moon surface temp • Altitude and attitude • Lunar view factor • Intense reflected IR from lunar surface. • Thus objects placement will important • If thermo enviroment is compromised anywhere and active system will be used

  20. Thermal Analysis • Equilibrium temperature range of 270-310 Kelvin • Electric heaters and sensors on items that do not fall within their ideal ranges. • Use of heat tubes and radiators if needed • Will be tuned in by a dynamic model

  21. Structural System Determination • Properties of Ti an Al • Bulk system of TI. • AL only used where conduction requires it. • Current structural mass of approximately 18Kg. • Titanium will also have less thermal expansion

  22. Radiation Protection Everything placed into space must be protected in some way from cosmic radiation. Typical commercial satellites protected to 2Mrad for a 10 year mission and SF of 2. Our mission is shorter. Everything will be shielded to 1Mrad, unless otherwise required by specific components. 3g/cm2 of Al will provide an order of magnitude reduction in total dosage over a 10 year mission: this is sufficient to reduce total dosage to less than 1 Mrad. Sensitive components shall be organized as to benefit from spot-shielding. This layout must also mesh with the thermal management system.

  23. Radiation Protection Reduction in Exposure when utilizing Al shielding *Courtesy of http://see.msfc.nasa.gov/ire/iretech.htm

  24. Power • Requirements • Supply power to satellite • Support mission profile and requirements • Major Design Drivers • Must fit inside Taurus launch vehicle • Provide adequate power • Reliable and easy to obtain

  25. Power • Trade Studies • Solar Power vs. RTG vs. Nuclear Reactor • Silicon vs. GaAs solar cells • Body Mounted Array vs. Gimbaled Array Panels

  26. Power Triple Junction GaAs Solar Cells 28.5% average efficiency 26.6 square cm Radiation Resistant 289 Watts per square meter Secondary Batteries Peak Power Trackers Active power regulation Protects sensitive electrical components

  27. Power SolarArray Battery PeakPowerTracker ChargeController DischargeController 28V Bus Loads

  28. Power - Battery • Lithium Ion • Highest number of Cycles for chosen depth of discharge (DOD) • High energy density • Customizable size and shape

  29. Satellite Structure - Transport Fitting within the Taurus launch vehicle

  30. Satellite Structure - Functional

  31. Rest of Semester • Detailed end-to-end data flow from lander and camera back to Earth including timeline, data rates, use of on-board storage, and contact times • Optimize power system for our mission/components • Detailed design of spacecraft structure and thermal conduction/radiation model • Integrate radiation protection with components and structure

  32. Questions?