An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Layer 0 Status • 48 modules, 96 SVX4 readout chips 6-fold symmetry • 8 module types different in sensor and analog cable length

  2. Analog cable Pitch Adapter SVX4 sensor hybrid L0 Status • Layer 0 consists of: • 48 sensor/analog cable/readout modules of 8 types • 7 and 12 cm sensors • x 4 analog cable lengths • SVX4 readout chips, BeO hybrids • Digital jumper cables • Carbon Fiber Support structure • Readout Components • Junction cards/twisted pair cables/adapter cards • Installation components • Supports attached to the Run2a SMT structure • Tooling to install and align Layer 0 and extract the Run2a beampipe

  3. Module Quality • All modules are built • 8 of each type (6 needed) • Require: • <1.5 mA current • no pinholes • <4 bad or noisy channels • Have one good spare for each type (one marginal)

  4. Component Status • Modules – done • Digital jumper cables – done (spares still being assembled at KU) • Carbon Fiber Support structure – done • Readout Components • Junction cards – done • Twisted pair cables – done • Adapter cards – done • Installation components being fabricated • Supports attached to the Run2a SMT structure • Tooling to install and align Layer 0 and extract the Run2a beampipe

  5. Module Installation • 48 to install, started June 2 • Problems with the stability of the CMM slowed the start • Two sets of fixtures. Plan to install two modules/day (north+south). Procedure • Remove vacuum, electrical test of previously installed modules • Glue on foam spacers • Measure locations of previously installed sensors • Glue on next sensor/hybrid pairs • Allow to cure overnight • Scheduled for 6 weeks • Six facets (3 inner, 3 outer) • Stop after inner layer is complete for ~2 week electrical test • Assumes 1 additional day/facet for rotation and alignment

  6. Module Installation

  7. System Tests and Grounding • Layer 0 performance depends on the grounding scheme developed for Run2b • Carbon fiber cocured with kapton ground mesh • Low inductance connections to sensors and hybrids • Isolation of adapter card grounds to break ground loops • Minimum gap between analog cables and conductors (mesh spacers) • A series of system tests have been performed with pre-production modules beginning last fall. • Used mechanical prototype support structure (electrically good) • Installed 10 modules (in stages). • Good overall noise performance • Effects of digital signals on hybrid coupling to analog cable (negligible at 396ns bandwidth) • Pedestal splitting (also negligible at 396ns bandwidth) • Verified need for low impedance grounding • Checked that there is no effect of adding modules on adjacent facets, opposite ends • Tested effect of a signal generator on CF support

  8. Full System Tests Two parallel efforts: • Full system test at Sidet • Plan to read out full Layer 0 withfinal electronics. • 10 electrical modules already read out • First stage inner layer only end of June • Found timing problems – addressed by sequencer firmware changes • Hybrid strings installed at Dzero, test crate 79 • Testing with conditions similar to operations Use real DAQ with Trigger Framework • Preparation and exercising of online software • See similar timing problems which still need to be addressed • Test crate progress slow – have now resolved interference with normal data taking – should make faster progress ungrounded

  9. Dzero Installation Tooling Layer 0 is installed by bringing the detector in through the EC beam pipe, a carbon fiber installation pole is passed through the SMT, picks up Layer 0 and guides it through the SMT. • Carbon fiber insertion tools • Half of “long tool” built, second, tapered half should take ~2 weeks • Stages and support tables designed, stages have been received • Alignment and coupling tooling • Reuse parts used for aperture survey last Fall • Junction card support being fabricated • Layer 0 to SMT couplings partially fabricated, some redesign to provide more compliance in supports • Need to fabricate Layer 0 to insertion tool coupling sections • Expect to begin Lab 3 tests in the beginning of July

  10. Installation Sequence Long tool inserted Through SMT Layer 0 connected to tool L0 partially inserted in SMT Layer 0 in installed position

  11. Cabling DJ cables in installedposition DJ cables in insertion position Twisted pair cables(not shown) Run 2a Support Junction Cards (12/side)

  12. Cabling • Preparation • Decable and remove H disks • Remove outer H disk low mass cables • Install adapter cards, LV wire gauge transitions, temperature monitor interface cards on horseshoe • Installation • Connect DJCs to junction card/twisted pair assembly and secure to junction card ring • Test readout • Connect 12 temperature monitor cables • Insert and recable inner H disks 4 ch. Adapter Card at HorseShoe

  13. Schedule Summary

  14. Schedule (April 05 update) Milestones we are watching: • Begin module installation (June 2) • Completion of inner layer (June 21) Two weeks of testing • Completion of module installation (July 27) Four weeks of testing Complete and ready to move (Sept 16) • D0 Installation • Test fixtures at Lab 3 (June 20-July 20) • Modify and complete (July 21-Aug 30) Ready for mechanical installation Aug 30 We assume that Layer 0 needs to be available at the start of the shutdown