Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee. Mike Neitzey, Program Manager Department of Information Technology August 28, 2013. Project History. SIRCITS grant was awarded in August 2010
E N D
Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to theProject Certification Committee Mike Neitzey, Program Manager Department of Information Technology August 28, 2013
Project History • SIRCITS grant was awarded in August 2010 • Received approval to add 9 sites to the DMW project September 2011 • Contracts issued, began design phase November 2011 • Environmental Assessment FONSI issued December 2011 • Contract amendments for construction executed April 2012 • LTE suspended May 2012 • FirstNet Board established September 2012 • Extension request submitted May 2013 • Received an extension to September 30, 2013 to negotiate a Spectrum Management Lease Agreement (SMLA) with First Net • Signed the SMLA on August xx, 2013 • Submitted a request to extend the project to 2015 (final date to be determined, but no later than September 30th) • Submitted a letter requesting that the suspension of funds be lifted in order to complete the 700MHz LTE phase of the project
Budget Status • Budget allocated • Total - $55,700,000 • Federal BTOP - $38,699,997 • State Matching - $5,399,999 • State In-Kind Matching $11,600,004 • Budget status • Budget amendment moving $4,734,501 from LTE to DMW was approved • Total LTE Budget - $4,006,500 • LTE equipment and build - $2,952,500 (suspended) • Design - $1,054,000 (suspended) • New fund established due to expiration of the Budget Reference Code, new PO’s have been/are being approved
Budget Status • Budget expenditures for quarter ending 06/30/2013 $3,442,398 • Budget expended • As of 06/30/13 - $32,807,381 (cash) + $11,600,004 (in kind match) Total $44,407,385 • Over $3,321,627 spent on design, planning, equipment, and construction during the quarter
Budget Status • What have we done? • Towers 2,376,245 • Shelters 2,037,912 • Generators 527,856 • Network 4,792,240 • Antennas 3,403,700 • Radios 5,218,878 • Batteries 1,161,284 • Construction 7,090,686
DMW Status • Design - Feasibility analysis, RF design, and Construction design were completed for all Sites • Construction – • Completed at 24 sites, • nearly completed at 3 sites and • soon to start at 2 sites • Radios, antennas, waveguides and routers have been installed at over 60 sites • Over 900 network miles are in production • Installation & implementation are expected to be completed by the end of Q4CY13
LTE Status • LTE Border Operations Project • Briefed to FirstNet in December 2012 • Up to 7 State sites and 2 Federal sites to be established (final selection will be based on Spectrum Analysis results, System Requirements, and System Design • Use State DMW and Fiber backhaul • Establish MOUs with Federal agencies • Establish MOU with Texas to connect to Harris County LTE core
LTE Status • SMLA with FirstNet has been signed • Suspension lift and project extension requests have been submitted • Starting to develop MOUs with Federal agencies and Texas
LTE Plan • Design contract 10/01/13-01/17/14 • System Design 01/20/14-04/11/14 • 700MHz LTE RFP 03/24/14-08/08/14 • Build & Implementation • Contract 08/11/14-10/14/14 • B&I process 11/12/14-03/03/15 • System Integration Test 03/04/15-08/18/15 • Operational turnover 08/19/15-09/30/15
Risk & Issues • Weather and Fire restrictions continue to play a role in upgrade delays, but has been minimal at this time • USFS Santa Fe insurance requirements has delayed the permitting process on 2 sites • Demolition is now included as part of budget; Priority for State Land Office and BLM sites • No funding for • Purchase/move of LMR equipment (separate $1.5M funding)